Professional Documents
Culture Documents
(a)
Amount
(Rs.)
3,65,200
3,800
- Notional rent
7,200
2,400
2,800
1,100
1,800
1,100
2,000
- Directors fees
13,400
52,000
- Interest expenses
9,600
1,300
13,600
(85,300)
2,93,300
(b) Workings
(a) Contribution per unit
(b) Profit
(i)
(ii)
Rs. 1,00,50,000
Pr ofit
=
Rs. 510
Contributionper unit
(iii) To maintain the same amount of profit, total contribution should be equal
to Present profit + Total fixed Cost = Rs.1,00,50,000 + (Rs.1,80,00,000 +
Rs.20,00,000) = Rs. 3,00,50,000.
Revised contribution per unit = Rs.510 10% of Rs. 2,890 = Rs. 221
No. of units to be sold
=
Rs. 3,00,50,000
Rs. 221
Re quiredcontribution
Re visedcontributionper unit
Units
Output Particulars
Opening
1,600 Work on Op. WIP
WIP
Process-II 55,400 Introduced
&
Transfer
completed during
the month
Normal loss (5% of
52,800 units)
Closing WIP
Abnormal Gain
57,000
Units
1,600
Equivalent Production
Labour &
Material-A
Material-B
Overhead
% Units %
Units
%
Units
- 20
320 40
640
50,600 100
2,640
4,200 100
(2,040) 100
57,000
50,600 100
50,600 100
4,200 70
(2,040) 100
52,760
2,940
50
(2,040) 100
51,820
50,600
2,100
(2,040)
51,300
Working note:
Production units = Opening units + Units transferred from Process-II Closing Units
= 1,600 units + 55,400 units 4,200 units
= 52,800 units
Statement of Cost
Cost
(Rs.)
52,760
51,820
51,300
51,300
11.5627
4.0988
1.8795
1.0994
18.6404
Material A
Amount
(Rs.)
24,000
1311.62
1202.88
703.62
3,218.12
9,43,204.24
9,70,422.36
48,563.34
12,050.47
3,946.95
2,308.74
66,869.50
38,026.42
Units
To Balance b/d
To Process II A/c
To Direct
material
To Direct wages
To Production
overheads
To Abnormal
gain
Amount (Rs.)
1,600
55,400
2,040
Particulars
Units
Amount (Rs.)
2,640
52,200
13,200
9,70,422.36
4,200
66,874.06*
38,026.42
59,040 10,50,496.42
59,040 10,50,496.42
* Difference in figure due to rounding off has been adjusted with closing WIP
3.
Particulars
Rs. 30,000
50,000kms 754kms.
Rs.12,00,000
24,00,000kms
Rs. 2,400
30days
Rs. 12,000
Chauffeurs salary
30days
3days
3days
Total Cost
Add: Profit (25% of net takings or 1/3rd of total cost)
Add: Service Tax @12.36%
Price of the package (inclusive of service tax)
150.00
377.00
754kms.
2,635.00
452.40
Chauffeurs meal cost (three 200 km. completed journey Rs. 50)
Other Allocable costs:
Depreciation
Amount
(Rs.)
240.00
1,200.00
1,817.00
5,054.40
1,684.80
6,739.20
832.97
7,572.17
Working Notes
(1) Total distance of journey
To
From
Delhi
Jaipur
Agra
274
238
242
754
Jaipur
Agra
Delhi
Total Distance
To
II
III
Delhi
Jaipur
Agra
4.
Jaipur
Agra
Delhi
274
238
242
924.75
833.00
877.25
2,635.00
54
56
58
Total cost
35
= 5 labour hours
7
Standard labour hours for actual output = 400 units 5 = 2,000 hours
Standard cost for actual output = 2,000 hours Rs. 24 = Rs.48,000
Actual hours paid and Idle hours
Worker
hours
Idle
time
(hours)
Actual hours
worked
Rate per
hour (Rs.)
Amount
Paid
(Rs.)
