Professional Documents
Culture Documents
p/ g + v 2 /2 g
+z
(1.1)
When there is the difference between the energy of water, the difference in the energy can be
efficiently converted into useable energy by using hydropower plant. The energy at the intake of
HPP will be high and the exist from the HPP will be low thus the energy from the water will be
obtain as follow.
Power (Energy/sec) = (
p/ g + v 2 /2 g
+ z)intake - (
p/ g + v 2 /2 g
+ z)exit
(1.2)
There will be some loss of power during conversion from the available water energy by using
hydropower plant. Those loss are expressed in term of efficiencies. Finally the power that can be
generated by HPP is expressed as follow.
P=gHQ
(1.3)
Where,
P = electrical or mechanical power produced, W
= density of water, kg/m3
g = acceleration due to gravity, m/s2
H = elevation head of water, m
Q = flow rate of water, m3/s
= overall efficiency of MHP system
Thus, equation shows that, power generated by the water available depends upon the amount rate
(flow rate of water), elevation head (elevation difference between intake and exist of water),
gravitation force, density of water and efficiency of the HP system. Thus by using HP plant,
available water energy will be converted to the useful mechanical/ electrical energy as an output.
2.2 Classification of hydropower and end uses
Energy available in water will be converted into useful energy like mechanical or electrical energy by
using Hydropower plant. HPP can be classified according the generation of electricity, type of
storage, type of distribution grid system, type of load capacity etc. There are wide variety of HPP it
can be classified in different ways.
According to the electricity generation HPP can be classified according to following table 1.1. there
may be few variation in power generation range according to the useful situation and norms of the
particular country.
Table 1.1 Classification of HPP according to the power generation capacity
Power generation capacity
Less than 100 KW
100KW to 1000KW
1MW to 10MW
10MW to 300MW
300MW to above
According to the type of storage type HPP can be classified into storage type and run of the river
type. The storage type of HPP consists of dam to stop the flow of water in the river stream. There
will be big reservoir behind the dam to store water. The reservoir stores rain water too. This type of
HPP supplies water continuously to the plant and there will be no flow variation during dry season.
These plant are generally costly, complex to design. This is generally used for small to larger HPP.
For MHP storage type HPP is not used.
Run of the river type HPP does not stops the river stream but it diverts water into the water way of
HPP. There will not be any reservoir in these type of HPP. Flow of water in this type of HPP may
vary according to the seasons. These type of HPP is less costly and environmentally friendly. These
type of HPP is generally used for micro, mini and small HPP.
Forebay tank
Pressure pipe leading
turbine (Penstock)
Turbine
Stream
Storage reservoir
Turbine enclosed
River flow
Tailrace
Flood spillway
Power house
Regulating gates
Intake
Anchor
Spillway drain
Penstock
Penstock support
Wing walls
Sand trap
Channel crossing
Channel
Forebay tank
Settling
Outlet
Top view
Spillway drain
The purpose of desanding basin is to trap sediments so that these do not enter the canal. The de-sanding basin is, as a
rule, built at the head of the canal and it is regarded as a part of the head works. The de-sanding basin
is wide and long pool designed to settle the sediments carried by the diverted water through reduction
in the speed of water. Most de-sanding basins are designed to settle particles above 0.2 0.3 mm.
De-sanding basin is provided with a sediment flush in order to reduce the cost associated with its
cleaning. During the rainy season daily flushing of the de-sanding basin may be required.
Flood flow
hsp
hflood
Design Flow
Longitudinal section
Cross section
in case of sudden valve closure at the powerhouse Such overflow may continue for long time if the
canal intake is not closed.
Air vent
Fine trashrack
3
300 mm
minimum
Penstock
hs
Spillway
1
Gate
Compact earth
2.3.6 Penstock
A penstock is a close conduct pipe that conveys the flow from the fore-bay to the turbine. Penstock is
made of steel or HDPE, and rarely of timber. Recently PVC penstock has also been introduced. If
HDPE penstock is prevalent at lower heads, steel penstock is prevalent at higher heads. The MHP
head varies from a few meters to over hundred meters. Ghandruk MHP of Nepal, has a head of 220
m, which is the highest in Nepal among MHP. Mild steel and HDPE pipes are the most common
materials used for the penstock in MHP schemes. HDPE pipes are usually economical for low heads
and flows and are easy to join and repair.
The conversion of potential energy of water into kinetic energy takes place in the penstock. The
typical velocity of water in the penstock is around 3 m/sec. In order to reduce the head loss in
penstock it is desirable to make the penstock short and less bends. For this purpose penstock is
located in a steep slope, which is very often over 45 too. Above ground penstock pipes are subjected
to expansion or contraction in length as a result of changes in the ambient temperature. A sliding type
of expansion joint, is commonly used in MHP schemes. It can be placed between two consecutive
pipe lengths and can either be welded or bolted to the pipes.
Anchor blocks are used to holds the penstock to restrain the pipe movement in all directions. It is a
mass of concrete fixed into the ground. Support piers are short columns that are placed between
anchor blocks along straight sections of exposed penstock pipe. Support piers prevent the pipe from
sagging and becoming over stressed.
Penstock gate
Expansion joint
Vent pipe
Power house
Pipe joint
Valve
Side block
Anchor block
2.3.8 Tailrace
The tailrace is the final civil structure that conveys the design flow from the turbine (after power
generation) back into the stream, generally the same stream from which the water was initially
withdrawn. Similar to the headrace, open channel or pipes can be used for the tailrace section.
2.4 Turbine
2.4.1 Introduction
A hydraulic turbine is a prime mover that uses the energy of flowing water and converts it into the
mechanical energy (in the form of rotation of the runner). Science ancient time turbines are used
under the name of water wheels, made out of wood. The water wheels have very low efficiency and
short life.
There are different types and sizes of turbine available but the particular type and size for the
particular site is determined by,
Particular speed of each turbine rotor at which it performs best is called its optimum speed. The
turbine needs to be operated at this speed at all loading conditions to get the maximum output.
2.4.2 Types of turbine
Principally, according to the working of turbine it can be categorized into two types, as impulse
turbines, and reaction turbines. Under these two main categories there comes many types of impulse
turbines which can be selected for given site.
Impulse Turbine.
There are three types of impulse turbines known as Pelton turbine, Turgo turbine and Cross flow
turbine. In these turbines the rotor rotates freely in atmospheric pressure. The rotor is never be
submerged in water of the tail race. It is kept above the tail race water level and the nozzles of these
turbines are free jet type. In this turbine pressure energy in water is converted into kinetic energy
when water passed through nozzle. Free high velocity water jet impinge on the bucket mounted on
the periphery of the runner. Impulse force on the bucket rotates the runner and shaft of turbine.
Reaction turbine
In reaction turbine s rotor remains immersed in water all the time and water acting on wheel is under
pressure which is greater than atmospheric pressure. Draft tube is an integral part of the reaction
turbine fitted at outlet. It runs by the reaction force of the exiting fluid. Potential energy and kinetic
energy of the fluid come to stationary part of turbine blades and partly changes potential energy and
kinetic energy. Moving part (runner) utilize both potential energy and kinetic energy of water.
2.5 Design Parameter:
2.5.1 Hydrology and site survey
Preparation for site survey
10
MHP plants are designed to produce electrical and mechanical power from water power. The power
is generated according to the demand of the local community. It is necessary to carry out survey to
collect information of power demand and willingness to pay for that. The sight survey should be
done for the MHPP potential to the demanded generation. Proper performance of the survey leads to
the success of the whole MHP schemes.
Adequate and accurate survey work is essential if the MHP project is implemented is to be
successful. Survey should included both technical and socio economical issues of the project.
Demand survey is mainly concerned with the counting of households and other potential consumers
(shops. lodges, offices, temples, schools, industry), who are ready to commit themselves to receive
power and pay for it, and with calculating the total demand for power. The survey can be conducted
before the comprehensive meeting or even before the reconnaissance of survey.
