Professional Documents
Culture Documents
Expensive fix
Southwest Ohio from
flooding, preserves the
quality and quantity of
water, and promotes
Potential underseepage at levees
the enjoyment of our Miami Conservancy District levees have “We’re working to determine how many miles
waterways. withstood every storm event since their of levee will need improvements,” says Janet
construction nearly 90 years ago. But an Bly, MCD general manager. “The analysis is
extensive engineering analysis has revealed a under way in Butler, Warren, and Miami counties
potential vulnerability with the foundation of but hasn’t yet begun in Montgomery County.
the levees. Since the foundations all have similar geology,
it’s likely there could be problem areas in
MCD is doing the engineering analysis to
each county.”
comply with the Federal Emergency Management
Agency’s (FEMA) effort to update flood Unfortunately, if a levee section doesn’t meet
insurance rate maps nationwide. For levees to every single requirement, FEMA will deaccredit
be shown on the new maps as offering protection, that levee section. This means cities will have
the levees must protect to the 100-year flood to enforce floodplain regulations regarding
(a storm event that has a 1-percent chance of development, and many homeowners will be
occurring in any given year). required to purchase flood insurance. Flood
insurance is available to virtually everyone but
“There are eight different requirements that each
Workers drill deep into currently is optional. (More information on
the levee to retrieve soil levee section must pass, “says Kurt Rinehart,
flood insurance)
samples for analysis. MCD chief engineer. “After extensive studies in
Butler and Warren counties where FEMA began “It’s important to note that if a levee section is
the process locally, MCD levees have exceeded deaccredited, that doesn’t mean the levee will
most of the standards. One area of concern is fail,” Bly says. “The probability of a storm
foundation stability or underseepage.” large enough to put this kind of pressure on the
levees remains small, and the risk of piping is
Underseepage is water that seeps through a
even smaller. Plus, there are flood-fighting steps
dam or levee foundation. Water flowing under
that can be taken to further reduce the risk of
pressure through the foundation soils can cause
levee failure. And remember, these levees have
soil particles to move, creating voids in the
withstood every storm since 1922.”
foundation which in turn allow more water to
flow. This situation is called piping because the The process
flow creates a “pipe” in the foundation and can More than 18 miles of levee have been evaluated
lead to instability and potential levee failure. in Butler and Warren counties, and another
Science was not advanced enough to know 7.5 miles of levee in Miami County are under
about the effects of underseepage when the review. FEMA provides only a two-year window
MCD dams and levees were built. MCD has to complete the extensive review and submit
addressed underseepage at three of its five dams the report including detailed data, drawings and
and expects to finish capital improvements at analyses for each levee section.
Englewood and Lockington dams by next year.
Underseepage story continued on page 8.
2
Protecting
“The concrete below the
waterline is in excellent
Dam Safety Initiative
In 1999, MCD began a multi-year Dam Safety At Englewood Dam, MCD installed additional
shape,” says Kurt Rinehart, Initiative (DSI) capital improvement plan to ensure relief wells in 2009. A weighted toe berm and toe
MCD chief engineer, “but the integrity of the dams for future generations. drains will complete the underseepage control.
The schedule was aggressive and the costs
there are problems above were conservative. Concrete repairs needed at the dams
the waterline—a result of The plans called for addressing underseepage— As part of the DSI, MCD completed a thorough
water that seeps through a dam’s foundation inspection of the concrete at Lockington Dam. In
freezing and thawing over and can lead to dam failure—at all five dams by 2009, MCD hired a contractor to dewater the dam’s
constructing projects along the downstream toes east conduit to inspect the concrete.
the years.” of the dams.
The plans also included modifying the crest at three The dam’s concrete was visually inspected for
dams by constructing impermeable cut-off walls to cracking and spalling (surface pieces falling off),
prevent stored flood waters from seeping through and the entire surface was mapped. In addition,
Workers inspect concrete in the embankments. In addition, major repairs workers drilled into the concrete, taking samples to
the dewatered stilling basin would be made to concrete at the dams. Concrete be analyzed at a lab.
at Lockington Dam. floodwalls and revetment would be replaced at
MCD last inspected the concrete in the 1970s and
several locations.
subsequently performed repairs to the concrete.