Skilled
5 56 = 280
280 2% =
5.6
280 - 5.6 =
274.4
30
8,400
Semiskilled
10 56 = 560
560 2% =
11.2
560 -11.2 =
548.8
24
13,440
20 56 = 1,120
1,120 2% =
22.4
1,120-22.4 =
1,097.6
18
20,160
1,960
39.2
1,920.8
Unskilled
Total
Actual
paid
42,000
Calculation of Variances
(i)
= Rs.6,000 (F)
= Rs.1,680 (A)
= Nil
Unskilled worker
= Rs.6,720 (F)
Rs.5,040 (F)
(iii) Labour Efficiency Variance = Std. Rate (Standard hours Actual hours worked)
Skilled worker
= Rs.271.54 (F)
= Rs.1,086.17(F)
Rs.1,900.80 (F)
5.
= Rs.543.09 (F)
= Rs.940.80 (A)
Sales Budget
Production Budget
(b)
The main points which distinguish Job Costing and Process Costing are as below:
Job Costing
Process Costing
(i)
A Job is carried out or a product The process of producing the product has
is produced by specific orders.
a continuous flow and the product
produced is homogeneous.
(ii)
Costs are determined for each Costs are compiled on time basis i.e., for
job.
production of a given accounting period
for each process or department.
(iv) Each job or order has a number The unit cost of process is an average
and costs are collected against cost for the period.
the same job number.
6.
Dr.
Panchal Group
Contract account for the year ended 31st March 2014
(Rs.)
To Materials purchased
To Wages paid
Add: Wages accrued
To General expenses
45,000
15,000
To Depreciation of plant
To Notional profit c/d
(Rs.)
1,25,000
60,000
12,000
12,500
86,900
2,96,400
By Work-inprogress c/d
Work certified
Work uncertified
Effect of
escalation clause
(Working note- 1)
By Materials in
hand c/d
Cr.
(Rs.)
(Rs.)
2,50,000
15,000
6,400
2,71,400
25,000
2,96,400
46,347
86,900
40,553
86,900
1.4.2014
To Work-in-progress b/d
Work certified
Work uncertified
Effect of escalation
clause
To materials in hand b/d
By Notional profit
b/d
86,900
1.4.2014
By Work-inprogress b/d
(profit in reserve)
2,50,000
15,000
6,400
40,553
2,71,400
25,000
Working notes
(i)
Materials:
Effect of increased price
(Rs. 1,25,000 Rs. 25,000)
25
125
Wages:
Effect of increased wage rates:
25
Rs. 60,000
125
Total increase
Total increase
25%
(Rs.)
Increase up
to 5%
(Rs.)
Increase
beyond 5%
(Rs.)
20,000
4,000
16,000
12,000
2,400
9,600
32,000
6,400
25,600
Increase in value of work done (certified & uncertified) to date: 25% of Rs. 25,600 =
Rs. 6,400
(ii) Profit to be transferred to the profit and loss account:
Since the contract is 50% complete, two-third of the notional profit, reduced by the
proportion of cash received to work certified, is to be transferred as below:
=
2
Cash received
Notional profit
3
Work certified
=
7.
2
3
Rs. 86,900
Rs.2,00,000
Rs. 2,50,000
= Rs. 46,347
Writing off to costing P&L A/c: Small difference between the actual and
absorbed amount should simply be transferred to costing P&L A/c, if difference
is large then investigate the causes and after that abnormal loss shall be
transferred to costing P&L A/c.
(ii) Use of supplementary Rate: Under this method the balance of under and
over absorbed overheads may be charged to cost of W.I.P., finished stock and
cost of sales proportionately with the help of supplementary rate of overhead.
(iii) Carry Forward to Subsequent Year: Difference should be carried forward in the
expectation that next year the position will be automatically corrected. This
would really mean that costing data of two years would be wrong.
(b) Difference between Fixed and Flexible Budgets
1.
2.
3.
4.
Fixed Budget
It does not change with actual
volume of activity achieved. Thus it
is rigid
It operates on one level of activity
and under one set of conditions
If the budgeted and actual activity
levels differ significantly, then cost
ascertainment and price fixation do
not give a correct picture.
Comparisons of actual and budgeted
targets are meaningless particularly
when there is difference between
two levels.
Flexible Budget
It can be re-casted on the basis of
activity level to be achieved. Thus it
is not rigid.
It consists of various budgets for
different level of activity.
