Professional Documents
Culture Documents
chapter
17
EVALUATING IRRIGATION
SYSTEMS ANO PRACTICES
17.1
17.2
17.3
17.4
Purpose................................
Definitions
Field Evaluation and Interpretation . . . . . . . ..
Measuring Devices and Methods Used
in Evaluations. . . . . . . . . . . . . . . . . . . . . . . ..
721
721
724
749
. , flI
17
EVALUATING IRRIGATION SYSTEMS ANO PRACTICES
by
17.1 PURPOSE
17
The purpose of evaluating irrigation systems is fourfold: (a) To determine the efficiency of the system as it is being used; (b) to determine how effectively the system can be operated and whether it can be improved; (c) to
obtain information that will assist engineers in designing other systems; and
(d) to obtain information to enable comparing various methods, systems, and
operating procedures as a basis for economic decisions.
Evaluations involve measuring conditions at one or more points in a
fleld selected to be typical or representative. Value judgments or additional
measurements must be made to correlate these data to an overall fleld, farm,
or project efficiency. For example, for sprinklers, the pre-nozzle Iosses,
nonuniform pressures, topography influences, etc. usually are not included
in estimating the potential application efficiency, and for surface methods,
soils typically are assumed to be uniformo The accuracy of most
measurements wilI seldom justify calculating efflciencies to more than 3
percent.
17.2 DEFINITIONS
The on-farm irrigation systems and operations need to be measured to
determine the potential efflciency of the systems as designed and the actual
efflciency that is obtained with present management. To make and interpret
the measurements requires a precise terminology. In order that all cornparisons have a common basis, the three performance parameters (potential
application efflciency, actual application efflciency, and distribution uniformity) are based on the average depth of water infiltrated or stored in the
quarter of the area receiving the least amount of water. The low quarter (LQ)
concept was developed by the USDA, Soil Conservation Service, and is
recornmended as the standard for comparing alternative conditions. For
sorne uniformity studies, Christiansen's uniformity coefficient may be used.
17.2.1 Performance Parameters
Application efflciency (AE) is the ratio ofthe average depth ofthe irrigation water infiltrated and stored in the root zone to the average depth of irrigation water applied, expressed as a percent.
721
722
[17.1]
This term indicates the percentage of the water applied (calculated from nozzle discharge for a sprinkler system) that is stored in the root zone for crop
use. It may not be useful in evaluating irrigation system operation in the field
because high efficiencies can be obtained by excessive under-irrigation even
when water is distributed very non-uniformly.
Actual appllcatlon efficiency of low-quarter (AELQ) is the ratio of the
average low-quarter (LQ) depth of irrigation water infiltrated and stored in
the root zone to the average depth of irrigation water applied (calculated
from nozzle discharge for sprinkler systems), expressed as a percent. The
average LQ depth infiltrated is the average of the lowest one-fourth of the
measured values where each value represents an equal unit of area and cannot exceed the soil moisture deficiency (SMD). Values of AELQ indicate
both the uniformity of water distribution and adequacy of irrigation. When
the LQ value is less than the SMD or the desired management alIowed deficiency (MAD), under-irrigation is indicated. The numerical value of the LQ
average depth indicates the adequacy of the irrigation.
AELQ = average low-quarter depth of water inftrated and stored 100
average depth of water applied
.. :
[17.2)
= average low-quarter
= MAD 100
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
[17.3)
PELQ is a measure of how well the system can apply water if management is
optimal. The difference between PELQ and AELQ is a measure of management operations. Low PELQ values indicate design problems. This is the onIy efficiency ter m that should be used to compare systems or methods.
DIstrlbutlon unlformity (DU) is the ratio of the average LQ depth of irrigation water infiltrated (or caught) to the average depth of irrigation water
infiltrated (or caught), expressed as a percent.
DU = average low-quarter depth of water inHl.trated (or caught) 100
average depth of water inftltrated (or caught)
...............
depth of water caught (or infiltrated) minus the average deviation from this
depth, divided by the average depth caught (or infil~r~ted~ as would occur
with sprinkler patterns overlapped during a complete irrigatton, expressed as
a percent.
_ average depth caught - average deviation from average depth caught 100
UC average depth caught
. ..................
[17.5a]
or
_
average deviation from the average depth caught) .....
UC - (1 average depth caught
[17.5b}
= 100 -
s
0.8
; ............................
[ 17.6}
[ 17.7}
[17.4)
723
..................
'"
[17.8}
Storage ratio (SR) is the ratio of the average depth of ,,:ater ~tore~ in the
root zone to the average depth storable. It is used in conJunct1o~ with t~e
distribution uniformity and the application efficiency terms. This term IS
724
= average depth
stored 100
average depth storable
. . . . . . . . . . . . . . . . . . . . . . ..
(17.9]
725
II'
726
--,
ReC8ssion
End of turro.
=r+r>
;1------~j-/...I.-7
~
,/'
-~
.... ,",
" ,.."
,/'
J _-
DiBtance
ADVANCE-RECESSION
Time
CUMULATIVE INTAKE
EFFICIENCIES
AND LOSSES
Advance ratio
1/4 1/2 1/1
Appliedwater 10~
In!lltrated
66
StoredMAD(PELQ)61
Dralnage
5
Runo!!
J4
With retllrn
Diatance
INFlLTRATED DEPTH DISTRIBUTION
flow
10~ 100~
77 91
66 70
11 21
2J
9
and no runnoff
Infiltrated 10~
Stored MAD(PELQ)9J
Stored SMD(AELQ)6J
Dralnage
7
100% 100%
86 77
60 54
14 2J
uniform intake along the furrow providing it is level across to keep the water
spread. It is not adaptable to fields with much longitudinal or lateral slope
because of the difficulty in keeping the whole furrow bottom covered.
The shape and spacing of furrows has a large effect on Ti and resultant
effects on efficiencies. The ability to change furrow shape, spacing, length
and flow rate, and the MAD provide more management-controllable functions than are available for other methods.
Observational evaluations permit determining whether or not the furrows are being operated reasonably well. Observations do not require
measurements and so cannot provide numerical values or efficiencies, but a
numerical check on the SMD to see that it approximates the MAD-is it dry
enough to irrigate-should always be done.
Observations should consist of: (a) probing the soil in the furrow near
the lower end during and at the end of irrigation to assure that the SMD at
the lower end has just been replaced. AH water applied after this time is 100
percent wasted unless a return flow system is used; and (b) observing the
duration and rates at which water runs off at the lower end provides a
measure of runoff loss. Generally, runoff is the largest loss. However, it can
be reduced by about one half by utilizing a cut-back of the initial stream, and
the loss can be recovered by using a return flow system.
The uniformity of the infiltration is related to the advance ratio, AR (see
Fig. 17.1). If the initial stream is large enough to cause the flow to arrive at
the lower end in one fourth ofT, (AR = TadjTi = 114), very high uniformity
is assured with distribution uniformity (DU) being between 90 and 95 percent with the higher values occurring on the finer soils. In most cases this requires a large capacity system and much labor and may be uneconomically
uniformo It results in a large amount of runoff which may be of the
magnitude of 35 percent. This causes a low potential application efficiency
---
_~-~ ---
..
lOsa
727
(PELQ). However, if a return flow system is used, PELQ can equal DU and
labor is very small. An AR of 1/2 usually results in a DU of about 85 percent
and moderate runoff. An AR of 111 results in the infiltration of appreciable
water too deep at the upper end but very little runoff. ARs of this magnitude
will often resuIt in about the highest PELQ when no cutback or return flow
system is used.
.
In summary, high furrow application efficiency is assured when: (a) ~~st
enough water is infiltrated at the low end to satisfy the SMD; (b) the. initial
stream size is cut back to result in little runoff or a return flow system 1S used
to recover runoff; and (e) the AR is low enough to assure reasonable uniformity of depth infiltrated along the furrow.
Measured evaluations permit determining numerical values of DU,
AELQ, and PELQ. From these values economic decisions can be made as to
where and what changes are desirable. The procedure consists o~ ma.king
field measurements, assembling the information, and then evaluatng t:
The test should use existing irrigation practices (SMD, stream size,
shape, etc.) so that the AELQ value may be determined. Other furrow.shapes
and stream sizes should also be tested. The PELQ values are determmed by
making reasonable calculated modifications of the system or it~ operation,
such as changes in MAD, stream size, furrow shape or spacmg, furrow
length, use of cut-back streams or return flow system, etc.