By the end of 2009, MCD had: The 2009 inspection showed a good news/bad
news scenario.
n Addressed underseepage at three of the five dams
(Germantown, Taylorsville and Huffman) using “The concrete below the waterline is in excellent
combinations of relief wells, weighted toe berms shape,” says Kurt Rinehart, MCD chief engineer,
and toe drains. “but there are problems above the waterline—a
result of freezing and thawing over the years.”
n Completed relief well projects at the other
two dams (Englewood and Lockington) along with Despite needing repair, there is no immediate
a weighted toe berm and toe drain project threat to the dam. The deterioration, however, will
at Lockington Dam. continue if not repaired. Repairs to Lockington
Dam concrete will be more extensive than in the
n Completed crest walls at Huffman, Taylorsville past, with some repair work as deep as 2 feet into
and Englewood dams. MCD completed crest the spillway walls. The total estimated cost for
remediation projects at Germantown and repairs to Lockington Dam concrete is about
Lockington dams before the DSI in 1970 and 1993, $10 million.
respectively.
“Given that the concrete at the dams is about 90
n Repaired concrete revetment and floodwalls years old, it has held up very well,” Rinehart says,
in Troy, Dayton, and Hamilton. “but like bridges and roads and other concrete
n Completed concrete inspection at Lockington structures, repairs are necessary and can be
Dam. expensive.”
Although MCD hasn’t inspected the concrete at the
Final underseepage projects other four dams, it anticipates similar findings at
The geology at Lockington Dam is more complex each. MCD will add the concrete repair projects at
than at the other four dams. The dam’s foundation the dams to its list of capital improvement projects
sits on fractured limestone bedrock. The unique that will be needed in the coming years.
geology required more testing—and creativity—
to determine a solution to control the underseepage.
While relief wells and weighted toe berms have
been installed to help address the problem, grouting
of four large areas in the foundation east and west
of the spillway also is necessary. Grouting is
expected to start in 2010.
3
Floodwall exercise
average each year. federal sources
n None of the 13 storage events had more than n Revising equipment
two dams storing floodwaters at any one time. replacement schedules to
Practice makes perfect delay equipment purchases
n Huffman Dam did not have any storage events
in 2009—the first time that’s happened in 19 years. It would take a massive storm—even larger than n Using seasonal staff in place
the 1913 flood—for the river in downtown Dayton of full-time staff when
The largest event of 2009 took place February 8- to rise high enough to flow through the open possible
12, resulting in total peak storage of 10,955 acre- levee at RiverScape. Still, MCD prepares for
feet (3.6 billion gallons). The high water event was all possibilities.
triggered by melting snow on February 8 and 9,
followed by 0.7 to 1.2 inches of rain falling within That’s why staff members from MCD, the City of
the Great Miami River Watershed on February 10, Dayton and Five Rivers MetroParks installed a Flood Protection Revenues
11, and 12. The heaviest rainfall occurred north floodwall at the RiverScape plaza last fall as part of (2009 Actual)
of Dayton in Darke, Miami, Logan, and Shelby a flood protection exercise.
counties. n Assessments ($4,422,356)
“When RiverScape was developed, a portion of the
n Intergovernmental ($135,202)
“From a financial standpoint the lack of high- levee was removed,” says Kurt Rinehart, MCD chief
engineer. “The floodwall provides protection for n Other ($120,348)
water events was beneficial in that we didn’t have
a lot of costs in overtime,” says Janet Bly, MCD that section of the levee should the water ever get n Fees & Charges ($107,276)
general manager. “In this economy, every little bit that high. Every few years, we work with the City n Interest ($38,348)
of savings helps.” of Dayton and MetroParks to practice installing
the floodwall to keep everyone current on the
procedure.”
To install the floodwall, caps are removed from the
plaza floor area and posts put into the openings.
A backhoe is used to install sections of aluminum
stoplogs. The main floodwall is about 3 or 4 feet
high and about 160 feet wide with another smaller
opening—about 30 feet wide—west of the plaza.