It facilitates the cost ascertainment
and price fixation at different levels
of activity.
It provided meaningful basis of
comparison of actual and budgeted
targets.
2.
(b) (i)
Project Y
Rs.
Rs.
(10,000)
(10,000)
(3,500)
(6,500)
(500)
(3,000)
2,500
500
3,500
4,000
Rs. 500
Payback = 2 +
= 2.17 years.
x
Rs. 3,000
Rs. 3,000
Payback = 2 +
= 2.86 years.
y
Rs. 3,500
3.
Payback
NPV
IRR
MIRR
Analysis: All methods rank Project X over Project Y. In addition, both projects
are acceptable under the NPV, IRR, and MIRR criteria. Thus, both projects
should be accepted if they are independent.
(iii) If the projects are mutually exclusive, then the project with the higher NPV at k
= 12%, or Project X would be accepted.
(a) (i) Statement of Calculation of Earnings Available to Equity holders and Debt
holders
Company
Net operating income
Less: Interest on Debt (11% of Rs. 7,00,000)
Profit before taxes
15,00,000
15,00,000
77,000
15,00,000
14,23,000
3,75,000
3,55,750
11,25,000
10,67,250
11,25,000
10,67,250 +
77,000
= 11,44,250
(ii) As we can see that the earnings in case of Company B is more than the
earnings of Company A because of tax shield available to shareholders of
Company B due to the presence of Debt structure in Company B. The interest
is deducted from EBIT without tax deduction at the corporate level; equity
holders also get their income after tax deduction. Due to which income of both
the investors increase to the extent of tax saving on the interest paid i.e. tax
shield i.e. 25% 77,000 = 19,250 i.e. difference in the income of two
Companies earnings i.e. 11,44,250 11,25,000 = Rs. 19,250.
(b) Activity level: 1,30,000 units
Statement showing Estimate of Working Capital Needs
A.
Investment in Inventory:
Raw material inventory: 1 month
4
10,00,000
4,25,000
1,30,000 212.50
52
10,62,500
B.
1,30,000 212.50
5
52
17,00,000
C.
Cash balance
D.
E.
Current Liabilities:
Creditors : 3 weeks
3
1,30,000 100
52
37,500
42,25,000
7,50,000
1,30,000 37.50
52
93,750
1,30,000 75
52
3,75,000 12,18,750
(a)
30,06,250
(i) Deep Discount Bonds and Zero Coupon Bonds : Deep Discount Bonds (DDBs)
are in the form of zero interest bonds. These bonds are sold at a discounted value
and on maturity face value is paid to the investors. In such bonds, there is no
interest payout during lock-in period.
IDBI was first to issue a Deep Discount Bonds (DDBs) in India in January 1992.
The bond of a face value of Rs.1 lakh was sold for Rs. 2,700 with a maturity period
of 25 years.
A zero coupon bond (ZCB) does not carry any interest but it is sold by the issuing
company at a discount. The difference between discounted value and maturing or
face value represents the interest to be earned by the investor on such bonds.
(ii) Investment Decision and Financing Decision: The investment of long term
funds is made after a careful assessment of the various projects through
capital budgeting and uncertainty analysis. However, only that investment
proposal is to be accepted which is expected to yield at least so much return
as is adequate to meet its cost of financing. This has an influence on the
profitability of the company and ultimately on its wealth. Such types of
decisions are known as investment decisions.
On the other hand, Financing Decisions relate to raising of funds from various
sources. Each source of funds involves different issues. The finance manager
has to maintain a proper balance between long-term and short-term funds.
With the total volume of long-term funds, he has to ensure a proper mix of loan
funds and owners funds. The optimum financing mix will increase return to
equity shareholders and thus maximise their wealth.
(b) Seed Capital Assistance: The seed capital assistance has been designed by IDBI
for professionally or technically qualified entrepreneurs. All the projects eligible for
financial assistance from IDBI, directly or indirectly through refinance are eligible
under the scheme. The project cost should not exceed Rs. 2 crores and the
maximum assistance under the project will be restricted to 50% of the required
promoters contribution or Rs. 15 lacs whichever is lower.
The seed capital assistance is interest free but carries a security charge of one
percent per annum for the first five years and an increasing rate thereafter.