Field Procedures. A detailed presentation of techniques and interpretation with illustrations can be found in Farm Irrigation System Evaluation: A
Guidefor Management (Merriam and Keller, 1978). Procedures are outlined
below:
1 Determine with a soil auger or other methods the soil uniformity,
depth of root zone, and the soil moisture deficiency (SMD) and compare it to
the MAD.
2 Measure the inflow rates into the test furrows which, for noncracking soils, may conveniently be alternate furrows. At least three different
stream sizes should be used: too large, too small, and reasonable.
3 Measure the instantaneous intake rate (see Subsection 17.4.2 and
17.4.4) in a furrow with the medium size stream using inflow-outflow
measurement. Rates should also be determined for other stream sizes if practical.
4 Measure the advance rate using stakes placed adjacent to the furrows at intervals of 20 to 30 m before the start of the test. The time water arrives at each station, starting with zero time at station zero, is noted for each
of the stream sizes on the Water Advance and! or Recession sheet. (Form 1)
(This is not the same zero time as for intake.) If it is occasionally impractical
to observe this time at the staked station, any time and distan ce may be noted
since the objective of collecting these data is to be able to plot advance curves
for several different stream sizes. A minimum of eight points should be obtained. Minor changes in the advance rate are often indicative of variations
of soil, slope, or furrow conditions.
5 Determine the depth of penetration and lateral spread of the water
during the latter part and at the end ofthe tes.t by u~ing a pro?e. It sh.ould be
rechecked to determine the adequacy of the irrigation by usmg a soil auger
one or two days later. Probings made before the end of the test are necessary
to avoid over-irrigation. Water will continue to penetrate deeper after the
flow is turned off.
6 Observations of the furrows during and after the test are made
728
rURROW INTAKK
ti...l..!....!
_____
"H .[C[5'IO"
.... __
=.-::..._,.
SoU T
t..u __
fIohtllu
.. f-'"
TillE
--,_o
SUUI)fI
Cut
-- e
r--
1-f-1-f-1-1--
1--1-
f--
r--
f--
r--
1-
1r-1-
--
1--1--
1--1-
1-1-
11-
r--
1-
r-r--
1--11-1-
---
1--
1--
r-- '---
f--
-- 1-- f--
IUlt_
T 1 Mt
"Uf. <'
1--
T
.... te
O'
f-1--
--SutlOI\
.. "f,c_,
, 'fl<
1--
f-f--
f-1-f--
1-11-1-
C:re,,
......
r r xc
...ce
1--
!--
tt.d
oneer-ve r
ela.slflcatlon
.1dth_.lopo_cond1tlon_-
Da te ---SMD---8g.
j.eng
th AIl__
l.n\ake rat.
rate
1-1-1-f1-
1--
f--
!-1-!--
1--
1-
Loc" tlon
So11! textura
l'urro.: .hapo __
f-1-f--
r-- !--
11-
St.thn
fru
dUf
r-- 1-1-
1--
DATA
Conunent.
f1-1f-1f'f-- '-
f--
RA'lE
FORM
UU
Odtc1ft\c:y__
rr __
14.I'IlUlc..ct_
729
'-
'!-!--
PClU' 1
f---
f-- f---
length A.S
S
t~po ",.uur1ng d avioe
n
e rata
Sta tion S
atat on A.
7
6
4
lo. ra e
Clo. rll te
- - -
-~
f-f-- f---
aecurBcy raf!.ge
A.nd B
l.
Flrat entry made .hen stream reaches mldway between at&tlonl
Second entry dde _hen stream 11 about 3.m pe e t. Itatlon
8.Subaequent
e c tr tes made s.t incre8singly
longer lntervall
o time.
2.
Dltference
ln tlme be tween suce eea f ve wa tch times.
3.
Summs.tlon of aue ce ee t ve tlme incrementa.
To be plotted
ve col. 9.
",6. Head on paraball
flume, or-Lffc e , _eir,
etc. Show de vice and. unlts
uaed .
If 8. jug 18 ueed , aho_ size a nd time to f111.
.
f),? Rlght column r cr rlo.
rateo Left column for mlscellaneou8
_or}c entr tes .
e
Flow r-ate dlfference
ce teeen col. b and col. ? per length A.8.
9:
Flo. rato por un1t Lengt h , (L/o-m,
cr .. /t , gpnl/100ft)
Plot vo col. 3.
Accuracy range. Sho. plus or mlnus l1mSts of 8ccuracy of measurements and
or the resultlng Clo. rate., Show renge enen plottlng.
calculated intake rate points will generally give a broken line which is not
valid. Unless sorne unusual condition occurs, or the duration is very long, the
plotted line should be straight. The equation of the intake curve is
1 = KTn
[17.10
where I is the intake rate in L/min-m, (or gal/min-lOO ft) for the length between the stations at the time T in minutes. K is a constant and has the value
given by the curve when T eq uals 1.0 minute, and n is the geometric slope .of
the line and is negative. It is very desirable to calculate and p~otthe val~es tor
this curve at the time the measurements are taken so that discrepancies can
be detected and new readings taken if necessary. The value of K t~pically
changes appreciably with cultural operations, and decreases during the
season.
.
3 The cumulative intiltrated depth curve is developed for the studied
turrow shape and spacing, and other spacings as ~ay be ~esirab.le to study
PELQ. It is done mathematically or graphically by mtegranng the intake rate
equation and plotting it on logarithmic paper with the intake rate curve. For
SI units,
730
DESIGN
ANO OPERATION
OF FARM IRRIGATlON
SYSTEMS
731
D(S) = K'Tn+1
[17.11]
where D(SIis depth in mm for the specific furrow spacing S in meters, and KI
= K/(n + 1)S. (For English units, D(SI is depth in inches for a specific furrow spacing S in feet and KI = K/62.3(n + 1)S.) T is elapsed time in
minutes. The cumulative infiltrated depth curve for any specific furrow spacing is easily plotted. The intercept at T = 1.0 min is the value of KI, and the
line is drawn upwardto the right on the geometric slope of(n + 1):1 (see Fig.
17.2).
4 "Adjusted" intake rate and cumulative infiltrated depth curves are
frequently needed. They are necessary for furrows that have been formed in
loose soil or soils that crack. They are needed because the infiltration
measuring techique described cannot provide rates for the first few minutes
of applying water under these conditions. AIso, since the technique involves
taking the difference between the inflow and outflow measurements, small
discrepancies may be magnified.
Assuming the rate and duration of the inflow to the tested furrow can be
measured with reasonable accuracy, the total volume of water applied to the
test area can also be found to the same degree of accuracy. This can be compared to the average depth obtained using the original cumulative depth infiltrated curve. The latter is then "adjusted" ifnot reasonably similar, to give
a consistent answer. This is done as follows:
An advance curve (extrapolated beyond the end of the furrow) is drawn
on rectangular coordinates for the duration T. (see Fig. 17.2). A recession
curve is drawn horizontally (unless known to be appreciably slow) at T. The
time increment between the advance and recession curves is the opportunity
time (T.) at any station. Convenient, equally spaced stations are selected to
give about six or more locations along the extrapolated furrow length. The T.
at each of these locations is noted below the station. Then using the
cumulated infiltrated depth curve for the corresponding furrow spacing, the
depth infiltrated at each location is determined and an infiltrated depth
distribution curve is plotted. The average for each equal section can be
calculated or scaled, and their average determined. This should correspond
to the actual average depth applied calculated using the inflow rate, the T.,
and the area represented by the spacing and extrapolated furrow length.
Alternatively, the area under the infiltrated depth distribution curve for the
furrow and extrapolated length can be found and its average determined, or
the average line can be drawn (see Fig. 17.2).
If measurements have been carefulIy made and the soil is uniform for
the entire furrow length and does not have a high initial intake rate due to
cracks or loose soil, the caIculated average depth infiltrated wilI cIosely equal
the calculated average inflow depth. If they are not reasonably cIose, adjusted curves should be drawn as described below.
