Professional Documents
Culture Documents
Pj
5
6
19
22
18
14
23
16
21
20
15
8
Dj
25
10
100
70
100
100
70
100
70
180
180
180
Wj
2
1
1
3
1
2
2
1
1
3
3
1
Summary
The table below shows the summary of sequences for the
different objectives as well as the resulting value from the test done in
Excel. For the first objective, which is to minimize the number of tardy
jobs, the sequence 2-1-8-9-5-3-6-4-11-10-12-7 minimizes the number
of tardy jobs up to 2 jobs only. The second objective, which is to
minimize the maximum tardiness, the sequence 8-2-4-6-1-9-7-3-5-1210-11 results to a maximum of 44 days of tardiness. Lastly, the third
objective, which is to mnimze the total weighted tardiness, the
sequence 2-1-7-4-9-6-8-5-3-10-11-12 was able to minimize the total
weighted tardiness up to 90.
Objective
Minimize the number of tardy
jobs
Minimize the maximum tardiness
for any job
Minimize the total weighted
tardiness
II.
Value
2
44
90
Sequence
2-1-8-9-5-3-6-4-11-1012-7
8-2-4-6-1-9-7-3-5-1210-11
2-1-7-4-9-6-8-5-3-1011-12
The total slack time is equal to 100 while the total tardiness is
equal to 44. What this implies is that even though the slack time is
enough, the tardiness cannot be eliminated completely as we are only
allowed a total of 30 days. Notice also that the weights for the
remaining tardy jobs is all equal to 1, which means that any tardy job
can be prioritized.
Jobs 1,2,4,6,7,10 and 11s due dates can be shortened so that
Jobs 3,4,8,9 and 12s tardiness can be eliminated of minimized.
Whichever jobs may be chosen, and whatever amount of due dates will
be traded off, will yield a minimum total weighted tardiness that is
equal to 60 days.