The installation takes about three hours.
Preserving
Take-back program keeps drugs out of water supply
Promoting
The new hand-carried-boat ramp just above the Ohio 73 bridge over the Great Miami River
8
Conservancy Court
A message from the general manager
MCD is governed by a
Levee accreditation process creates challenges
Conservancy Court comprised
of one common pleas court judge The Miami Conservancy District (MCD) has Underseepage story continued from page 1
from each of the counties within been a long–time advocate of robust flood Levee accreditation does not guarantee the levee
the Conservancy District bound- protection infrastructure to ensure public safety or its performance, it simply is an indicator of
aries. The Conservancy Court and economic prosperity. MCD supports the
appoints MCD’s Board of compliance with certain FEMA requirements.
FEMA Map Modernization program to update
Directors and Board of Appraisers, Addressing underseepage to meet FEMA
and approves their plans. flood maps and accurately identify flooding risks
across the country. However, MCD—like many standards could require millions – or tens of
communities nationwide—faces challenges in millions – of dollars in capital improvements.
Butler County Even more extensive improvements could be
dealing with the levee accreditation process of
Honorable Keith M. Spaeth
Map Modernization. The process requires that necessary to meet MCD’s Official Plan Flood
Clark County standards, which are higher than a 100-year
Honorable Richard J. O’Neill levees meet rigorous compliance standards to be
accredited by FEMA. New FEMA maps will flood. MCD will calculate the cost of improving
Greene County
Honorable J. Timothy Campbell show accredited levees as providing protection. levees once all of the levee systems have
If levees are not accredited the maps will be been through the levee accreditation process.
Hamilton County
Honorable Robert P. Ruehlman published as though the levees did not exist. These costs would be added to MCD’s capital
Miami County improvement needs.
Honorable Jeffrey M. Welbaum Some of the challenges include:
Montgomery County n Tight deadlines and unexpected costs to
Honorable Barbara P. Gorman Levee Accreditation Process
evaluate the levees and certify that compliance
Preble County standards are met. To even begin the Levee Accreditation process,
Honorable David N. Abruzzo
n Inadequate time and funds to complete
levee owners must provide FEMA information
Shelby County
repairs to levees before the flood insurance (including a Maintenance, Operations and
Honorable James F. Stevenson Inspection manual; maintenance records; and
maps are finalized.
Warren County levee height estimates) that would lead FEMA
Honorable Neal Bronson n Potential economic impacts new flood maps
could have on the communities MCD protects. officials to expect the levee can be accredited.
Below is a brief diagram of the process and
Board of Directors Levee owners have been given only a two-year potential outcomes.
window to complete the extensive evaluation of
their levees. Miami Conservancy District staff Provisionally Accredited Levee (PAL)
is working hard to assure we meet the two-year
Gayle B. Price, Jr. deadline for levee evaluation submittals. FEMA
President has not allowed any time for levee repair.
2 years to submit more in-depth
Reducing the risk of flooding is our primary
information plus geotechnical borings
goal. Preventing flooding—by allowing time
and analysis to FEMA.
William E. Lukens for levee repairs—seems a better approach
Vice President than simply requiring that property owners
purchase insurance.
Some Congressmen agree. Proposed legislation FEMA Accreditation Decision
Thomas B. Rentschler
in both the House of Representatives and
Member Senate would suspend flood insurance rate Yes No
map updates in areas where levees are being
Board of Appraisers repaired. Another bill in the House would allow n Cities must enforce
David K. Galbreath, Jr. FEMA to temporarily extend the deadline for n No changes floodplain regulations
Realtor, Troy, OH reaccreditation if “a good faith effort to upgrade n Flood insurance required
Robert Harris a levee to the accredited level is being made.”
Appraiser, Dayton, OH
To contact us…
James E. Sherron
By phone: (937) 223-1271
Attorney, Middletown, OH
By fax: (937) 223-4730
By e-mail: bgibson@miamiconservancy.org
Internet: www.miamiconservancy.org
10-01