Professional Documents
Culture Documents
Province of Masbate
Municipality of Pio V. Co
PROGRAM OF WORK
NAME OF PROJECT:
Date:
Source of Fund:
Project Engineer
Carpenter
Welder
General Foreman
Steelman
PROJECT DESCRIPTION
ITEM
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
DESCRIPTION
% OF TOTAL
SITE WORKS
CONCRETE WORKS
REINFORCING STEEL BARS
FORMWORKS & SCAFOLDING
MASONRY WORKS
TILE WORKS
DOORS AND WINDOWS
PLUMBING WORKS
HARDWARE & FOLDED PARTITION
PAINTING WORKS
ELECTRICAL WORKS
Sub-Total
A. DIRECT COST
Material Cost
Labor Cost
Equipment Cost
B. INDIRECT COST
OCM & Contractor's Profit
Taxes
0.00
0.00
GRAND TOTAL
Prepared by:
4.963
24.020
18.512
7.138
15.865
5.851
5.985
3.437
5.349
4.891
3.988
100.000
of Fund:
DILG
LGU - Counterpart
Php2,000,000.00
Php500,000.00
Materials Engr.
Mason
Tinsmith
Painter
Php2,500,000.00
Minimum Required Equipment:
1-Bagger Conc. Mixer
Hand Tools
Concrete Vibrator
Welding Machine
Bar Cutter
UNIT
QUANTITY
UNIT COST
TOTAL COST
sq.m.
cu.m.
Kgs.
Lot
sq.m.
sq.m.
sq.m.
Lot
sq.m.
sq.m.
lot
320.00
74.45
5,666.53
1.00
342.00
160.40
43.86
1.00
30.36
336.00
1.00
302.66
6,296.57
63.76
139,300.00
905.33
711.91
2,663.25
67,076.00
3,438.74
284.08
77,832.00
96,850.00
468,780.00
361,290.00
139,300.00
309,622.00
114,190.00
116,810.00
67,076.00
104,400.00
95,451.00
77,832.00
1,951,601.00
1,467,641.00
433,710.00
50,250.00
429,352.22
119,047.66
2,500,000.88
Checked:
JUVY S. CHING
Municipal Engineer
DETAILED ESTIMATE
EVACUATION FACILITY - 1 UNIT STANDARD EVACUATION CENTER
ITEM
NO.
I
ITEM DESCRIPTION
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
QUANTITY
UNIT
TOTAL
SITE WORKS
320.00
sq.m.
320.00
sq.m.
400.00
bd. ft.
18.00
7,200.00
2.00
kgs.
360.00
720.00
10.00
kgs.
70.00
A. Materials
100 - 2" x 2" x 12' Coco Lumber
Nylon # 0.80
3" CWN
Total
700.00
8,620.00
B. Labor
Productivity Rate: 26.67 sq. m./ man-day
Construction Foreman
4.00
day/s
1.00
450.00
1,800.00
Carpenter
4.00
day/s
3.00
350.00
4,200.00
Laborer
4.00
day/s
3.00
250.00
Total
I - 2. Structural Excavation
3,000.00
9,000.00
30.00
cu.m.
Construction Foreman
5.00
day/s
1.00
450.00
Laborer
5.00
day/s
4.00
250.00
Total
I - 3. Embankment:
2,250.00
5,000.00
7,250.00
100.00
cu.m
115.00
cu.m
400.00
Total
46,000.00
46,000.00
B. Labor
Productivity Rate: 1.50 cu. m./ man-day
Construction Foreman
8.00
day/s
1.00
450.00
3,600.00
Laborer
8.00
day/s
10.00
250.00
20,000.00
Total
I - 4. Soil Poisoning
23,600.00
1.00
lot
1.00
gals.
A. Materials
Termite Solution
1,680.00
Total
1,680.00
1,680.00
B. Labor
II
Construction Foreman
1.00
day/s
1.00
450.00
Laborer
1.00
day/s
1.00
250.00
450.00
250.00
Total
700.00
96,850.00
CONCRETE WORKS
74.45
cu.m.
Wall Footing, Columns & Footings, Floor Slab, Lintel Beams. Roof Beam
and Septic Tank
A. Materials
Portland Cement
671.00
bags
280.00
187,880.00
Washed Sand
38.00
cu.m.