Presuming that the average calculated inflow depth is correct, it is plotted as a point on the cumulative infiltrated depth sheet at a time that is the
same time as that at which the average infiltrated depth occured. A line
drawn through this point and parallel to the original curve is the adjusted
cumulative infiltrated depth curve for that furrow spacing. Its equation may
be found and the corresponding intake rate equation calculated and the adjusted intake rate curve drawn. AIso a new infiltrated depth distribution
curve for the extrapolated lengths should be drawn and used for the evaluation study.
JOO
.~200
r-_"""T"..,...--~--r-1100
~ 100
.......
OJ._----:D
...
i~8t=-=a-=:no::-::e-....L---~
INFILTRATED DEPTH DISTRIBUTION
(unadjusted)
_
100
-SMD
....
SMD
Stored
O .1.-----D~.t>:an;:::c::;;e-....L.------
Evaluation of information. The basic objective of evaluations is to id~ntify types and magnitudes of losses that are occurring,. a~d t~en dete~~me
how to improve the system and/or its, oper~tion, The. lrt1~atlon co~dlt~on~
determining certam rabos or eciences. The distribu
can b e evaluated by
.
'
. h hi h
t .
,
if
it
(DU)
mtion um orrnt y
, which describes the uniformty wit w re wa. er
(AR)
filtrated along the furrow length, is closely related to the advan~e ratio .
(see Fig. 17.1). The actual application efficiency (AELQ), which descnb.es
how much of the applied water can be used by the cr~p at the LQ, permts
the determination of the actual.losses to deep p~rcolatlon and, to :unoff (see
Fig, 17.2, SMD). The potential application efficiency (.PELQ) ln.dlcates w~at
can be done with certain variations in the system or its ope~ahon ~see Fig.
17,2, MAD). PELQ is the only proper term to u~efor comparisons with other
systems or methods. Low values of AELQ indicate management problems
and low values of PELQ indicate system problems. Large .v~l~es of AR and
nes for DU indicate too long a furrow, too small an intal stream, too
1ow o
.
small aMAD, or too small a furrow spacing.
.
Basic to the study of these parameters is the use of the 1D~ltrated depth
distribution curve adjusted if necessary. It is most conv~nlently plotted
directly below the extrapolated advance curve to the same h?rlzo~tal dl.stance
scale. On this graph note the actual furrow length as a vertical hne at its station, and the SMD and MAD values horizontally along the length ofthe fur-
732
row. A study of this graph will indicate the distribution of inflow water. The
area aboye the SMD line (which ideally is the same as the MAD line) up to
the infiltrated depth distribution curve is lost to deep percolation. The area
(if any) below a SMD line down to the infiltrated depth distribution curve
would be under-irrigated, The area beyond the end of the furrow is runoff.
The area that is below both the SMD and infiltrated depth distribution lines
is stored for crop use.
Three additional horizontallines drawn as shown on Fig. 17.2 are useful
in graphicalIy representing the information: a line showing the average infiltrated depth, a line showing the depth corresponding to the average depth
of the lowest quarter infiltrated (it will usualIy cross the infiltrated depth
distribution curve about 7/8 to 9/10 of the furrow length and should be the
same as the MAD line) , and a line corresponding to the average depth applied on the furrow length itself, i.e. incIuding all of the runoff water.
The are a under the various horizontal lines drawn correspond to equal
areas under the curved Iines, but all now have the same length. Therefore,
their depths are all proportional and can be used in evaluating DU, AELQ,
and PELQ.
The DU value (equation [17.4]) with easily obtainable values of AR
smalIer than about 112, will be about 85 to 90 percent indicating that onIy 15
to 10 percent of the infiltrated water need be lost to deep percolation.
In the AELQ (equation [17.2]) the minimum depth stored cannot exceed the SMD. If it is less, under-irrigation has occurred and the storage
ratio is less than 1.0. The difference between 100 percent and AELQ is the
measure of the deep percolation and the runoff losses occurring as the system
.is actualIy being operated. With under-irrigation sorne of the implied deep
percolation may be still stored in the root zone.
The PELQ (equation [17.3]) also can be studied utilizing the data from
the test. Changes in efficiencies result from changes in operating procedures
such as using larger or smalIer initial streams which will affect T.dv and hence
change AR and DU, and to sorne extent Ti; changes in MAD which will affect Ti and hence modify T DU, and AR; changes in furrow spacing or
shape which will affect Ti' Tad., Ta, AR, and DU; and changes in furrow
length interact with many of the aboye. A cut back stream and a return flow
system should almost always be studied, especialIy when high DU values occur which are accompanied by high runoff.
By studying the effects of changing or combining the aboye management
controlIable items, the most desirable or economical operation can be determined with a reasonable degree of accuracy. However, it might well not be
the highest PELQ depending on various costs of water, labor, and capital.
(seeFarm Irrigation System Evaluation: A Guide for Management, Merriam
and Keller, 1978, for illustrations.)
Example.
From the values shown in Fig. 17.2 (adjusted) for an AR of 1/2, SMD =
48 mm, MAD = 66 mm, infiltrated depth = 80 mm, applied depth = 101
mm, the DU, AELQ, PELQ, runoff and deep percolation values without and
with a reuse system are as follows:
733
Vales in percent
Parameter
DU
For SMD = 48 mm
AELQ
(48/101)100 = 48
Runoff
101-80)/101)100 = 21
Deep perc olation
80-48)/101)100 = 32
For MAD = 66 mm
PELQ
(66/101)100= 66
Runoff
101-80)/101)100 = 21
Deep perc olation
80-66)/101)100 = 14
- 82
(48/80)100
= 60
80'48)/80)100
(66/80)100
-o-
= 40
= 82
-0-
80-66)/80)100
18
4
734
Cut of! the water before the stream reaches the lower end and note
the time and distan ce. (It is very desirable to cut off one of the medium size
streams too soon so that it wiIJnot reaeh the end in order to provide the proper shaped curve for what is usually the extrapolated runoff curve.)
6 Note the time and distanee when the water disappears from the sur~aee so that, praetiealIy speaking, there is no more opportunity for water to
infiltrate, There may be sorne smaIl puddles or water may be flowing in smalJ
735
Obs erve r
Crop: kind
So i.L:
condition
texture
-:
MAllO;
A.'1C
Border: spacing
condition:
Date
recardance
Strip:
w.dtb __
SIiD
wet t ed width __
slopc __
Comments
str!:.E_ ~entl
t ame
ve t c
Lca t .cn
~ance
rmnu t e s
i
r---- -:---
t-r---- t--
s te crco
cumu
0+00
s tream S ae
reces s on
eunuce e
t rme
wa t c
cumu
---
t-t-t-t-t--
s r r i,
s r a m on
r-
0+00
0+00
0+00
r--
1-1-1-1-1-f----1-1-1-1--
r-t-t----
-----
t--
f----
---
t--
t--
-----
---
f--
r--
t-t--
r-r--
t--
f
.
t
should be made when t he water a s s t ar c ed ,
Note: For border-strip
r eces s Ion data, dlroSf~t~~~ ~geri_h1rd entry when the recession starts,
and
second en t r y at the time water 1.& turne
.'
all of these entr1es should be made at s t a tn.cn 0+<>0.
PORM
11
ehannels, but a eonsistent condition for eaeh station should exist at the
recorded momento Water will usually disappear first at the upper end sorne
minutes (or hours on fine textured, low gradient fields) after it is turned off
(Lag Time, TL). It later may disappear simultaneously at loeations at both
the upper and lower ends on long strips. On a strip that was cut off too soon,
it will first disappear at the lower end. (It is sometimes expeditious to
simultaneously take recession data on one strip while taking advanee data on
an adjaeent strip using the stream of water just turned off. This is espeeially
true where there is only one stream available.)
7 Cumulative infiltration measurements using at least four cylinder infiltrometers are taken at a representative location (see Seetion 17.4.4.).
Assembling data. Proeedures for preparing data for analysis are outlined below.
1 Plot the advanee and reeession curve for eaeh test. In addition to
plotting them on individual sheets for later evaluation, it is also desirable to
plot several curves on one sheet so that the effeet of the several stream sizes
on the advance curves will be obvious (see Fig. 17.3.). The reeession curves
should all normally have nearly identieal shapes though displaced in starting
time. The advanee and reeession curves should be extrapolated beyond the
end of the field until they interseet. The shape of this extrapolated portion
should be similar to that obtained from the stream that was cut off too soon.