Appropriate time for survey should be selected. It is prepared to perform survey during dry period
with not much rain or cold or hot seasons or according of the specific site conditions. Documented
information about hydrology, geology, social structure of the selected site could be obtained from
different sources previous to the survey. It is very useful to acquire to collect topographical maps for
the project area. It is better to allocate experienced survey persons with helpers from the local
community. Generally the method to be used for survey should be done beforehand and list of
equipments for that should be carried or transported to the project site.
Map study of site
The objective of field survey for MHP project is to obtain necessary data and information of the
identified hydropower site and the electricity supply area to carry out the technical feasibility and
financial viability of the project.
Maps help to develop ideas and methods for the technical survey. It helps to design and locate water
intake, water way, fore-bay, power house and transmission system. Accurately design and locate all
the components of MHP plant will be formed after different stages of survey. Maps, chart or data for
climatic condition, ground condition, plantation, government policies are important tools for the
success of the project.
Meteorological data analysis
Power generated from energy plants mostly depends on flow conditions of the river streams. River
stream condition is affected by the meteorological condition of the site. Data obtained in the survey
is co-related with the previously existing data to develop data bank. More the wider data on the data
bank more will be reliability of the meteorological out put data. It is important to get meteorological
information of many years as possible.
2.5.1.1 Site survey
Site survey includes flow measurement (preferably during dry seasons), determination of head
needed to generate required rated power, land survey (including slopes and distances), location of
different civil components so that rated power could e generated.
Head measurement
11
The head in MHPP is determined by the location of he powerhouse and the fore-bay, which also
determine the route of the canal and intake. The surveyor should first calculate the value of gross
head required from the simplified power equation,
P=gHQ
(1.1)
Where,
P = minimum present power demand plus losses, W
= density of water, kg/m3
g = acceleration due to gravity, m/s2
H = elevation head of water, m
Q = flow rate of water, m3/s
= overall efficiency of MHP system
The surveyor then starts by tentatively selecting a suitable site for the powerhouse and the fore-bay
and measuring the height and distance between the two. The process of 'determining the head'
involves a lot of surveying including measurement of distances (both horizontal and along a slope),
heights, and angles and bends. At the same time geological and other conditions of the selected
locations must also be examined and evaluated to ensure that they are fit for constructing such
structures and that no natural or human/animal damage will result
Once suitable locations have been selected for all the civil structures, the available head and the
distances between these structures should be measured. There are different method for head
measurement. The head can be measured using one or two of the following methods. Some common
types generally used for MHP plant are as follows:
(i) Abney level (Clinometers)
Hand-held Abney level (sighting meters) measures angle of inclination of a slope. Since the method
demands that the linear distance along the slope is recorded, it can have the advantage of doubling as
a measure of the length of penstock pipe too.
Height is calculated as,
H = L sine
Where,
H = height, m
L = linear distance, m
= angle of inclination, degree
(1.2)
Other equipment needed are a measuring tape, two graded rods, marking pins pegs etc.
12
H4
L4
H3
L3
L1
H1
H2
L2
Y1
Y3
B1
Y2
A2
Y5
Y4
13
H5
H4
H3
H2
H1
Bubble
error
14
Field of application
b) a float
15
(1.3)
(1.4)
16
d4
V3
d2
d1
d3
V4
V1
V2
Fig. 1.5 Measuring flow by velocity area method (using a flow meter)
17
L>3h
L'>2h
L'>2h
L'>2h
L'>2h
L">4h
L>2h
v<0.15 m/s
Often called current meters, consist of a shaft with a propeller or cups connected to the end. Propeller
is free to rotate and the speed of rotation is of course related to stream velocity. A simple mechanical
counter records the number of revolutions of a propeller placed at a desired depth. Main principle is
that current meters will be supplied with a formula relating rotational speed to the speed of the
stream. A simple propeller meter can be constructed & calibrated. Generally these devices are used
to measure velocities from 0.2 to 5 m/s with a probable error of approx. 2 percent.
730
Power house
720
Direction of flow
710
Weir
700
Penstock pipe
Canal with small slope
Forebay tank
Spillway
700
710
720
Contour line
730
powerhouse etc. The ideal layout of a scheme depends on appropriate site selection. Design and
existence of the components are specific to the selected site.
2.6.1 Intake and weir
Weir and intake structure helps in regulating and controlling the water flowing (at fairly constant rate)
in headrace during high river flow and low river flow conditions. The function of the weir is to
maintain a permanent water level above the intake mouth during both high and low flow seasons. A
weir should be constructed to raise the water level in the river upstream if the adequate river flow
cannot be diverted naturally into the intake during the low flow period.
The weir may be of natural or an artificial weir (temporary or permanent construction). There are
two common types of temporary weir, weir across the whole or weir across the part width of river
stream. The length of the weir across the river should be kept to a minimum. The part width weir
can further be extended if more river flow needs to be diverted.
Direction of flow
Diversion dam
Canal
Canal
Other
important design parameter being the height of weir. For both permanent and temporary weirs, the
height should be kept as low as possible but enough to divert the required flow. In order to
determine the height of a temporary or permanent weir the river depth/level during the dry
season must be known together with the upper height of the orifice of the intake mouth.
20
Flow
Flow
Suitable location
for intake
Unsuitable location
for intake
Intake Prepared
by large boulders
Large
boulders
Canal
The
location of an intake structure must be so chosen that the largest possible portion of the bed load
remains in the river and is not diverted into the headrace. It is desirable to locate the intake behind
or under large, permanently placed boulders or rock. This limits the water that can enter the
intake, and deflect flood flows and river borne debris away. Advantage can also be taken of stable
banks and rock outcrops. If we have to design intake in river bend, outer bend is preferable as it
limits sediment deposition and to ensure flow availability during the dry season. In straight
sections the location of the intake is governed by factors such as bank stability and headrace
alignment.
21
22
Side intake
Weir
River
Flow direction
Q= A x V = A x C
23
Hr-Hh
Orifice
Hh
Hr
Datum
A section through submerged
orifice
directly at the river (without a trashrack) the velocity should be less than 1.0 m/s to avoid
drawing bed load into the intake.
5. If a weir is placed across the river, the flood level may be somewhat higher than
before since the weir raises the water level. For temporary weirs this is not a problem
since they normally get washed away during high flow condition. If a permanent weir is used,
allowances should be made for this when calculating h r as by adding the weir height above the
measured food level.
Example: Design of orifice for side intake
Design a suitable size of an orifice for a design flow of 250 l/s. The normal water level in the river is
0.8 m above the bed level. The design flood level is about 0.6 m above the normal water level. What
is the discharge through the orifice during such a flood?
1. Given:
Design flow, Q = 0.250 m3/s
Normal water level in the river, hr = 0.8 m
Design flood level, hf =0.8 m + 0.6 m = 1.4 m
2. Let velocity through the orifice, V = 1.2 m/s
(since for MHP the recommended velocity through the orifice during normal flow is 1.0 - 1.5
m/s.)
Area of orifice, (A) = Q/v = (0.250 m3/) / (1.2 m/s) = 0.21 m2
3. A = Orifice height (H) Width of orifice (B)
Let Orifice height (H) = 0.2 m (consider)
Width of orifice (B) = A / H = (0.21 m2) / (0.2 m) = 1.05 m
4. Let bottom of orifice 0.2 m above the river bed level
(This value is normally taken for MHP this will minimise the bed load. Also, set the datum at
the river bed level.)
5. Let water level at headrace canal, hh = 0.5 m with respect to the datum as shown in Fig.2.6 (i.e.
100 mm above the upper edge of orifice to ensure submerged condition. Later the headrace canal
will have to be designed accordingly.)
h
h rh
6.