950.00
36,100.00
Washed Gravel
75.00
cu.m.
1,000.00
75,000.00
Gravel Bedding
25.00
cu.m.
1,000.00
25,000.00
O
T
H
E
R
S
ITEM
NO.
ITEM DESCRIPTION
Sahara (for roof slab only)
Total
QUANTITY
UNIT
150.00
kls
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
47.00
O
T
TOTAL
H
E
R
7,050.00
S
331,030.00
QUANTITY
UNIT
No. of
Crew/
Labor
Construction Foreman
25.00
day/s
1.00
450.00
11,250.00
Mason
25.00
day/s
2.00
350.00
17,500.00
Laborer
25.00
day/s
8.00
250.00
50,000.00
25.00
day/s
1.00
350.00
ITEM
NO.
ITEM DESCRIPTION
RATE PER
DAY/ UNIT
COST
TOTAL
B. Labor
Productivity Rate: 0.3 cu. m./ man-day
Total
8,750.00
87,500.00
III
25.00
day/s
1.00
25.00
day/s
16.00
25.00
day/s
0.25
1,000.00
25,000.00
60.00
24,000.00
200.00
1,250.00
Total
50,250.00
468,780.00
5,666.53
Kgs.
414.00
length
1,532.63
150.00
278.00
length
1,481.18
230.00
63,940.00
280.00
length
2,652.72
370.00
103,600.00
100.00
kgs.
65.00
6,500.00
40.00
pcs.
65.00
Wall Footing, Columns & Footings, Floor Slab, Lintel Beams, Roof Beam
and Septic Tank
A. Materials
Hacksaw Blade
Total
62,100.00
2,600.00
238,740.00
B. Labor
Productivity Rate: Cut, Bend and Place RSB (30.0 kgs./ man-day)
Construction Foreman
19.00
day/s
1.00
450.00
8,550.00
Steelman
19.00
day/s
10.00
350.00
66,500.00
19.00
day/s
10.00
250.00
Laborer
IV
47,500.00
Total
122,550.00
361,290.00
1.00
Lot
1,000.00
bd.ft.
18.00
18,000.00
3,300.00
bd.ft.
18.00
59,400.00
400.00
bd.ft.
18.00
7,200.00
80.00
shts.
410.00
32,800.00
#4 CWN
40.00
kgs.
70.00
2,800.00
#3 CWN
40.00
kgs.
70.00
2,800.00
#2 CWN
20.00
kgs.
70.00
1,400.00
#1 CWN
20.00
kgs.
70.00
Materials
Total
1,400.00
125,800.00
Labor
Construction Foreman
6.00
day/s
1.00
450.00
2,700.00
Carpenter
6.00
day/s
3.00
350.00
6,300.00
Laborer
6.00
day/s
3.00
250.00
Total
TOTAL FOR FORMWORKS AND SCAFFOLDING
V
MASONRY WORKS
4,500.00
13,500.00
139,300.00
342.00
sq.m.
189.00
bags
280.00
52,920.00
16.00
cu.m.
950.00
15,200.00
4,489.00
pcs.
18.00
80,802.00
268.00
length
150.00
40,200.00
6.00
kgs.
65.00
390.00
O
T
H
E
R
S
ITEM
NO.
ITEM DESCRIPTION
QUANTITY
Total
UNIT
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
O
T
TOTAL
H
E
R
189,512.00
S
ITEM
NO.
ITEM DESCRIPTION
QUANTITY
UNIT
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
TOTAL
B. Labor
Productivity Rate: 6.0 sq. m./ man-day
0.00
Construction Foreman
15.00
day/s
1.00
450.00
6,750.00
Mason
15.00
day/s
4.00
350.00
21,000.00
15.00
day/s
4.00
250.00
Laborer
Total
V - 2. Plastering
615.20
A. Materials
15,000.00
42,750.00
sq.m.
307.60
Portland Cement
Washed Sand
127.00
bags
280.00
11.00
cu.m.
950.00
Total
35,560.00
10,450.00
46,010.00
B. Labor
Productivity Rate: 8 sq. m./ man-day
9.61
Construction Foreman
11.00
day/s
1.00
450.00
4,950.00
Mason
11.00
day/s
4.00
350.00
15,400.00
11.00
day/s
4.00
250.00
Laborer
VI
11,000.00
Total
31,350.00
309,622.00
TILE WORKS
160.40
sq.m.