2 Plot all the individual eumulative infiltrated depth curves from the
eylinder infiltrometer data Form 4 on one sheet of3-eyc1e log paper similar to
Fig. 17-2. They should plot as straight lines essentialIy all parallel except for
possible "dog legs" either steeper_or flatter in the earIy parto They ~ener~lly
will have a large variation in magnitude within the group. A straight line
parallel to the general slope of the "non-dog leg" portion is next drawn and
:111
736
737
CYLIIrll)Ea
End of strip
tNFILTROHEtER
Loc.tlon'
So11 .,..bol,
.011 Uatur.'
.011 sol.ture
Crap bhtory'
a...
DAtA
oburver __
du:.
_
_
_
dr..
Distance
ADVANCE-RECESSION
1. Too small a stream. Cutoff made late in order to adequately
irrigate the lower end. Upper end over-irrigated, and little
runoff.
2. Correct stream size. Both ends adequately irrigated. Cutoff
time and distance correct, and little runoff.
3. Too large a stream. Cuto!! made late in order to adequately
irrigate the upper end. Lower end over-irrigated and much runo!!
..,Po
.c:
SMD (58Ill1ll)
Stored
ADJUSTED
Distance
INFILTRATED DEPTH DISTRIBUTION
iabeled "typical". This tine is not an average of the group, but is representative of the group. If the tested area consisted of soils that crack on drying
and so often have a steep dog leg section, the typical curve should be placed
well above the group sometimes as much as 2S mm at time equals one
minute. The reasons for this are that while the cylinders are hopefully placed
in typical soil conditions, they could not be placed over a "typical crack" and
so are usually placed to avoid obvious cracks, and that the initial infiltration
before the first reading at 20 or 30 s is not measured. The initial very high infiltration rate is therefore not measured even though it exists.
3 Adjusted cumulative inftltrated depth curve is next drawn. To
develop this curve an extrapolated advance-recession curve representative of
the test is used. The opportunity time (T.) at six to ten stations equally spaced (or weighted if non-uniforrn) along the whole extrapolated length is found
and the corresponding depths determined from the typical cumulative infiltrated depth curve. A typical infiltrated depth distribution curve is then
drawn and its average value found by a procedure similar to that illustrated
in Fig. 17.2. The average depth ofwater apptied to the extrapolated length is
calculated. It is usually larger than the typical depth, and often much Iarger
on soils that crack. An adjusted cumulative infiltrated depth curve is drawn
PORII 4
as follows to reconcile the two. At the time the average typical inftltrated
depth occurs as found from the inftltrated depth distribution curve, the actual 'average adjusted depth calculated using the inflow rate, duration of application and the area of the strip did infiltrate. A new curve, the adjusted
cumulative infiltrated depth curve, is drawn on the logarithmic paper
through that point (time and depth) and parallel to the typical curve.
Evaluation of information. The basic objective of evaluation is to identify the kind and magnitude of the losses and the potential economic value of
changing the system and/or its operation. The complicated management of
border-strips is studied with two techniques; one, using time vs. distance
curves, and the other using depth infiltrated vs. distan ce curves (see Fig.
17.3).
The time vs. distan ce relationships are found by plotting the advance
and recession curves extrapolated beyond the end ofthe strip, plus an irrigation curve. This latter curve is drawn parallel to the advance curve and above
it by the irrigation time (T) the value of which is taken from the adjusted
cumulative infiltrated depth curve. This set of curves indicates how long
water was and should have been at each point along the strip, whether the
time and distance to cutoff were reasonable, whether the border-strip length
and MAD were properly interrelated, whether the stream size was correct,
738
OF FARM IRRIGATION
SYSTEMS
whether there were changes in infiltration rate (soil) or slope along the strip s
as indicated by abnormal shapes of the advance-recession curves, and the
time effects of adjusting the management controllable items of stream size,
MAD, and length. It also emphasizes the fact that for the border-strip
method, the recession curve is the primary limitation as it is unique and has a
relatively unchanging shape for each strip. Therefore, all else must be made
to conform to it.
The depth infiltrated versus distance (distribution) curve provides the
information about the efficiencies and losses. Generally it is most convenientIy plotted below the advance-recession curves to the same horizontal distance
scale. It is plotted by finding the T. at various stations along the strip and its
extrapolation, then plotting the corresponding infiltrated depths from the
adjusted cumulative depth infiltrated curve. A vertical line is drawn at the
end of the strip, and for this length, horizontal lines are drawn representing
the average depth infiltrated, the SMD, and MAD, the minimum depth
(average ofthe low quarter infiltrated) infiltrated, and a line representing the
average depth, including the runoff, applied to just the field length.
The depths represented by these lines are the various items needed for
DU, AELQ, and various PELQ's. These terms can be calculated and the
various losses and their location found. Based on this information, the
economics of various changes in the system can be studied.
Example.
From the values shown in Fig. 17.3, test No. 2 for the correct stream,
with SMD = 58 mm, MAD = 76 mm, average infiltrated depth = 80 mm,
average applied depth = 86 mm, the DU, AELQ, PELQ, runoff, and deep
percolation values are found without and with a reuse system as follows:
Vales in percerit
Parameter
Without
a reuse system
(76/80)100 = 95
DU
For SMD
tOl1
(76/80)100
= 95
(58/80)100
(58/86)100
67
80-58)/86)100
86-80)/86)100
=
=
26
7
80-58) /80)1 00
(76/86)100
88
(76/80)100
80-76)/86)100
86-80)/86)100
5
7
80-76)/80)100
72
= 28
-0-
= 76 mm
PELQ
Deep percolaRunoff
a reuse svstem
58 mm
AELQ
Deep percolation
Runoff
For MAD
With
= 96
=
6
-0-
739
011
STREAMTOO SMALL
Curves converge and upper end
Is cver-Irrlqated.
FIG. 17.4 Time and dlstance curves for border strip advance, recesslon and irrIgadon.
.....
740
Oc..rwr
Cropl k\nd
'011, \4l:t,,"
root. scr..
"
now
pre ure__
r&~
_1nd_loet.t,.
.1.D4 cUr-cU_ &tTOII' natl
to P1P1 now dlncUon
:r~~:~;
~:c~~
an
tn.
....
Fc:wth sta,p
""'
spr1nU.r 'FK1ns_1I:
__
__
d,.pt.n __
~Illl
appUr;:at.lon
ratA_
4_11\&__
...
tinten
.un..
la'tllral
....
-
s-.olJ\( -
.1 --
o!!.._
SJ7l"lnkbr't..CRup
"01.. capt
u_ .tn\rtAI.
n_
ot
\AlU. _,ln
haponUon
__
1lnlllb __
4epUu
-at-a __
, d.ur&UClftIbr_
flalah
, ...
....._d.clMl
__
hCNZ'
, ....
_
_
-------
ud
locaUm.a --;
.&.
c.___
1 -----_
-------1-------
---
----------1-------------------I ----------
--------1---------
----------1-------------------------
I --------I --------
PeRa o
741
can-catch tests that should be runo If pressure and discharge data from
sprinklers fall within ASAE recommendations, only one can-catch test need
be runo However, the two areas between three sprinklers should be used 'as
the test area for single lines and the comparable area between two lateral s for
solid sets (also see Section 14.2.4).
Can Layout. If an individual lateral is being tested, cans must be placed
on both sides of the lateral as shown in Fig. 17.5. The catchments are then
mathematically moved to a position representing set B so that the effects of
overlap can be calculated. A minimum of 20 cans with a maximum spacing
of 3 m must be in the overlapped area to give reasonable uniformity test
values.
When sprinklers are operated as a block, cans are spaced equal
distances apart between sprinklers as shown in Fig. 17.6. If a triangular
sprinkler spacing is used, they are arranged as shown in Fig. 17.7.
AIternate sets which should normally be used for single line sprinklers
are shown in Fig. 17.8 This procedure reduces the effective spacing between
lateral sets SO percent when two full irrigations are superimposed. Uniforrnity can frequently be increased as much as 15 percent through this procedure
and larger moves may become practical. To determine the alternate set
uniformity, the combined overlapped catch pattern from the design condition is superimposed on itself but offset the half move distance simulating the
second round of irrigation. When move distances are not an even multiple of
can spacings, catchment cans will not be properly spaced for direct superimposition. Interpolation is then necessary to obtain the overlap effect,
Evaporation from the catch cans varies slightly, being greater for cans
near the edge than those nearer the sprinkler which are more thoroughly wet
on the outside and contain more water. A test can set outside the catch area
with expected typical catch depth placed in it at the start and measured at
the end provides an estimate of the loss. AH cans should be adjusted relative
to this amount if it is important. Evaporation can be retarded by wiping the
interior of each can with a cloth moistened with Iight oil prior to the test (also
see Section 14.5).
Selectlon of canso Catchments in cans are usually measured
volumetricalIy in milliliters, but can be measured directly as depth in cans
with vertical sides. Plastic cups with sloping sides which can be nested for
carrying are often more convenient, but are easily blown about. The volume
caught in them must be related to depth based on the area at the rimo The
tops of the can s must be level and close to the ground.
Duration of tests. UsualIy tests are run until at least an average depth of
10 mm is caught, but the results will be more accurate if run longer. If tests
are to inelude the overall effect of changes in wind velocity and direction during an irrigation, they should be run for the fulI period of the irrigation. Long
tests with larger can catches improves measurements by reducing the reading
error associated with measuring small quantities of water.
Details of each test should be recorded on the data sheet Form S. Note
whether runoff or ponding occurred. Calculations can then be made. Accur~cies greater than plus or minus 3 percent should not be expected. It is
desirable to convert all test data to one hour duration (rate) for easier comparisons and operation calculations involving various durations.
Distrl~ution uniformity (DU). The distribution uniformity is evaluated
by measunng the amount, depth, or rate caught. If water is applied through
1,
742
Se t "A
set
743
"a"
~I
'B
:'~l
.8~
..,
~('
~c
o
.
"o
..
~I
;01
""
~
FIG. 17.7 Catch container layout lor soUd set (triangular) sprlnkler layout.
sprinklers at arate equal to or less than the intake rate of the soil so there is
no runoff, can catchments are used to determine the depth of water infiltrated. Can-catch data are mathematically overlapped to simulate infiltration from a complete irrigation at the specific move distan ce as shown in Fig.
17.5 in which Set "B" is super-imposed on Set "A" (left on right side of test
run) and illustrated in Example 1.
Example 1.
Combined Can Catches (* indicates sprinkler location)
11
2
78
6
64
4
64
80
70
70
i4
16
62
18
48
00
74
66
12
56
20
50
78
68
iD
20
32
26
30
22
30
34
48
26
40
38
74
74
8
82
[[,
Set A
64
6
70
56
8
64
Set B
b4
48
24
tt
80
6
86
FIG. 17.8 Lateralllnes offset hall move d1stance (a1temate set Irrigatlon).
NOTE:
100 = 55.6_x
100
68.2
(equati
equabon
(17.4])
= 81 percent
-r'
744
80
'
.60
""o
FF _--~
vg , LQ
= 55.6
40 _
20 -
Percentof area
*
70
68
78
66
68
70
52
56
54
64
74
60
56
72
80
70
64
86
17.8 mL
13.8
11.8
9.8
5.8
5.8
3.8
1.8
1.8
1.8
0.2
0.2
2.2
4.2
4.2
8.2
12.2
12.2
14.2
.16.2
148.0 mL
148.0{20 =
7.4 (average
deviation)
1364{20 =
68.2 (mean)
. 68.2-7.4
68.2
ue =
100
= 89 percent
Coefficient
39
45
52
59
66
74
83
92
60
65
70
75
80
85
90
95
DU vales leave about 1{8 of the area at less than the numerator vales of LQ
average. (see Fig. 17.9)
UC vales leave about 1{4 of the area at less than the numerator valu of average average devia'ti n.
*"
80
68.2 mL
1364 mL
Low quarter DU
distribution uniformity
Christiansen's UC
uniformity coefficient
Deviation
from mean
Mean
86mL
82
80
78
74
74
72
70
70
70
68
68
66
64
64
60
56
56
54
52
_-
'"
Can
catch
~l _:_
11
745
74
NOTE:
The can catches have been arranged sequentially below and on Fig. 17.9 for
ilIustration but this is not essential.
average catch
.........................................
(equation
[17.5a])
Potential application efficiency (PELQ). The PELQ is the only term that
is used in design to calculate the gross depth of water to apply at an irrigation. It indicates how effectively a given sprinkler system can apply water
under optimum management neglecting prenozzle losses and leaving about
1/8 of the are a under-irrigated. (If it is desired to under-irrigate more than
the 1/8 of the area resulting from using the average of the low quarter,
Iighter applications can be made.) The difference between the water applied
(as measured at the sprinkler nozzle) and the water caught is an approxirnation of evaporation and drift losses plus water not accounted for due to part
ofthe area being ungauged (also see Section 14.2). The PELQ indicates how
efficiently the tested system can apply water if the system is run the correct
length of time to just satisfy the MAD. It is, therefore, a measure of the best
that management can do and should be thought of as the potential for the
system under the tested conditions to the extent that the tested area is
representative of the field.
746
OF FARM IRRIGATION
SYSTEMS
Example 3.
Combined Can Catch Rates (* indicates sprinkler location)
*
8.9
8.4
7.6
7.1
7.3
7.4
O <O> ([])
8.1
<O> <O>
8.9
7.6
7.1
8.1
7.6
7.1
7.9
9.4
..
0.41 L/s X 3600 s
average application rate = 122
= 8.0 mm/h
. m X 15.2 m
_ (96.3 X 6.5 gal/min . /h
40 ft X 50 ft
- 0.31 m.
PELQ = avg. LQ rate or depth of water caught
avg, rate or depth applied through sprinklers 100
(equation
[17.3])
6.0 100
= 8.0
= 75 percent
The water lost to evaporation, wind drift or otherwise unaccounted for is the
different between the average rate applied and the average rate caught. This
is:
8.0 - 7.4
100 = 8 percent
8 .0
AdditionalIy, the prenozzle losses from line drainage and leaking gaskets
amounting to 3 to 5 percent of the water delivered, need to be considered.
Actual application efficiency (AELQ). The AELQ requires that the soil
moisture deficit be known since this is the maximum depth that can be
stored. The actual applied depth neglecting prenozzle losses is calculated using the application rate for the duration of the set (T.).
Example 4.
SMD = 114 mm, Ta = 23.5 h
AELQ = avg. LQ depth of water infJtrated and stored 100
average depth of water applied
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (equation
AELQ =
114
8.0 X 23.5100
114 mm SMD
_
188 mm applied 100 - 61 percent
747
NOTE:
1. All readings in rate mm/h from a
test of 1.16 h
2. Sprmkler spacng 12.2 m X 15.2 m
(40 X 50 ft)
3. Crcled catches indicate inclusion in
LQ.
4. Sprtnkler Q = 0.41 L/s (6.5 U.S. gal/
min)
........................................
[17.2] )
T.=
1
SMD = 114mm
LQ rate
6.0 mm/h
=19.0h
or ifthe SMD were made equal to an MAD of(6.0 mm/h) X 23.5 = 141 mm
(5.6 in.), the AELQ would equal PELQ assuming that wind, humidity, etc.
for the day were typicalIy represented by the short duration test.
17.3.6 Center Plvot Sprinklers
The center pivot sprinkler system consists of a long pipe supported on
towers fairIy high aboye the ground to pass over talI crops. Each tower has a
drive motor so that the entire line rotates about a central pivot point at which
water is forced into the pipe and sprinklers. Because of continual movement
of the system and the engineered placement and size of the sprinklers, a very
high distribution uniformity of about 90 percent is possible. On long lines,
300 m or more, the rate of application at the outer end may be greater than
the soil intake rate and runoff may occur. On large fields adapted to this
method, there may be appreciable differences in elevation which will affect
relative pressures. Because the system rotates, and the fact that the system
can be set to pass over different areas during any windy period, the bad effect
of wind on the pattern is mitigated. Evaporation losses in the air may be
higher than other sprinklers because of the height of the system, the losses
are different in the daytime wetted areas relative to the nighttime areas which
may be important in sorne locations. These items need to be considered when
estimating the system PELQ.
Because of frequent applications, evaporation losses from the soil may
be greater than that of other systems. The SMD is not measurable in the normal manner between irrigations. Over-irrigation and a low actual application
efficiency can occur if the system is operated too often. Under-irrigation
often is planned so that a soil moisture deficiency gradualIy accumulates, but
because of frequent, even daily irrigation, only slight decreases in yield result
with many field crops. Special evaluation techniques normalIy are required
to evaluate the effectiveness of center pivot systems (also see Chapter 14).
17.3.7 Giant Sprinklers
Large diameter nozzles operating at high pressures may discharge water
75 m or more. Because of the long range and high trajectories of these
sprinklers, which depend on overlap for uniformity, they are greatIy affected
by wind and normalIy have a low distribution uniformity of about 60 percent.
However, since they are commonly used to supplement rainfalI which applies
water uniformly, the low DU may be economical. They are not well adapted
to arid-area irrigation. AIso because of the large diameter coverage, they
create poor application conditions on a wide strip along the periphery of
fields where overlap is not feasible (also see Section 14.6) .
17.3.8 Traveling Sprinklers
Traveling sprinklers are similar to giant sprinklers, but are often
operated to provide part circ1e coverage. They have the advantage of higher
distribution uniformity due to the continuous movement so that DU values of
748
749
750
downstream sections will reduce the ponding and permit submerged flow, require two depth measurements (also see Section 9.2).
The small portable flumes used for evaluations seldom have sight tubes
for measuring depths or differences in depths. Staff gauges marked on the
side of the flume rarely can be read with adequate precision. The best way to
obtain the necessary accuracy is to use a point gauge to measure down from a
datum established usually at the top of the flume. The depth should first be
measured down to the bottom ofthe flume and then to the water surface. The
difference is then the desired depth. A simple point gauge can be made using
any scale with adequately fine gradations and firmly attaching a short piece
of wire to it with tape or a rubber bando Precision to 0.5 mm is desirable. A
thin stick gauge can be used to measure the depth in the flume directly but it
is often hard to read precisely.
The easily-made flat bottomed vertical sided cutthroat flume is satisfactory. Flumes with sloping sides lose accuracy with increasing depth and so
are less preferable.
Orifices and tubes, Orifices, short tubes, and irrigation siphons can be
used to measure flow by measuring the head and cross-sectional area.
For orifices and short tubes when the head measured from the center of
the opening to the upstream water surface for free flows is greater than the
diameter, good accuracy is obtainable. However since the flow is a function
of the square root of head, appreciable ponding may be needed upstream for
fairIy small increases in flow. Orifices are adapted for use at the upper end of
a furrow when flow is constant and the necessary head can be obtained. A
series of orifice piates may be needed to obtain the desired range in flow with
reasonable head.
At the outflow station for intake tests the orifices desirably operate
submerged with the difference in head being measured. It may even be practical to excavate the bottom of the furrow to obtain adequate submergence if
erosion does not make it impractical to keep the depression from filling in.
Round orifices do not need full clearance on the bottom so they can be set
within a half diameter of the bottom and still be adequately accurate.
Because of the increasing flow rate passing the lower measuring device
with time. a series of increasing size piates can be set and the smaller ones
pulled out in sequence when head becomes exc~ssive. Whe~ the p.l~tesare set
fairIy close together, the increased furrow section length IS negligible.
Flow rates in orifices are caJculated from the equation
Q = CA (2gh)o.s
~-7-:-'rl:'+'-;-:;.,.;'t':
l' ,
.c-J:""
. +-,1
'1+.+-.,,",1n+~*:'~+' ..p:~'i:jH'iI::,!-,W;+.:+.:;~.g. ;;rnl*-IfLf-j,:i'14:'~'+';'iJlll~~:itr/4.:PjJ-.-,-4":''-W-'-I-i
1:
.l:...
I :
:1: ::tI.
p:::: 1:; : ~
... . 1 1:::1::::
,....[.:..
.O/~~~~~~~~~L-~~~~-L~~~~~~~~-L~~~~
1:.:1:1
1:::, r.
'5
11
IJ: []:}
::.
.1
, 2
'!J
0.5 G\)
NumH"
FIG. 17.10 Powers and roots of numbers flow rates of Parshall flumes and slphons.
.OJ
.02
.0 I
751
[17.12J
For sharp edged orifices which exist for holes drilled in t~e plates ~ varies
from 0.61 to 0.63. A is the orifice area, h is head, and g IS the gravity constant all in units consistent with the flow units.
.Short tubes (lOO-mm) with lO-mm radius rounded entrances set into a
face plate which can be set across a furrow, function similarly to orifices but
have greater capacity for an equal sized opening. Flow for them is given by
the equation
Q = CAK (2gh)o.s
[17.13]
where both C and K are for practical purposes equal to 1.00. The tubes can
be circular but are best made rectangular with widths of 30 to 100 mm. The
1I
752
depth should be shallow, e.g. 30 mm, so that they can easily be operated
submerged in fairly shallow furrows with very little upstream ponding.
Orifices and short tubes are convenient to use since the plates are easily
installed by setting them in a trench if the soil is dry and hard, or they can be
pressed into wet soil. For submerged flow they need not be set truly vertical.
Siphons can be used as measuring devices as well as for water distribution. They function similarly to short tubes with a projecting entran ce so C
and K are less than 1.00, but flows are proportional to the square root of
head. Different entrance shapes and tube material will cause minor changes
in flow rates so they are usualIy empirically calibrated. A graph of Head vs
Flow is included on Fig. 17.10.
A difference in head is needed to obtain flow rates through irrigation
siphons, short tubes, and orifices. For siphons and tubes this can be most
conveniently measured by using a 1.5- to 2.0-m length of plastic tubing 2- to
3-mm in diameter. It is helpful to have a short piece of metal tubing on the
inlet end ofthe plastic tubing to hold it in place. Graduations may be marked
on the outlet end but a small scale is often as practical. The tubing is filled
with water and allowed to flow as a siphon around the equipment being
measured to be sure aIl air is c1eaned out. The lower end ofthe tubing is then
held verticalIy aboye the downstream water surface for submerged conditions
or adjacent to the equipment for unsubmerged outlets. The rise in elevation
of the water level in the tubing aboye the downstream water level for
submerged flow, or aboye the center ef flow for the free flowing condition, is
the head to be used to calculate the corresponding flow rate.
The difference in head can also be measured using a carpenter' s level or
a comparable device with a spirit level on it. A stick can then be extended
from the upstream to downstream side and set level. The depth to the desired
points at each end can then be measured vertically and the difference found.
The use of a surveyor' s level is practical but seldom convenient.
For the small orifices used in evaluations it is practical to measure the
head directly on the orifice piate on one or both sides as needed. It must be
measured vertically.
Weirs. Weirs may be used for furrow evaluations but because of
decreased accuracy caused by large flow increases with small head increases,
and the need to measure head sorne distance away from the crest, it is more
difficuIt to obtain precision with them.
The 90 V-notch weir is the only practical one used for small flows. The
equations for it is
Q=CH2.S
.........
[17.14]
where C is 2.5 for flows in cubic feet per second and 1380 for flow in liters per
second, and H is in feet and meters respectively.
Special shaped weirs essentially combining the orfice and weir conditions, can be made and individually calibrated. A narrow weir decreasing in
width towards the top will provide a flow vs depth relation that is nearly
linear. A set of several sizes may be needed. They need to be individually
calibrated. They, like the orfice plates, can be set in sequence and as flow
and head increase, the smaller upstream pIates can be removed.
Volumetric. A volume in a measured time interval is probably the most
precise method if the time duration is adequate so that it can be measured
precisely. A stop watch rneasuring the O.l-second or 0.002-mi~ute is
753
desirabIe. Containers that fill in less than five seconds tend to cause imprecise values. Such flows usually entrain much air and sorne overflow must
be allowed to compensate. Three or more measurements can easi1ybe made
and averaged. It is desirable to have two people cooperating with the watch
and container, one of whom should make a countdown to be sure of a common starting time.
The stream flowing into the container must be free flowing. For flow in
furrows, a hole usually must be dug to hold the container under the jet from
the gated pipe, siphon, or spile.