2g
Q= A x V = A x C
Let C = 0.6 (for roughly finished masonry orifice)
Q=0.21 x 0.6 [2 x 9.81(0.80.5)]=0.31 m3 /s = 310 l/s
Q required = 250 l/s
7. Therefore orifice design is OK. Since the designed orifice can deliver 310 l/s
8. Discharge through the orifice during flood flow:
25
h
h rh
2g
Q= A x V = A x C
Let C = 0.6 (for roughly finished masonry orifice)
Qflood =0.21 x 0.6 [2 x 9.81(1.40.5)]=0.529 m3 / s = 530 l/s
Q flood = 530 1/s
2.6.2 Trashracks
Trashracks are placed at the intake to prevent logs, boulders and other large water-born objects from
entering the waterway. It is also placed at fore-bay to prevent leaves, twigs and branches from
entering the penstock. The trashrack at the intake is also known as "coarse trashrack" since the bar
spacing is wider here compared to the trashrack at the fore-bay. The spacing, strength, type (flats or
angles) depends on particle size of the sediments carried by the river flow (i.e. bed load), type of
intake and other provision for a settling basin in the canal system. The trashrack for intakes can be
manufactured from flat steel, angles, tees or round bars welded together at fixed intervals. It is also
important to place the trashrack such that the bars are along the direction of flow, this minimises the
risk of clogging.
Trashracks for side intakes are coarse trashrack not designed to exclude gravel and sediment. The size
of the trashrack should be such that the water velocity is approximately 0.6 m/s (a lower velocity is
uneconomic, whereas a high velocity tends to attract bed load and debris, and results in increased
head loss). Since boulders can frequently impact the coarse trashrack, it needs to be robust, i.e. thick
steel sections should be used. Depending on the length and width of the opening, nature of the
sediment load and the required flow, a clear spacing of 50 mm to 200 mm can be used.
Direct intake
Side intake
Shape
of
trashrack of bottom intake is also very important, since this affects the chances of clogging. Round
bars, for example, are more prone to clogging, because the opening in the middle is smaller than on
the top. The section chosen must be strong enough to withstand impact by any bed load moving
during floods. The recommended clear spacing between these flats, angles or bars is 6 to 15 mm and
26
a commonly used spacing is 12 mm. The reason why these bars are closer than those of the side
intake trashrack is that gravel also needs to be excluded from the bottom intake. If the openings are
too narrow, there is a high chance of clogging necessitating frequent cleaning of the trashrack. One of
the drawbacks of the bottom intake is the clogging of trashrack by pebbles and dry leaves. Especially
during the dry season, the river may carry a lot of leaves, which become trapped in the trashrack and
reduce the flow through it. Therefore the trashrack needs to be cleaned periodically during the dry
season. During monsoon, this is not a problem; the river flow sweeps the gravel and leaves before
they can clog the trashrack.
Capacity
Velocity
Slope of the side
Head loss and seepage
Stability
Economics
Sediment deposition in canal
Table 2.2 Recommended side slopes and maximum headrace canals velocities
28
Maximum recommended
Side slope
velocity for canals (V)
Canal material
(N = h/v)
less than 1 m
less than 0.3m depth
depth
Sandy loam
1.5 to 2 0 0. 4
07
Loam
1.0 to 1.5 0. 5
08
Clay loam
1.25
0.6
0.9
Clay
1.0
0.8
1.0
Stone masonry with mud mortar
0.5 to 1.0 1.0
1.0
Stone masonry with cement mortar 0 to 1.5
1.5
1.5
Concrete
0 to I.5
2.0
3.0
Description
Roughness
coefficient 'n'
Earthen
canals
0.020
0.030
0.040
0.037
0.045
0.059
0.025
0.015
0.017
0.020
0.010
0.015
0.016
0.018
0.020
30
v
h
B
Fig. 2.10 Headrace canal with trapezoidal cross-section
is the factor used to optimise the canal shape, for a rectangular canal N= 0 and
(A / 2), T = B = 2 H
=2, H =
If an optimum canal shape is not possible due to site specific conditions (such as narrow width along
a cliff) then either the width or the height should be selected to suit the site conditions. Then the other
dimension can be calculated.
6. To ensure stable and uniform flow in a long canal, the velocity must be less than 80% of the
"critical velocity, Vc.
Vc = (Ag / T)
(2.11)
For a rectangular canal Vc= (H g )
(2.12)
If the canal velocity is greater than 0.8V then repeat calculations with lower velocity.
7. Calculate the wetted perimeter (P) using the following equation:
P= B + 2 hr (1+N2)
For rectangular canal, P=B+2H
(2.13)
(2.14)
(2.15)
31
10. Calculate the head loss in canal by: Head loss = L S (2.17)
where L = length of the canal section. If the slope of the canal varies along different sections,
calculate the head loss for each section and add them up. If the loss is too high, or if the actual
ground slope differs from the calculated canal slope, repeat the calculations using different
velocities. Again Manning's equation ca be rewrite for H,
Q = [(BH + NH2) 5/3 S ] / [n { B+2H (1+N2)}2/3]
(2.18)
12. Allow a freeboard of about 300mm for Q 500 l/s and 400m for 500 l/s Q 1000 l/s. Free
board allows for uncertainties in the design (e.g. the value of `n' may differ by 5% to 10% from
estimate), water level being above the design level due to obstruction in the canal or during
emergencies and deterioration of the canal embankment.
13. Calculate the size of the largest particle that will be transported in the canal:
d = 11 RS
(2.19)
If this is less than the possible size in the canal, repeat the design using a higher velocity.
14. Check that possible flood flow in canal can be accommodated without using more than 50% of
the freeboard.
15. Find the total head loss. If this is too high or too small, repeat the calculations with a different
velocity. Consider using different types of canal keeping the overall cost in mind.
16. Avoid a canal width of less than 300 mm as narrow canals can be easily blocked. Also for
stone masonry canals, smaller sizes are difficult to construct.
Example: Design of a headrace canal
Design a headrace canal to convey a flow of 285 1/s. Site conditions indicate that the canal would be
stable if stone masonry in mud mortar is used. The expected flow through the intake during a 20year return flood is about 480 1/s.
1. Canal type: stone masonry in mud mortar Q = 0.285 m 3/s
From Table 2.3 Roughness coefficient n = 0.035
From Table 2.2, for gravelly earth, select side slope, N= 0.5, (lh/2v) and V = 1.0 m/s
Cross sectional area, A = 0.285/1.0 = 0.285 m 2
=2(1+N2) -2N
=2 (1+0.52) -20.5
= 1.236
2.
Calculate the water depth in the canal H
H = [A / ( + N)]
H = [0.285 / (1.236+0.5)]
H = 0.405 m
3. Calculate the bed width, B
B=H
B = 0.405 1.236
B = 0.50m
4. Calculate the top width up to the design water level
T = B + (2HN)
32
0.40 m
0.30 m
0.9 m
2
1
0.50 m
Fig. 2.11 Proposed internal canal dimensions
Flood flow
hsp
hflood
Design Flow
Longitudinal section
Cross section
Excess
flow that enters into the intake during flood flow needs to be spilled as early as possible to minimize
foundation erosion, channel collapse in headrace canal. This is achieved by incorporating a spillway
close to the intake and easy access distance during flood condition. If the headrace canal is long,
numbers of spillway can be constructed so that the entire design flow can be diverted if the canal is
blocked as a result of falling debris or landslides. It is also constructed in silt basin and fore-bay. At
the fore-bay to spill the entire design flow in case of sudden valve closure at the powerhouse as may
occur during emergencies. Here it consists of a means of canal emptying combined with control
gates. The excess flows that are discharged via a spillway should be safely diverted into the stream
or nearby gully such that they do not cause any erosion or damage to other structures. Sometimes,
this may require the construction of a canal to the natural water course. Locating spillways close to a
gully will save the cost of canal construction.
34
(2..20)
2. Cw = a coefficient (similar to weir coefficient) which aries according to the spillway profile. C w
for different weir profiles. Choose a spillway profile and determine C w . For MHP, a broad,
round edged profile (C w = 1.6) is suitable since it is easy to construct.
3. Calculate the flow through the intake during floods . The spillway should be sized such that
the entire flood flow can be diverted away from the canal. This is because the micro-hydro
system could be closed during flood or there could be an obstruction in the canal.
35
4. The design procedure involves first calculating the maximum height of the water level in the
canal during a flood (hflood). Then the height of the spillway crest (h sp) is set such that it is about
50 mm higher than the design water level. This ensues that part of the design flow is not spelled,
which would decrease the power output.
5. A coefficient for a road crested weir of a spillway with round edges and easy to construct is
considered as 1.6 for MHP.
6. Spillway crest level should be 0.05 m above normal canal water level. No more than 50% of
the freeboard should be used. Therefore, with a generally used freeboard of 300 mm, the
available h overtop is 0.5 x 0.30 - 0.05 = 0.10 m. The required length can then be calculated for
the chosen h overtop and flood flow.
7. Where there is no pounding immediately downstream, such as in the headrace canal, the spillway
length calculated above equation should be multiplied by 2. This accounts for the gradual
decrease in head over the spillway, until the required level is reached at the downstream end of
the spillway. In this case only the excess flow (Q flood - Qdesign) should be used. Note that in such
cases, locating the spillway immediately upstream of an orifice will increase the flow through the
weir.
Example: Spillway design
Astone masonry in mud mortar headrace canal convey a design flow of 285 1/s. The expected flow
through the intake during a 20-year return flood is about 480 1/s. Design an adequate spillway.
Let head overtop is 100 mm.
Note that two cases need to be checked as follows:
1. The spillway must be able to convey the entire flood flow of 4801/s in case the headrace canal
downstream gets obstructed (pounding case).
2. The spillway should be able to spill the excess flow (480 l/s - 2851/s) when there is no obstruction
downstream. The calculated maximum spillway length should be used in the design.
Case 1:
1. Choose a broad crested weir with round edges profile, so Cw = 1.6
Qspiilway = 4801/s
Qdesign = 0 1/s
hovertop = 100 mm calculated earlier.
Now calculate the length of the spillway,
Lspillway = (Qflood Qdesign) / Cw (hflood hsp)1.5
= (0.480-0) / 1.6 ( 0.1)1.5
= 9.5 m
36
Case 2:
Qspillway = 4801/s
Qdesign = 285 1/s
hovertop = 100 mm calculated earlier.
Now calculate the length of the spillway,
Lspillway = 2 (Qflood Qdesign) / Cw (hflood hsp)1.5
= 2 (0.480-285) / 1.6 ( 0.1)1.5
= 7.7 m
Therefore a spillway length of 9.5 m is required for the above canal (which solve both Case 1 and
case 2).
2.6.5 Settling basins
Most rivers carry a substantial quantity of sediment of different sizes (in the form of gravel,
sand or finer material) depending on the river characteristics, geology of the catchments area
and the discharge. Also steeper rivers of some types carry cobbles and even move large
boulders during annual floods. Intakes are located and designed to prevent boulders and
cobbles from entering into the system but sediments like gravel, sand or finer material cannot
be entirely eliminated. Large particles can block the headrace and reduce its capacity.
Suspended sediment can cause severe wear on the turbine runner, seals and bearings, since the
flow velocity at runner is high.
A settling basin is to settle the suspended particles present in the diverted river flow. The basic
principle of settling basin is the greater the basin surface area and the lower the through velocity
the smaller the particles that can settle. Settling basin can further divided into sand trap
(commonly known as settling basin) which settle sediment size less than 0.3 mm and gravel trap
for larger sediments. To reduce costs, one settling basin (sand trap) should be combined with the
fore-bay or combined with the gravel trap but with adequate size, if possible according to site
conditions. If flood or excess flows can reach the settling basin, such as when it is combined with
the gravel trap, a spillway should be incorporated and sized adequately. A trashrack could also be
an additive in settling basin.
Settling basin should be located at a safe place but as close to the intake as possible. The settling
capacity should be large enough to reduce the velocity sufficiently to settle the sediments in the basin.
It should be easy to flush the deposited silt. The basin should have a sufficient volume to storage
capacity the settled particles until they are flushed (a flushing frequency of twice a day, i.e. 12 hours
for wet and dry season). It should be possible to lead the discharge and sediments flushed from the
basin safely into the river or a nearby gully without causing erosion or damage to other struc tures. Sharp bends should be avoided just before or within the basin since they cause turbu lent
flows which prevent the settling of particles.
Components of settling basin
Inlet zone
This is the initial zone where the transition from the headrace to the settling basin occurs and
there is a gradual expansion in the basin width. Gradual expansion of the inlet channel about 1:5
(1 = 11) as shown in Figure 2.13. This will allow an even flow distribution at the beginning of the
settling zone. The vertical expansion ratio can be higher at about 1:2 (1= 27).
37
Ystorage
Outlet zone
L
Side view
38
Free board
Settling zone
Inlet zone
Inlet
Settling
Outlet
Top view
2m
0.5 m
2m
Settling
2m
Inlet
41
Outlet
tank above the minimum pipe submergence level. This is more important if the scheme consists
of a headrace pipe instead of a canal. There can be small transient surges in the headrace pipe
which result in uneven flow. The 15 second storage capacity helps to balance such uneven flows.
4. A gate valve
A gate at the entrance of the penstock will make maintenance work on the turbine easier. The
gate can be closed and the penstock emptied so that work can be carried out on the turbine.
Rapid closure of the gate, however, could create negative pressure (i.e., a vacuum) inside the
pipe and even cause it to collapse.
5. An air vent
An air vent should be placed as shown in figure 2.15, prevent such a situation. Air can then be
drawn from the air vent pipe into the penstock
Diameter of air vent, dairvent is given as,
dairvent = Q [(F/E )(D / teffective)3]
where,
dairvent= internal diameter of air vent in mm
Q = maximum flow of water through turbine l/s
E = youngs modulus for the penstock N/mm2
D = penstock diameter mm
teffective = effective penstock wall thickness at upper end mm
F = safety factor, 5 for buried and 10 for exposed pipe
Air vent
300 mm
minimum
hs
Spillway
Fine trashrack
Penstock
(2.26)
1
Gate
Compact earth
43
alignment, a clear cover of 300 mm between the pipe and the ground should be provided to facilitate
maintenance and to minimise corrosion. Buried penstock pipe will have better protection
but it is complicate for maintenance.
Design of the penstock pipe
1. Material
Mild steel and HDPE pipes are the most common materials used for the penstock in MHP schemes.
HDPE pipes are usually economical for low heads and flows and are easy to join and repair. They
are light and flexible enough to accommodate small angle bends or radial expansions resulting
from pressure surges. The disadvantage is that these pipes can degrade if exposed to ultra-violet
rays (sunlight) and temperature variations and hence these pipes need to be buried.
Table 2.4 Penstock pipe material
(Note: more the numbers * more will be the favorable condition)
S.N. Material
Corrosion
Cost
Jointing
Pressure
Mild steel
***
***
***
****
****
*****
uPVC
*****
*****
****
****
****
****
Concrete
*****
***
***
Ductile
Iron
****
****
**
*****
****
2. Pipe diameter
A pipe diameter is designed such that the velocity, V, is between 2.5 m/s and 3.5 m/s. In general,
velocity lower than 2.5 m/s results in an uneconomically large diameter. Similarly, if the
velocity exceeds 3.5 m/s, the head loss can be excessive and hence uneconomical in the long
run due to loss in power output. Furthermore, higher velocities in the penstock will result in
high surge pressure as will be discussed later.
dpipe = [ 4Q/V]
where
dpipe is the inside pipe diameter in m
Q is the design flow in m3/s.
V is average velocity inside pipe in m/s
(2.26)
3. Head loss
To calculate the head loss in the pipe length is given as,
Total head loss = major head loss + minor head losses
major head loss h f= fLV2/2g dpipe
minor head losses,h minor= v2 (Kentrance + Kbend + Kcontraction + Kvalve)/2g
45
(2.27)
(2.28)
(2.29)
where,
F = friction factor for pipe material, dimension less
L = length of pipe in m
V = average velocity inside pipe, m/s
dpipe = the inside pipe diameter, m
Ks = coefficients for pipe shape geometry, dimension less
4. Pipe thickness
The thickness of the pipe depends on the pipe diameter, the material, and the type of turbine
selected. The surge effect is different for different types of turbine and hence the pipe thickness
can differ even when the design flow, static head, and pipe materials are similar. If the pipe is
strong enough to withstand the initial surge effect, the pressure will ultimately dissipate
through friction losses in the water and pipe wall as well as through the fore-bay.
The calculation of the minimum wall thickness of the penstock for Pelton turbine is as follows:
(a) To calculate the surge head. Calculate the pressure wave velocity, a
a = 1400 / [1 + {2.1 x 109 d / (E t)} ]
(2.30)
where,
E = the value of Young's Modulus for mild steel is 210 x 10 9 N/m2 and for HDPE is 0.2 to 0.8
x 109 N/m2
d = is the pipe diameter in mm
t = the wall thickness in mm
(b) Calculate velocity V in the penstock,
V=4Q/d2
(2.31)
(c) Calculate the surge head (hsurge),
hsurge= aV/ ng
where,n = the total no. of nozzles in the turbine(s)
(2.32)
(2.33)
(e) As a precaution, calculate the critical time, T, from the following equation:
Tc = (2L)/a
(2.34)
Tc = the critical time in seconds,
where,
L = the length of penstock in m,
a = the wave velocity calculated earlier.
If the turbine valve closure time, T, is less than T c, then the surge pressure wave is significantly
high. Similarly, the longer T is compared to T c, the lower the surge effect. Note that this
calculation is based on the assumption that the penstock diameter, material and wall thickness
are uniform. If any of these parameters vary, then separate calculations should be done for
each section. Closure time of at least twice the critical time (i.e., T > 2Tc) is recommended.
When the operator closes or opens the valve, timing should be such that there is no observable
change in the pressure gauge reading if installed upstream of the valve.
46
(d) Once the surge head has been determined, the nominal wall thickness (t) can be calculated. If
the pipe is made of mild steel, it will be subject to corrosion and welding or rolling defects.
Thus the effective thickness, t effective, will be less than the original thickness. t. For mild steel,
assume an initial thickness, t and calculate teffective,,
using the following guidelines
a) If the pipes are joined by welding divide the initial thickness by 1.1.
b) If the pipe is prepared by rolling flat sheets, divide the initial thickness by 1.2.
c) Since mild steel pipe is subject to corrosion, subtract one mm for every 10 years of plant life.
For example, the effective thickness of a four mm thick flat rolled and welded mild steel pipe
designed for a 10-year life is
teffectiv = 4 / [(1.2 1.2) 1] = 2.03 mm
(2.35)
Note that this does not apply to HDPE pipes where the effective thickness is the same as the original
thickness of the pipe.
5. Calculate the safety factor (SF)
SF = (teffectiv S) / (5 htotal 103 d )
(2.36)
where,
S = the ultimate tensile strength of the pipe material in N/m 2. For mild steel S is usually taken as
350 x 106 N/m2. For HDPE the value is between 6 and 9 x 10 6 N/m2
d = the internal diameter of the pipe, m
For mild steel or PVC pipes, if SF < 3.5, reject this penstock option and repeat the calculation for
a greater thickness. For HDEP pipe SF 1.5 is acceptable.
In order to provide an adequate factor of safety against buckling, the minimum pipe wall
thickness is given by:
teffectiv d[ F P / 2E]0.33
(2.37)
where,
teffectivee = the effective pipe wall thickness, mm
d = the pipe internal diameter, mm
F = factor of safety against buckling (2 for buried penstock and 4 for exposed penstock)
P = the negative pressure, N/mm Z (10 m head = 0.1 N/mmZ)
E = Young's modulus for the pipe material, N/mmZ (from Table 6.2).
Example: Design of penstock pipe diameter
Design a penstock pipe diameter and wall thickness.. Data available are:
Q = 4501/s and hgoss = 180m
Ten vertical bends, = 69, 23, 26, 37, 40, 2, 3, 12, 8 & 3
Penstock material: mild steel, flat rolled and site welded, 550 m long.
High quality steel plates were bought and tested for tensile strength at the laboratory. Minimum
tensile strength, S = 400 N/mm2 was ensured through the tests.
Turbine type: 3 Pelton turbines with 2 nozzles in each turbine, therefore n = 3 x 2 = 6.
47
Reinforced bar
Metal tag
Bend angle ( - )
Penstock
4. Immediately upstream of the powerhouse. This minimises forces on the turbine housing.
5. For micro-hydro schemes with a gross head more than 60 m and an installed power capacity more
than or equal to 20 kW .The design of anchor blocks and support piers requires resolving common
forces, which applies on it. Then the structures are tentatively sized and the various forces that act on
them are resolved. The minimum calculated block size that is safe against bearing, sliding and
overturning is accepted. It should be noted that the design process involves a few iterations. Once all
of the above relevant forces have been calculated the design procedure for anchor blocks and support
piers requires checking the three conditions of stability as follows: safety against overturning,safety
on baring, safety againsting sliding.
2.6.9 Support piers
Support piers are short columns that are placed between anchor blocks along straight sections of
exposed penstock pipe. These structures prevent the pipe from sagging and becoming over stressed.
Support piers restrain the vertical forces of the penstock resulting from the weight of the pipe and
water. However, they allow axial movement resulting from thermal expansion or contraction.
For micro-hydro schemes with a gross head less than 60 m and an installed power capacity less than
or equal to 20 kW, following guidelines is used to design support piers. Support piers are generally
constructed out of stone masonry in 1:6 cement mortar. Dressed stone should be used for the outside
surfaces of the pier. A 140 bearing area from the centre of the penstock diameter should be provided
to support the penstock pipe as shown in Figure 2.18. Placing a steel saddle plate above the support
pier where the penstock pipe rests along with a 3 mm thick tar paper as shown in Figure 2.18. This
minimises frictional effects and increases the useful life of the pipe. C-clamps may also be provided
to protect the pipe from vandalism and a sideways movement, but there must be a gap between the
surface of the pipe and the C-clamp, so that axial forces are not transferred to the support pier.
Table 2.5 should be used to determine the spacing of support piers for mild steel pipes that are welded
or connected by flanges according to British Standard specifications (minimum flange thickness =
16mm). (Support piers are not required for buried pipes). Note that in Table 2.5, the support pier
spacing is the horizontal (plan) length and not the sloping length of the pipe. For flanged mild steel
pipes that do not meet British Standards, one support per individual pipe length should be used with
the pier placed in the middle.
50
300 mm
Penstock
300 mm
300 mm
Penstock
100
200
300
400
500
51
Stay ring
Packing
Retainer ring
Weld
52
20
30
40
50
25
12
15
35
13
17
21
45
11
16
22
27
2.6.11 Powerhouse
The powerhouse accommodates electro-mechanical equipment such as the turbine, generator, agroprocessing units and control panels. The main function of the powerhouse is to protect the electromechanical units from rain and other weather effects as well as possible mishandling by unauthorised person.
The powerhouse should be big enough that all the electro-mechanical equipment can fit in and be
easily accessible for operation and repair work. If agro-processing units are also installed inside the
powerhouse, additional space should be provided so that it is not overcrowded when people are
working or delivering grain and so on.
Design and requirement of powerhouse
1. The location of the powerhouse is governed by the penstock alignment since this building must be
located at the end of the penstock. The powerhouse should be safe from not only annual floods. It
should also be possible to discharge the tail-water safely from the powerhouse back to the stream.
It is advantage to build on level ground to minimise excavation work. The powerhouse should be
located close to the community.
Grid line
Mechanical
Grinder
Penstock
Generator
Turbine
Belt
54
55
Flow Available or designed discharge for the turbine. The unit will be liter per second (l/s) or
(m3/s). Almost all the MHP schemes are run-of-river type, meaning that the storage reservoir
will not be constructed. But flow varies considerably during the seasons. Therefore, the design
flow chosen for the scheme is that which is available through out the year. That is why the
flow measurement will be carried out especially during the dry season as possible.
Gross Head: In case of impulse turbines, the height from fore-bay tank water level to turbine
rotor axis is known as gross head. But in case of reaction turbine the gross head is measured
from fore-bay tank water level to tail race water level. So it can be determined the correct
gross head after having detail land profile design. However, once the civil works constructed
the gross head remains constant whether the plant will run for part or full load.
Net head:
The designed head is known as net head. The height available after deducting
all the head loses of different component along the water line like Entrance (Bellmouth),
Penstock pipe, Expansion Joint, Bend, Reducer, depending upon turbine type etc. Head loses
will be considered of that situation when the designed discharge is flowing through turbine. (it
can be measured the true net head at the time of test or commissioning period only through
precision pressure gauge installed at near by the turbine.
Turbine Selection:
There are various types of turbines. The best selection of turbine type
will be depending upon the site data and other technical parameters likewise afford able quality
of the machine or cost of machine, appropriate equipment to operate for local people etc. In
fact, one of the selection criteria for the turbine type is its efficiency, characteristics under partflow conditions. It is very essential part while selecting the turbine for the MHP projects.
Tentatively the type of turbine cab be selected from the following Figure:
Fig 3.1 Selection of turbine type (source Escher Wyss SKAT Micro pelton book
Functional range of different water turbines)
By using Nomogram (Refer Lecture Note)
2.7.2 Drive System
Drive system is used to transmit the power from turbine to generator or any other output shaft at the
correct speed and in a suitable direction. Major drive system components are: generator shaft, turbine
shaft, bearings, couplings, gearboxes, belts and pulleys, etc.
i)
Direct coupled drive
This drive system is only for the case where the shaft speeds are identical because it uses a flexible
coupling to join the two shafts together directly.
Induction motor
used as alternator
Gear box
Inline
coupling
Turbine runner
2.
Switch fuse: These are similar to isolator but with additional fuse for current limiting.
3.
Molded case circuits breakers (MCCB): This is used for protection from over current,
short circuits and earth fault. For over current, bimetallic strips, for short circuits
58
magnetic trips and for earth fault relays are connected. This is used up to 600 amps. This
is main protection instrument used in micro and Pico- hydropower.
4.
Oil and air circuits breakers: These have similar functions as MCCB but are used over
11kv and over 600amp. They are costly, and are mainly used in small hydropower.
5.
Earth leakage circuit breakers (ELCB): This is special type of MCCB, which can protect
the circuit against earth leakage.
6.
Contactor: used in control circuits as in motor starters; used as circuit breakers\s along
with the relevant trips.
7.
Changeovers: Select power either from main grid or from micro hydro.
CHAPTER THREE
BIOMASS AND BIO FUEL
3.1 Introduction to biomass
Biomass is defined as any organic matter that is available on a renewable or recurring basis. It
includes all plants and plant derived materials, including agricultural crops and trees, wood and wood
residues, grasses, aquatic plants, animal manure, municipal residues, and other residue materials.
Biomass fuel can be defined as fuel that is derived from any organic, renewable material that can be
used in either raw or processed form.
The energy stored inside biomass comes from the sun through the process known as photosynthesis.
The chemical energy that is stored in plants and animls (that eat plants or other animals), or in the
wastes that they produse, is called bioenergy. Essentially, the use of biomass for energy is the reversal
of photosynthesis. Biomass energy is used in many different ways, but always as fuel.
Photosynthesis process
Light
CO2+H2O
(CH2O)+O2
60
Heat
Energy conversion process
For example; combustion process:
CH2O+O2
CO2+H2O+Energy
61
The energy required for the cooking depends on the type and quality of cook stove, . For example, in
traditional and improved cooking stove the fuel wood required for cooking the same quantity of meal
varies.
Smoke
Fire wood
Fire wood
b) Methods of cooking
i. Using pressure cooker: One of the most energy efficient methods of cooking is with pressure
cooker. A pressure cooker requires very little water and reduces cooking time due to high
temperature inside the pot and heat is very evenly, deeply and quickly distributed.
ii. Lid on the pot: Cooking ware having the lid consumes little energy compare to the kitchen
ware having no lid. All research indicates that considerable energy is lost through evaporation
of water surfaces during the cooking processes. This evaporation can be reduced two ways.
One is to have a well fitting lid on the pot and the second is to be able to lower the heat
source, allowing simmering after the food has been brought to the boiling point on hot fire.
iii. Thermo Box or Hay Box: Thermo box or hay box is also one option to cook food by using
less fuel wood when rice or beans are at cooking temperature, the well closed pot is placed in
an insulated container (hay box). Inside the insulated container, the cooking process continues
with out the need of a fire. The rice or beans are perfectly cooked within 30 minutes.
iv. Small pieces: Other method for reducing the cooking time and consumption of fire wood is to
cut vegetables into small pieces before cooking. Size of the food materials also varies the
consumption of fuel wood. This will also require less water.
62
v. Soaking: Soaking beans or rice for certain time before cooking also save fuel wood.
Foods are cooked much faster by using pressure cooker than by other methods, and with much
less water than boiling, so dishes can be ready sooner. Less energy is required. Since less water is
necessary, the foods come to cooking temperature faster. The food is cooked at a temperature
above the normal boiling point of water, killing bacteria and viruses. The pressure cooker can also
be used as an effective sterilizer, for jam pots and glass baby bottles for example, or for water
while camping.
Stone base
Iron Tripod
Fire wood
Fire wood
Use of
traditional stoves consumes more fuel wood increasing the burden on women, as women are mainly
responsible for cooking and collection of biomass. Use of biomass energy and low grade biomass
fuels lead to excessive levels of indoor smoke/air pollution women and children in particular are
exposed to the smoke emission.This is one of the reasons for higher rates of infant mortality and
morbidity and other unhealthy living conditions. Release of CO 2 and other harmful gases in the
atmosphere due to poor combustion of biomass fuels in rudimentary stoves resulting into the
emission of green house gases. The produced smoke stays in the kitchen due to absence of vent pipe
and ill ventilation. So utensils and clothes are blackened by soot, open fire has an inherent risk of
burning houses or their occupants.
63
Figure 1.4: Iron Tripod and Three stone traditional biomass cooking
Improved cook stove (ICS) is designed with modifications over traditional one with reduction in
smoke emission and increased efficiency. The direct and indirect benefits of ICS includes: increased
thermal efficiency, the conservation of forests by cutback in firewood consumption, reduction in
womens labour, reduction in indoor air pollution and hence smoke-released health disorders,
prevention of fire hazards, reduction of cooking time.
Chimney
Pot hole
Fire wood
and accidents.
7. No need of frequent blowing.
8. Less cooking time, less fuel spent.
9. Less emission, less GWP.
common in many parts of Africa and South Asia, adds to a downward spiral in soil fertility. Once the
trees and vegetation on hillsides are removed, soil erosion proceeds rapidly with rain water runoff
and flooding, and the land can be turned into a desert. Current patterns of daily firewood
consumption around the world are thus important factors in an advancing environmental crisis.
3.4.3 Promote health condition
Cooking and heating with solid fuels such as wood, dung, coal or crop waste over open fires or stoves
without chimneys can lead to indoor air pollution. This indoor smoke contains carbon monoxide,
benzenes, aldehydes, small soot and dust particles and other health-damaging pollutants. More than
90% of particles emitted from combustion of wood and dung are fine particles that are less than 1
micron in diameter. These fine particles can remain suspended in the lungs when they are inhaled.
The most common associated diseases with indoor air pollution is respiratory diseases such as lower
respiratory infections among children and chronic obstructive pulmonary diseases among women.
Children exposed to indoor smoke are more than twice as likely to suffer from pneumonia than
unexposed children.. Other possible health impact includes lung cancer, tuberculosis, cataract,
asthma, low birth weight etc.
A WHO assessment found indoor air pollution to be the 8th most important risk factor for disease. It
is a particularly important risk factor for acute respiratory tract infections (ARI) including bronchitis
and pneumonia. Each year, indoor air pollution (IAP) is implicated in the deaths of 1.6 million people
(a death every 20 seconds). Because women and children spend the most time near the domestic
hearth, they are especially vulnerable.
Use of cleaner burning fuels, access to improved stoves and/or behavior changes could substantially
reduce exposure to indoor smoke and associated diseases and ultimately promote the health
condition.
66
1. Carbon dioxide (CO2) In perfect combustion, emissions from burning fuel would be only
Carbon dioxide and water. If biomass was completely combusted, and the fuel was harvested
sustainably, cooking with biomass could be a carbon-neutral situation.
2. Carbon monoxide (CO) Carbon monoxide is one of the primary products of incomplete
combustion. Emissions of carbon monoxide in unimproved wood-burning stoves are
frequently as much as 10-15% of the CO2 emissions, and this figure is even higher for
charcoal. CO generally has a lifetime of several months before it converts to CO2 by natural
atmospheric processes.
3. Methane (CH4) - Methane is a relatively potent greenhouse gas. Averaged over 100 years,
each kg of CH4 warms the earth 21 times as much as the same mass of CO2. Methane has an
atmospheric lifetime of about 12 years. Methane is a part of the Kyoto Accords and is
considered one of the most important greenhouse gases resulting from biomass burning
4. Non-methane hydrocarbons (NMHC) Hydrocarbons are gases consisting primarily of
hydrogen, carbon and oxygen. Emissions of unburned hydrocarbons indicate incomplete
combustion and the vapors can be harmful if inhaled. Overall, the 100-year GWP of the nonmethane hydrocarbons is approximately 12 times that of CO2 , with climate forcing occurring
because of their contribution to ozone formation
5. Nitrous oxide (N2O) A powerful greenhouse gas, nitrous oxide has an atmospheric lifetime
of 120 years and a GWP of 296 over 100 years. N2O is also a part of the Primary Kyoto
Accords and one of the primary gases considered in inventories of biomass burning. While
naturally occurring from bacteria and oceans, the main source of human-produced nitrous
oxide seems to be the use of nitrogen fertilizers and animal-waste handling.
6. An oxide of nitrogen (NOx) NOx is a broad term for the various nitrogen oxides produced
during combustion when combustion temperatures reach a high enough level to burn some of
the nitrogen in the air. NOx is an ozone precursor and when dissolved in atmospheric
moisture can result in acid rain.
7. Particulate Matter (PM) PM is composed of tiny, solid or liquid particles. The effects of
inhaling particulate matter have been widely studied in humans and animals. They include
asthma, lung cancer, cardiovascular issues, and premature death. By weight, particles can
have an extremely strong effect on the atmosphere by absorbing and/or scattering the suns
incoming radiation.
3.5 Biogas: Properties and production methods
Biogas, which is combustible in nature, is produced by anaerobic fermentation of organic materials
by the action of methanogenic bacteria. This odorless gas is 20% lighter than air and burns with blue
flame as LPG. This gas is principally of methane and carbon dioxide and has the proportion of gas
as: methane - 50 to 70 %, carbon dioxide - 30 to 40%, hydrogen - 5 to 10%, nitrogen - 1 to 2%, water
vapor about 0.3% and traces of hydrogen sulphide. Retention time of biodegradable material varies
from 40-60 or 70-90 days depending upon temperature and type of material. Methane is virtually
odorless and is invisible in burning. It burns with a clear flame without smoke and is non-toxic in
nature. Biogas is produced by anaerobic digestion of organic matter. Anaerobic digestion of organic
matter takes place by the action of methanogenic bacteria. In principle a biogas plant should have
three essential components which are digestion chamber, inlet, and outlet parts.
67
Manhole
Composite
pit I
Composite
pit II
Plan
Inlet
Gas outlet
Compacted earth
Ground
Outlet
Dome
Level
Digester
Sectional View
70
angle of twist
angle of incidence
(V ) Wind speed
Where:
V
r
r
= 2 f
f
upper limit of Cp = 59.33%, although in practice real wind rotors have maximum C p values in the
range of 25% - 45%. (G.D.RAI, 2006)
Solidity is usually defined as the percentage of the area of the rotor, which contains material rather
than air. High solidity machines carry a lot material and have coarse blade angles. They generate
much higher starting torque than low-solidity machines but are inherently less efficient than lowsolidity machines. The wind pump is generally of this type. Low solidity machines tend to be used
for electricity generation. High solidity machines will have a low tip-speed ratio and vice-versa. The
overall comparisons of rotors are given in table 2.1.
Table 2.1 Comparison of Rotors
Type
Horizontal axis
Multi blade
Three- bladed
aerofoil
Vertical axis
Panemone
Darrieus
Speed
Torque
Cp
Solidity
(%)
Use
Low
High
0.25-0.4
50 80
Mechanical power
High
Low
Up to 0.45
Less than 5
Electricity production
Low
Moderat
e
Medium
50
Mechanical power
Very low
0.25-0.35
10 20
Electricity production
b) Centrifugal Pump
It comprised of a rotating impeller supplying energy to a fluid
as the fluid moves toward the outer diameter of the pump as
shown in figure 2.8. The water is forced out of the pump by the
energy it obtains from the rotating impeller. Centrifugal pumps
obtain optimal performance at high RPM (1000). Efficiency
and flow decrease rapidly as pressure increases or RPM
decreases. The rotational energy from the turbine could be
transmitted via gearing or belts.
Reliability (18 %) The reliability of the pump is a qualitative measurement based on how
long the pump type typically runs without failure. It also considers the pumping systems
susceptibility to corrosion, fatigue and wear.
Maintainability (22 %) This measurement assesses the pumping systems ability to be
maintained. This includes consideration for accessibility by humans, repairable with basic
technical knowledge and rudimentary tools.
From the above findings search for the site narrowed down to the Morang District. Then to meet the
other criteria mentioned above, the site visit was carried out in the Morang district and searched out
for the sites which met best to the above criteria.
Wind speed and wind direction
Wind rose and the weibull curve help to understand the wind distribution during the period as shown
in figure 3.4. WAsP software was utilized to analyze these characteristics. The annual mean wind
speed was found to be 1.8 m/s and the power density was obtained to be 15 W/m 2. The highest
occurrence of wind was found to be in the direction of North (10.6%) and North East (10.4%) with
the mean speed of 1.76 m/s and 2.9 m/s respectively. Similarly, power density was found to be 17
W/m2 and 30 W/m2 respectively.
S
E
900
2
)/2 g
Where,
= Angle described by rotating crank (rad)
r = Radius of rotating crank (m)
A = Area of cylinder (m2)
d = diameter of suction pipe (m)
a = Area of suction pipe (m2)
= 6 rad/s
Total dynamic head (H) = Suction head + Delivery head + total friction losses on suction
and delivery pipes + Drawdown head
= 2.5 m + 1 m + (0.3419+0.151) m + 0.7 m
= 4.51 m
The wind water pumping system consists of following main components. They are:
The rotor
The safety system
Transmission mechanism
Pump and
Tower
The designs of each component based on design parameter are given below.
4.9 Design of rotor
Rotor is main component of wind of wind pump. Common rotor blades are made of 1 mm thick and 2
m length steel sheet, however, at storms the tips and the inner parts are collapsed and cracked. To
avoid this third ring is used to support the blades but this will make the construction too heavy and
more expensive. A better solution is to choose the length of the blades shorter. Hence blade material
is taken as 1 mm thick and 1 m length standard steel sheet, which is available in local market. One of
the advantage of 1 m length blade is smaller sheet roller can be used to make bent profile. The net
diameter of rotor is taken as 4.5 m including spokes and blade.
4.9.1 Tip speed ratio
The tip speed ratio depends on power coefficient. To get maximum power from wind maximum
power coefficient is desired. For 4.5 m rotor power coefficient is maximum when tip speed ratio is
77
one. Earlier tip speed ratio of 2 is used. However low tip speed ratio causes less friction between
piston and pump cylinder. Thus design tip speed ratio is taken as one.
4.9.2 Blade design
Blade profile depends on solidity. Solidity is the area of all the blades divided by the rotor area. High
solidity means low wind speed can rotate wind turbine. For mechanical energy like water pumping
and low wind speed high solidity is required. The number of blades depends on number of spokes.
Optimum spokes for 4.5 m rotor is six. Hence the number of blades must be a multiple of six. To get
high solidity large blade area is required as area of rotor is same. The possible number of blades are
6, 12, 18, 24 etc. To design blade dimensions following formulas are used.
Where
Rr
= Rotor radius
B
= Number of blades
= Design tip speed ratio
Cl
= Lift coefficient
= Angle of attack
78
A = 0.97 Sq. m
1m
6 Blades
0.5 m
A = 0.501 Sq. m
12 Blades
A = 0.34 Sq. m
0.35 m
18 Blades
0.26 m
A = 0.26 Sq. m
24 Blades
79
f = 0.035 m
C = 0.35 m
f = 0.035 m
C = 0.35 m
The sheets are bent as in figure 4.2 with f/c = 0.1. The code 18PU450 is used for the new rotor that
means rotor has a diameter of 450 cm and 18 blades that is coupled to a pump unit as shown in figure
4.3.
80
2.5 m
4.5 m
Table 4.2 Comparison between hysteresis and inclined hinge safety system
SN Description
Hysteresis system
Inclined hinge system
81
Sensitivity
Catch shock
Wind speed
Reacting time
Manufacturing
cost
Construction
Automation
Application
High as compared to
hysteresis system
Not applicable
Suitable for constant as well
as variable wind speed
Low reacting time and avoid
huge axial force
High
Low
Based on above comparison inclined hinge main vane system is better safety system. The calculations
herein have been made to construct the whole safety mechanism depending on the wind characteristic
found on local site. The design is focused on to find the dimensional parameters of the safety system
components. Various understood terms and equations have been directly interpreted from the
literatures.
4.10.1 The inclined hinge main vane system
This system has a tail vane (or main vane) situated at backside of the rotor at normal position (neutral
position) given in figure below. The vane with its arm is hinged at the tower through a couple of ball
bearings at a certain angle () to the vertical axis in the opposite direction of the rotor plane. The
system has also a side vane with an arm parallel to the rotor plane and this vane is fixed to the tower.
When the wind speed increases the wind thrust on the rotor and side vane causes the rotor to rotate
out of the wind about the tower axis (z-axis). The main vane also rotates as the tower rotates but not
at the same angle. As the main vane is hinged at an inclined ball bearing, the wind thrust on the vane
and vanes self weight cause the vane to rotate at lesser angle than that of the rotor and at a certain
constant wind speed the whole system rotation is balanced at a certain angle to the direction of wind
(). This angle increases as wind speed increases and at a certain high wind speed (in storm
condition) the rotor will be completely perpendicular to the direction of wind.
As the wind speed decreases the rotor changes its position gradually towards its normal position and
ultimately in the direction of the wind when the winds speed reaches its normal designed value. Thus
the system works fully automatic with no need of human intervention. The system works on the
moments balance of numbers of forces developed about z-axis and s-axis (vane axis).
82
Z- axis
S - axis
Vane axis
Tail Vane
Fv
Side View
e
Frt
Ra
Frt
f
Frs
Frs
Resultant force
on rotor
Top view
Fa
83
Practical thrust force is greater than theoritical thrust force due to high bearing friction. Maximum
thrust force, 1128.91 N occurs at 12 m/s consedering bearing friction, however its value is 814.84 N
theoritically at the same wind speed. Design of safety system structure is based on practical peak
load.
Maximum stress 1.11 MPa and 26.7 MPa on bearing and structure respectively. Possible materials for
bearing are given in table 4.5.
84
Rubber bearing can not be used because design stress is less than actual stress on bearing and carbon
graphite bearing can not be used due to low factor of safety. Aluminum alloy ball bearing has
excellent fatigue strength and high factor of safety as compared to other bearing. Similar to safety
system ball bearing is best option for transmission bearing. Locally available steel is safe for other
members of mechanism.
4.12 Design of Pump
The proposed pump is single acting piston pump. The pump is submerged in the water well. The
piston is connected to the pump rod which is driven by the four bar mechanism. With the upward
movement of the piston the pump delivers the water through the rising main. The pump has two
valves; one is at the piston (piston valve) and second at the bottom of the pump (foot valve).
The pump is designed based upon the peak forces occurred during its operation. The peak forces in
the pump rod appear just after the piston has passed its lowest position. The peak forces consist of
different forces:
Fpeak = Fstat+Fa+Fs+Fw+Fwl
Fstat
= force caused by the static pressure
Fa
= force caused by the acceleration of the water, piston and pump rod
Fs
= force caused by the shock of the piston against the water column at the
moment that the piston valve closes.
Fw
= force caused by the friction of the piston and the cylinder.
Fwl
= force caused by the conductor resistance in the pump and the rising
main.
From the nature of forces mentioned above, it may be clear that it is not easy to calculate F peak this
way. The Consulting Services Wind Energy Developing Countries (CWD) suggested the following
simple formula to calculate Fpeak.
Fpeak = k x w x H x (Ap Apr) x {g + 2 x Rc x (Ap Apr) /(Arm Apr)} (CWD, 1989)
Where,
K is an overshoot factor
w
= density of water
H
= water lifting head
Ap
= piston area
Apr
= area of pump rod
g
= gravitational pull = 9.8m/s2
Vs
a 2 C p tot v 2 Dr
8 w g H vol
Where Cp
= power coefficient
tot
= total efficiency of the wind pump
w
= density of water
vol
= volumetric efficiency of the pump
Vs
Vs = Ap x S = 8.956/H (Liter)
Since the design of the pump depends upon the efficiency of the pump. Efficiency is taken as 67%
(WOT, 1990). Various diameter pumps are possible to lift the water. Maximum water lifting head for
each pump is calculated in table 4.7.
Table 4.7 Selection of pump
Diameter of Piston (mm)
Stroke (mm) Water Lifting Head, H (m)
Swept Volume (L)
8" (190.2 mm)
250.00
1.26
8.956/H
6" (150.6 mm)
250.00
2.01
8.956/H
5" (117.6 mm)
250.00
3.50
8.956/H
4" (101.6 mm)
250.00
4.60
8.956/H
The required water lifting head is 4.51 m. Pump having a diameter above 4 is not suitable to lift
water above 4.51 m. Pump less than 4 diameter can lift water greater than 4.51m but they have low
discharge. Hence best possible diameter of pump is 4.
Diameter, Inch
Hence, the basis of table 4.6 it is found that the maximum theoretical water lifting head is 4.6 m for 4
inch diameter of piston. No other size greater than this size could lift water as much of this calculated
head at particular location. The head versus required diameter for piston is shown in figure 4.7.
Head, m
The peak force with safety system and monthly variation are shown in figure 4.8 and 4.9. These peak
forces are calculated on the basis rotor axis is changes with wind speed and monthly variation of
average wind speed in Biratnagar respectively.
= 4.51m
=
: for 4 pump: 1.4 < k < 2.0
4.13 Tower
For the Diever 450 a tower with a height of 10 meters is chosen. The tower is a frame consisting of
angle irons and is welded in 10 parts which are connected together with bolts. The construction has
four legs which are made of 50 x 50 x 5 mm, the horizontals and diagonals of 30 x 30 x 3 mm. The
tower pipe is made of 4" gas pipe. At one side there are stairs till a height of 6 meters. It continues at
two opposite sides of the tower till 9 meters. The last 3 meters two stairs at opposite sides to stay
away from the turning rotor is chosen. From the stairs one can step on the seat which is connected to
the head. On this seat it is easy and safe to lubricate the shaft bearings and the bearings of the
transmission or to do other maintenance work. This is safer then standing on a platform which is
connected to the tower. Aerodynamic forces, gravity forces and pump rod forces act on the tower.
These are calculated for two situations: for maximum operating conditions and for storm conditions.
In the calculations the following conditions are assumed survival winds peed of 40 m/s. At the wind
speed of 12 m/s it is possible that the rotor temporarily faces the wind perpendicular. The influence of
rain, snow and glazed frost is neglected. The stresses in the legs will be maximal when the wind
attacks the tower in a diagonal way. This is explained in figure 4.10. Assuming the tower to hinge on
foundation blocks B and D during diagonal attack, the total wind force is divided among legs A and
C, loading A to buckle and C to tensile forces. The vertical load is divided over all four legs in both situations.
But the horizontal load (wind load) and the moments on the tower top cause a bar force in leg A
(compression) and C (tensile) under diagonal attack which is 2 times higher than in leg C and D
(compression) and A and B (tensile) under orthogonal attack. Also the projected area of the tower
under diagonal attack is bigger than under orthogonal attack.
The maximum force on tower member is 18606 N, compressive (WOT, 1990). The type of material,
design stress and maximum possible stress on tower member is given in table 4.12.