126.00
sq.m.
34.40
sq.m.
368.00
pcs.
180.00
126.00
pcs.
50.00
6,300.00
268.00
pcs.
50.00
13,400.00
Washed Sand
66,240.00
3.00
cu.m.
950.00
2,850.00
Portland Cement
37.00
bags
280.00
10,360.00
10.00
kls.
88.00
880.00
Tile Trim
16.00
pcs.
60.00
Total
960.00
100,990.00
B. Labor
Productivity Rate: .625 sq. m./ man-day
VII
Construction Foreman
8.00
day/s
1.00
450.00
3,600.00
Mason
8.00
day/s
2.00
350.00
5,600.00
Laborer
8.00
day/s
2.00
250.00
4,000.00
Total
13,200.00
114,190.00
43.86
sq.m.
A. Materials
DOORS
13.02
sq.m.
2.00
sets
5,900.00
11,800.00
2.00
sets
3,800.00
7,600.00
4.00
sets
2,200.00
8,800.00
D - 4, (0.80m x 2.10m)
1.00
sets
3,500.00
Total
3,500.00
31,700.00
B. Labor
B.1. Installation of Doors (Productivity Rate: 2.69 sq. m./ man-day
Construction Foreman
3.00
day/s
1.00
450.00
1,350.00
Installer
3.00
day/s
2.00
350.00
2,100.00
Laborer
3.00
day/s
2.00
260.00
Total
WINDOWS
1,560.00
5,010.00
30.84
sq.m.
W1 (1.80m x 1.20m Steel Casement Window with 1/4" thick clear glass
& 0.40m Thick clear Glass)
4.00
sets
5,500.00
22,000.00
W2 (1.20m x 1.20m Steel Casement Window with 1/4" thick clear glass
& 0.40m Thick clear Glass)
8.00
sets
4,000.00
32,000.00
O
T
H
E
R
S
ITEM
NO.
ITEM DESCRIPTION
QUANTITY
UNIT
W3 (1.20m x 1.20m Steel Casement Window with 1/4" thick clear glass)
2.00
sets
3,500.00
O
T
TOTAL
H
E
R
7,000.00 S
W4 (0.60m x 0.60m Steel Casement Window with 1/4" thick clear glass)
5.00
sets
2,500.00
12,500.00
Total
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
73,500.00
QUANTITY
UNIT
No. of
Crew/
Labor
Construction Foreman
4.00
day/s
1.00
450.00
1,800.00
Installers
4.00
day/s
2.00
350.00
2,800.00
Laborer
4.00
day/s
2.00
250.00
ITEM
NO.
ITEM DESCRIPTION
RATE PER
DAY/ UNIT
COST
TOTAL
B. Labor
B.1. Instalation of Windows (Productivity Rate: 1.95 sq. m./ man-day
VIII
2,000.00
Total
6,600.00
116,810.00
PLUMBING WORKS
1.00
Lot
5.00
pcs.
5,500.00
5.00
sets
100.00
Sub-Total
27,500.00
500.00
28,000.00
100.00
L meter
45.00
4,500.00
1/2" Elbow
11.00
pcs.
25.00
275.00
1/2" Coupling
11.00
length
15.00
165.00
1/2" T-Joints
6.00
length
30.00
180.00
6.00
pcs.
65.00
390.00
2.00
pcs.
268.00
536.00
12.00
pcs.
162.00
1,944.00
6.00
pcs.
45.00
270.00
6.00
pcs.
45.00
270.00
16.00
pcs.
220.00
3,520.00
8.00
pcs.
55.00
440.00
8.00
pcs.
50.00
400.00
24.00
pcs.
250.00
6,000.00
12.00
pcs.
65.00
780.00
12.00
pcs.
65.00
780.00
20.00
pcs.
330.00
6,600.00
10.00
cans
200.00
2,000.00
6.00
rolls
21.00
Teflon Tape
Sub-Total
126.00
###
29,176.00
B. Labor
IX
Construction Foreman
6.00
day/s
1.00
450.00
2,700.00
Plumber/ Mason
6.00
day/s
2.00
350.00
4,200.00
Laborer
6.00
day/s
2.00
250.00
3,000.00
Sub-Total
9,900.00
67,076.00
30.36
sq.m.