17.4.3 Border-strip and Baslo Devices
Border-strip and basin systems require large streams and correspondingly larger measuring devices.
Siphons and flumes. Where siphons or flumes are used, the earlier
discussion under furrows is pertinent except for size.
Weirs. Weirs can be used for flow measurements where the water can be
concentrated in one location. For large areas, several weirs may be needed.
Rectangular weirs are useful. Cipolletti trapezoidal weirs have no advantage
for shallow depths. Weirs must have adequate c1earance below the crest on
the upstream side to have a standard bottom contraction. Two times the
head or more is desirable. To obtain this may require an appreciable ponded
depth, or a tren eh of adequate depth and five times the head in width may be
excavated adjacent upstream to the weir. Clearance at the ends of the crest
should be about three times the head. The jet from the weir should fall freely
so downstream depth offlow will not back up to the crest ofthe weir though a
little drowning-out will not greatly affect accuracy.
The depth over the crest should be not less than about 15 mm. The weirs
for this purpose may be quite long and shallow to permit large flows with
small heads. They may even have a little horizontal curvature to provide stiffness against overturning.
For shallow wide flows the end contractions are of little importance. but
the crest ofthe weir should be leve!. If it is not, the length may be broken into
sections and a representative head used for each section.
The flow equation used for wide rectangular weirs is
Q = K (L - O.2H) H1.S
.. '
[17.15]
K = 3.33 where L and H are in feet and Q is in cubic feet per second. For
corresponding SI units K is 1840, where L and H are in meters and Q is in
liters per second.
Jet trajectory. Trajectory of a horizontal, or nearIy so, jet may often be a
simple and practical measuring device where flow from the end of a pipeline
is accessible. For full flowing pipes the velocity of flow is equal to four times
the distance (L) from the end of the pipe to where the jet has dropped 1.01
feet or 0.308 m which occurs in 0.25 second. The drop and distance would
theoretically be measured at the centerline of the jet but the top surface gives
reasonable accuracy. The area ofthe pipe (A) should be calculated in square
feet or square meters. The product of the velocity times area gives flow rates
(Q) in cubic feet per second or cubic meters per second. Tables are available
for pipes flowing partially fuIl.
Q=4AL
........................................
[17.16]
754
Vertical jets occur from pipeline valves such as orchard valves. Approximate flow rates can be found for small heights where the pipe rim acts essentially as a weir. When the rise (H) is less than 0.4 of the pipe diameter (d)
Q= 8.8 d1-I1.S
[17.17]
[17.18]
[17.17a]
[17.18a]
and
For H values between 0.4 and 1.4 d, the flow rate is a little less than that
given by either equation. Because of the distortion of the vertical jet by the
valves and the pipe therefore not flowing full, both equations probably give
higher than true values. The jet is generally rather unstable so values of H are
not very accurate.
Other devices. Additional flow measuring devices may sometimes be
useful in ditches or pipelines that can be equipped with them. In ditches current meters, surface floats, moving vertical sticks, etc., may be used to determine velocities in several sub-section areas of the cross section and then their
product totaled to determine the flow.
In pipelines, a variation of pitot meters are often used. Also visible
fluorescent dye at a few parts per million may be injected to observe the
velocity. Various other types of meters for rate or total flow volume are
available but they are usually permanently installed.
Sometimes measuring devices may be improvised based on sorne
hydraulic characteristic such as constrictions or critical depth; or the stream
may be proportionally divided if the total flow is known. The flow
measurements may often have to be made in the supply system rather than at
the point of application in the field.
17.4.4 Soil Moisture Infiltration and Deficiency Measurements
Efficiency approximations can be made from simple observations of
conditions. However in order to obtain numerical values and information for
design or comparison, test of the soil infiltration characteristics should be
made when conditions representing the usual irrigation conditions existoThis
would typically be when the top 10 cm of soil is at about wilting point, which
occurs at about a 50 percent MAD. Moist soils or soils that have wet surfaces
as from a rain, will have a much slower initial infiltration rate. Soils that are
excessively dry may have appreciable open cracks and normally may need to
be irrigated before they thoroughly dry out to mitigate cracking. The soil
moisture deficiency conditions of the surface and the profile of a tested soil
must be recorded as part of the measurements.
There are two different conditions under which irrigation water enters
the soil. They require different measurement methods. One condition is call-
755
ed intake which is that from shaped areas such as furrows where the ~ate
depends on the furrow shape and size and i~volves}ateral as w~ll as vertical
flow. The second condition is called infiltration which occurs with a flooded
surface and the flow is vertical.
Water moves in a soil downward by gravity and capillarity. It also moves
laterally and upward by capillarity where shape permits it. Because of the
high energy difference betwe~n the dry. soil near the surface andot~~ f~ee
water on it and the corresponding short distance between them, th: l~~ttal 10take rate is very rapid. Gravity plays a relativ~ly s.m~llpart of the initial r~te
except in coarse soils. As the length ofthe capillares mcrease and t~e w~ttmg
front reaches moister soil the infiltration rate decreases as the capi1la~ttyeffect becomes smaller and the gravitational effect plays a proportionally
greater part until final1y it essentially becomes the only ~orce.
The infiltration rate, or the intake rate for the specific tested length of
furrow, generally can be described by the equation
...........................
'
. [17.19]
and from the integration the cumulated infiltration depth or the intake depth
on unit width of 1.0 foot or 1.0 meter of furrow by
D = K' Tn+1 + CT
....................................
[17.20]
756
OF FARM IRRIGATION
SYSTEMS
and n, but structure, the resuIt of natural or cultural processes, often great1y
modifies the numerical values from typical textural values.
Furrow intake tests. The intake measurement is done by measuring the
inflow and the outflow rate at the two stations. Suitable flow measuring
devices are set in several furrows having different typical flow rates. Theyare
set at measured distances apart, 30 m (100 ft) being typical. The setting and
flow measurements must be carefully done as described in Section 17.4.2.
For slow intake soils the spacing may be longer or two furrows may be combined if each furrow carries about equal flow. If the soil at the upper end of
the furrows is typical, the upper device is set at the upper end ofthe furrow so
that the inflow rate can remain constant.
For soils that crack or have a loose layer over a plowpan permitting abnormal lateral flow, adjacent furrows must be run and it may be very difficult
to have access to and make measurements at the lower device. Where access
becomes too difficult, the entire furrow length can be used. However values
can only be obtained after water has advanced the furrow length so the early
part of intake is not measured. By utilizing the "adjusting" procedure a
curve can be developed but the high initial intake rates will be approximations as the dry dog-Ieg effect can only be conjectured. This means that the
presumed instantaneous intake rate is an average of appreciably different
rates. For normal soil conditions, it is more convenient to run aIternate furrows to provide a walkway for access to the lower device. Entries called for on
the Furrow Intake Test form (Form 2) should all be made. The zero starting
time for making measurements s when the stream has reached half way to
the second station since this will closely represent an average time on the section. The second rate and time measurement is made simultaneously (or
nearly so) at each station when the flow is three to five meters past the second
station. Several readings should be taken at short intervals of three to five
minutes, and then at increasingly longer intervals for the duration of irrigation (TI) or the time of advance (T.dJ whichever is larger, and at least eight
readings should be taken. They must be taken with appreciable precision
since the difference between them is presumed to be the intake rate at that
momento The precision of the readings should be determined and recorded
so that the "range of accuracy" -the plus or minus of the precision of the
readings-can be plotted on the intake rate curve.
Utilizing the "range of accuracy" in plotting the instantaneous intake
rate points, is often essential to make the field data useful. Because the difference of inflow minus outflow often may be small (dealing with small
numbers), ignoring the accuracy ofthe two readings may result in misleading
numbers. By plotting the points with their plus or minus accuracy to
establish a range, a straight line can almost always be drawn. If the points
are plotted as the data is taken, poor sets of readings become obvious and
can be redone.
Tests should be run on several furrows. The results should not be
averaged. Each line should be drawn separately as different conditions may
be affecting the results. However they are all expected to be parallel. Soil
structure in furrows is often different because of location of tractor wheel
travellanes. In orchards, furrows adjacent to trees may have twice the intake
rate of those in central portien. Different stream sizes giving different wetted
sections will have sorne effect, more so in V-shaped furrows than in parabolic
or broad ones.
757
The intake rate plotting and equation are not related to furrow spacing
but the plotting of the cumulative intake depth curves and the equations
must be related to the specific furrow spacing being studied assuming that
water is stored in this width. Since change in furrow spacing is one of the important management controlled variations affecting duration of irrigation,
several spacings should be studied for their effect. This is done by finding K;
values for the various spacings.
Care must be taken with units for the equations. Intake rates for furrows
are usually expressed in gallons per minute per 100 feet and liters per minute
per meter. There is no width implied for these rates.
When integrating these rates to cumulative depths, area (width) must be
considered as well as the conversion constants to obtain the usual depth units
of inches and millimeters in the equation
D=K~Tn+1
[17.21)
...............................
[17.22)
To convert liters per minute per meter to millimeters depth with a given
furrow spacing in meters
K' = K(L/min-m)
s
(n+1)S
....................................
[17.23)
Cylinder infiltration test. Where water is applied over the entire soil surface such as for border-strip or basin irrigation, single cylinder inftltrometers
provide a comparable vertical flow condition only iftheir diameter is 250 mm
or greater and they are driven at least 150 mm deep. Double ring or buffered
cylinders with water level maintained on both sides are sometimes used but
seldom provide more accuracy. For soils that do not crack, the inftltration
depth from the cylinders may relate fairly closely to the field conditions.
More commonly they must be "adjusted" as described in Section 17.4.2 since
the small sampled areas seldom represent the actual conditions. Tests must
be made when the soil moisture deficiency (SMD) is about the same as when
as irrigation should be applied since the infiltration rate varies with moisture
contento The rate often also decreases with lateness in the season as the soil
structure becomes modified.
At least four cylinders varying in diameter from 250 to 300 mm so that
they can be nested for carrying, about 400 mm long, and having a wall
thickness of about 1.5 mm, are driven into the ground at least 150 mm. They
are usually driven into the soil by a heavy (lO to 15 kg) hammer driving
against a 6-mm thick plate about 0.5 m square laid over the top of the
cylinder. The operator stands on top ofthe plate to add weight and drops the
hammer to do the driving. The cylinder should be driven straight without
wobbling to reduce the size of any crack s around the perimeter. After driving
any small crack that does occur should have the soil pressed down to block it.
The test location should be selected to represent as typical a condition as
possible and all four, or more, cylinders should be in a small group. Unusual
Ii
758
soil conditions such as cracks, cow prints, tractor wheel paths, etc., should
be avoided.
The procedure consists of selecting a datum on each cylinder. This may
be a point on the top or a mark made inside at a more convenient depth. A
scale with a point that will reach the ground from the datum is needed. The
point may be a short piece of wire taped to any convenient scale. A point is
preferable to a hook which does not permit the measuring of the lowest part
of the water depth. High accuracy is not needed for measurements so
readings to the nearest 1 mm is adequate.
Before water is poured into a cylinder, protection from possible erosion
must be assured. Existing sod may be adequate, or a piece of cloth or paper
may be laid in the bottom. The information on the heading of the Cylinder
Infiltrometer Data sheet (Form 4) should be filled out and the cylinders identified usually by their diameter. Since several cylinders are to be tested, a
stop watch is not desirable nor is it needed for accuracy.
At a convenient full minute water is poured into a cylinder to a depth
corresponding to the typical ponded irrigation depth usualIy about 100 mm,
the protective cloth removed, and a depth to water surface measurement
made as soon as possible, usualIyat 15 to 20 s. The depth and watch time are
recorded. On very high intake rate soils a second depth reading at 30 s is
desirable. Under normal conditions the next reading is taken at 1 mino
Subsequent readings should be taken at about 2,.'4, 7, 10 min and increasingly longer intervals to provide three or four points for each cycle on the log-log
papero The test duration should be as long as needed to apply an irrigation
but may be less as long as a straight line graph is welI established. After the
first cyclinder is welI started, a second may be started.
For sorne high intake rate soils, it may be necessary to add water. This is
done immediately after taking a normal reading. The new refilled depth is
recorded as though taken at the same time as the normal one was taken. The
change in depth is ignored by leaving it blank on the formo
The cumulative times and depths are desirably plotted for each cylinder
as the data is taken. Errors in measurements become obvious and new
readings can then be taken. The plotted lines should be straight though often
with a flatter or steeper dog-Ieg section in the first part. The plots from the
adjacent cylinders will rarely coincide because of variations in the small
sampled areas. They should not be averaged but each should be looked at as
identifying sorne characteristic of the sampled area. It is usual that the "adjusted" curve is aboye any tested cylinder.
Typical infiltration values for soils are shown in Fig. 17.11. Arbitrarily
selected values, but which are representative of many tests, represent various
infiJtration groups. The USDA Soil Conservation Service intake family
curves are shown and also the comparable c1assification of time-rated curves.
The latter are designated as to how many minutes it takes to infiJtrate 100
mm (4 in.) which corresponds to a typical depth of irrigation. It therefore has
the advantage of having a physically related name. It has a further advantage
that variations in the slope (n + 1) of the line do not cause a great effect on
the cumulative intake for values in the normal irrigation range of 100 mm
plus or minus 3S mm. Broad textural classifications shown must be used with
caution since structure has appreciable effect. A great deal of caution must
be used when reading the curves for cracking soil.
Soil moisture deficiency. For all evaluations of actual irrigations practices, the soil moisture deficiency (SMD) must be known to obtain the actual
759
TIMERU'ED 100 mm
ses
(4.0
ln)
and
INTJKE FU:ILIES
50 2
30
10
1000
100
time
mlnutn
FIG.17.11
and
wiltlng point.)
011/)00ln/ft
O -
O. O
(Fhld capacity)
L:!!!:
:r:~:rln.ion:!:!:
:r:~~IIn.
Le.v....
t ol11:11n.
on h.&nd, .. 111 rlb'bon
on h.and .men
hand. ....
.qu ....
Appearl
Mil....
10 -
.4
.8
IK)ht,
ball
!:r.~;~!r.tlY
toC.th.r
20-
IU&ht1y
rlbbon
about
QI.l1
..tl
aU"
dar)l: color,
bard ball
Darll: color,
tor.. a
pla.t!c
b&ll, .11cll:. Dark color,
_hin rubbed
and ribbon
Palrly
..a
dark color
cood ball
IS ..
(Phld capaclty)
lA.v Illght .obture
on hand _hIn Iqueeud,
_111 ribbon out about
50 ..
lhort
Qu.ite dark.
hard lILll
toral
Dry. loo".
tlo ..
through finger.
(w11Ung polnt)
)0 -
Sl1Chtly dartlto~.
...u bal1
1.2
v.ry a11ctrUy0010"d
due to eol.tlU"t
(_llt1ng
polnt)
40 -
1.6
50 -
2.0
Lil,htly c010"d.
.a&l.1 cloda Cr\lIIole
lairl)'
. 11y
0-0.0
20-
-.t.
dark,
cLcde
Sliebtly oolo"d
du.
to .obtu",
a.all
cloda are hard
So darlm du. to
(_11Ung polnt)
unavaUable ec e tur-e ,
clod. are hardl craclr:ed
(_11tlng polnt
50 -2.0
ASA.!)(
1 >. "vil.eS
1n
197.5>
10U
J.
L. 1960. TRANSAC1'IONS
al
.4
.8
760
an irrigation when using a 50 pereent MAD. Take the soil samples placing
eaeh 30 cm sample in sequential piles or row and protect them from the sun.
Use the chart for the correet soil texture and correlate the description with
the SMD for each sampled layer. It should run the range from wilting point
for the top sample to nearly field capacity for the bottom of the root zone.
Sampling to the bottom of the root zone a couple of days after irrigation
is the only way to assure that adequate water has been applied to replaee the
SMD, or whether too mueh has been applied. Such a check should be made
every few irrigations regardless of how the SMD was measured or estimated.
References
1 Merriam, J. L. and J. Keller. 1978. Farm irrigation system evaluation: A guide for
management. 3rd ed., Utah State Univ., Logan, 28S p.
chapter
18
IRRIGATION WATER
MANAGEMENT
18.1
18.2
18.3
1804
763
775
787
801