A. Materials
Aluminum Folded Partition with fixed transom ( Fabricated) includes
installation
1.00
set
80,000.00
80,000.00
6.00
pc
1,200.00
7,200.00
Double lock
6.00
pc
1,250.00
7,500.00
2.00
pc
1,300.00
2,600.00
Stair nosing
20.00
l.m.
190.00
Sub-Total
3,800.00
101,100.00
B. Labor
Construction Foreman
2.00
day/s
1.00
450.00
900.00
Skilled Worker
2.00
day/s
2.00
350.00
1,400.00
2.00
day/s
2.00
250.00
Common Laborer
PAINTING WORKS
A. Materials
1,000.00
Sub-Total
3,300.00
104,400.00
336.00
sq.m.
O
T
H
E
R
S
ITEM
NO.
ITEM DESCRIPTION
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
QUANTITY
UNIT
5.00
pale
2,320.00
7.00
pale
2,500.00
O
T
TOTAL
H
E
R
11,600.00
S
17,500.00
ITEM
NO.
ITEM DESCRIPTION
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
O
T
TOTAL
H
E
R
3,375.00
S
800.00
QUANTITY
UNIT
Masonry Putty
9.00
gals.
4.00
gals.
200.00
8.00
gals.
1,220.00
9,760.00
12.00
gals.
610.00
7,320.00
Paint Thinner
2.00
gals.
160.00
320.00
9.00
gals.
700.00
6,300.00
10.00
yards
85.00
850.00
26.00
pint
80.00
2,080.00
375.00
6.00
set
86.00
516.00
6.00
pcs.
75.00
450.00
6.00
pcs.
30.00
Sub-Total
180.00
61,051.00
B. Labor
Productivity Rate: 21 sq. m./ gang 2 skilled 4 laborers)
Construction Foreman
16.00
day/s
1.00
450.00
7,200.00
Painter
16.00
day/s
2.00
350.00
11,200.00
16.00
day/s
4.00
250.00
Laborer
Sub-Total
TOTAL FOR PAINTING WORKS
XI
ELECTRICAL WORKS
16,000.00
34,400.00
95,451.00
1.00
lot
A. Materials
#14 THHN Copper Wire
3.00
box
2,550.00
7,650.00
3.00
60.00
box
m
3,200.00
24.00
9,600.00
Junction Box
24.00
pc
35.00
840.00
Utility Box
16.00
pc
30.00
480.00
10.00
pc
155.00
1,550.00
1,440.00
8.00
pc
180.00
1,440.00
20.00
pc
175.00
3,500.00
Bulb Receptacle
20.00
pc
65.00
1,300.00
1.00
set
3,532.00
3,532.00
20.00
pc
30.00
600.00
Drop Wire #6
50.00
80.00
4,000.00
10.00
80.00
800.00
Lamp Fixture
12.00
pc
1,500.00
18,000.00
54,732.00
Construction Foreman
14.00
day/s
1.00
450.00
6,300.00
Electrician
14.00
day/s
2.00
350.00
9,800.00
Helper
14.00
day/s
2.00
250.00
Sub-Total
B. Labor
Productivity Rate: 60 units of electrical wirings and fixtures/ gang
7,000.00
Sub-Total
23,100.00
77,832.00
DIRECT COST
Material Cost
1,467,641.00
Equipment Rental
50,250.00
Labor Cost
a. Foreman
66,150.00
b. Skilled
176,750.00
c. Unskilled
190,810.00
Sub-Total A
1,951,601.00
INDIRECT COST
OCM & Contractor's Profit
429,352.22
Taxes
119,047.66
Sub-Total B
548,399.88
ITEM
NO.
ITEM DESCRIPTION
QUANTITY
TOTAL (A+B)
TOTAL ESTIMATED COST
GRAND TOTAL
UNIT
No. of
Crew/
Labor
RATE PER
DAY/ UNIT
COST
O
T
TOTAL
H
E
R
2,500,000.88
S
2,500,000.88
2,500,000.88
Checked by:
Prepared by:
JUVY S. CHING
Municipal Engineer
Approved by: