Professional Documents
Culture Documents
2
This worksheet summarizes the TRL Calculator results. It displays the TRL, MRL, and PRL computed elsewhere. You may select the technology types
and TRL categories (elements) you wish to include here or on the Calculator worksheet. Choose Hardware, Software, or Both to fit your program. If
you omit a category of readiness level, (TRL, MRL, or PRL) that calculation is removed from the summary. The box in front of each readiness level
element is checked when that category is included in the summary.
You can enter program identification information here, too.
TRL documentation including discussions of TRL, MRL, and PRL is available
from the Main Menu.
X
X
X
##
Use
Omit
Use
Omit
Use
Omit
##
##
##
##
Here you can change the default values the spreadsheet uses to determine which color to award
at a given level of question completion. System defaults are 100% for Green, and 67%
for Yellow. You can change these set points to any value above 75% for Green, and any value from 50% to 85% for Yellow; however, the Yellow
set point will always be at least 15% below the Green set point. Use the spinners to set your desired values. The defaults kick in if you try to set
a value less than the minimum values of 75% for Green and 50% for Yellow. Start with the "Up" arrow to change defaults.
100%
67%
#
##
###
Program Manager:
Date TRL Calculated:
9
6
MRL 9
PRL 9
##
##
##
Hide
Use Manufacturing
Blank
No Manufacturing
Rows
100%
67%
Summary
Program Name: 0
Date TRL Computed:
HW/SW?
Use Mfg?
Use Prg?
% Complete is
Use Programmatics
now set at:
No Programmatics
100%
Technical:
7
9
9
Only Hardware
% Complete set point
Default % Complete:
Only Software
Rows in:
Hardware & Software
Program Manager: 0
30-Dec-99
TOP LEVEL VIEW -- Demonstration Environment (Start at top and pick the first correct answer)
Has an identical unit been successful an on operational mission (space or launch) in an identical configuration?
Has an identical unit been demonstrated on an operational mission, but in a different configuration/system architecture?
Has an identical unit been mission (flight) qualified but not operationally demonstrated (space or launch)?
Has a prototype unit been demonstrated in the operational environment (space or launch)?
Has a prototype been demonstrated in a relevant environment, on the target or surrogate platform?
Has a breadboard unit been demonstrated in a relevant (typical; not necessarily stressing) environment?
Has a breadboard unit been demonstrated in a laboratory (controlled) environment?
Has analytical and experimental proof-of-concept been demonstrated?
Has a concept or application been formulated?
Have basic principles been observed and reported?
None of the above
Source: James W. Bilbro, NASA, Marshall SFC, May 2001
Comments:
Button
11-Button
TRL
TRL 9
##
##
##
##
##
##
##
##
##
##
#
H/SW
Ques
Both
Catgry
B
B
S
S
B
S
S
B
B
B
B
B
T
T
T
T
T
T
T
P
T
P
T
P
##
% Complete
TRL
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL1
Comments:
#
#
H/SW
Both
Ques
Catgry
B
B
B
B
B
H
B
H
H
B
S
B
P
T
T
P
T
T
T
T
T
P
T
T
##
TRL
##
##
##
##
##
##
##
##
##
##
##
##
H
B
S
B
B
B
B
S
B
B
B
B
B
B
T
P
T
P
T
P
T
T
T
P
P
T
P
P
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL2
Comments:
#
#
H/SW
Both
Ques
Catgry
B
H
S
H
H
S
H
S
H
B
H
B
B
B
H
B
B
B
B
S
S
H
S
S
H
S
B
B
B
B
B
T
T
T
T
P
T
T
T
M
T
T
P
P
T
M
T
P
T
P
T
T
M
T
T
M
T
T
T
P
P
P
##
% Complete
Academic environment
Predictions of elements of technology capability validated by Analytical Studies
Analytical studies verify predictions, produce algorithms
Science known to extent that mathematical and/or computer models and simulations are possible
Preliminary system performance characteristics and measures have been identified and estimated
Outline of software algorithms available
Predictions of elements of technology capability validated by Modeling and Simulation
Preliminary coding verifies that software can satisfy an operational need
No system components, just basic laboratory research equipment to verify physical principles
Laboratory experiments verify feasibility of application
Predictions of elements of technology capability validated by Laboratory Experiments
Customer representative identified to work with development team
Customer participates in requirements generation
Cross technology effects (if any) have begun to be identified
Design techniques have been identified/developed
Paper studies indicate that system components ought to work together
Customer identifies transition window(s) of opportunity
Metrics established
Scaling studies have been started
Experiments carried out with small representative data sets
Algorithms run on surrogate processor in a laboratory environment
Current manufacturability concepts assessed
Know what software is presently available that does similar task (100% = Inventory completed)
Existing software examined for possible reuse
Producibility needs for key breadboard components identified
Know limitations of presently available software (Analysis of current software completed)
Scientific feasibility fully demonstrated
Analysis of present state of the art shows that technology fills a need
Risk areas identified in general terms
Risk mitigation strategies identified
Rudimentary best value analysis performed, not including cost factors
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL3
Comments:
#
#
H/SW
Both
Ques
Catgry
B
H
H
H
H
S
B
B
B
S
B
H
H
S
S
S
S
H
S
B
B
S
H
B
H
B
B
S
B
B
S
H
B
S
H
B
B
H
B
B
B
B
B
B
B
T
M
T
M
T
T
P
T
P
T
P
M
T
T
T
T
T
T
M
P
T
P
M
P
M
T
P
T
M
P
T
M
P
T
M
P
T
M
P
T
P
P
P
P
P
% Complete
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
TRL
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL4
Comments:
#
#
H/SW
Both
Ques
Catgry
B
H
B
B
S
H
T
M
T
P
T
M
% Complete
100
100
100
100
100
100
Cross technology effects (if any) identified and established through analysis
Pre-production hardware available
System interface requirements known
System requirements flow down through work breakdown structure (systems engineering begins)
System software architecture established
Targets for improved yield established
TRL
##
##
##
##
##
##
S
S
H
B
H
S
H
H
B
H
H
H
B
H
H
B
H
H
H
B
B
B
H
B
B
S
B
S
S
S
S
B
B
S
H
B
B
H
B
B
B
B
T
T
M
T
M
T
M
M
T
M
P
T
M
M
P
T
M
P
M
P
P
P
M
P
P
T
P
T
T
T
P
P
P
T
P
P
P
P
P
T
T
P
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
External interfaces described as to source, format, structure, content, and method of support
Analysis of internal interface requirements completed
Trade studies and lab experiments define key manufacturing processes
Interfaces between components/subsystems are realistic (Breadboard with realistic interfaces)
Significant engineering and design changes
Coding of individual functions/modules completed
Prototypes have been created
Tooling and machines demonstrated in lab
High fidelity lab integration of system completed, ready for test in realistic/simulated environments
Design techniques have been defined to the point where largest problems defined
Form, fit, and function for application addressed in conjunction with end user development staff
Fidelity of system mock-up improves from breadboard to brassboard
Quality and reliability considered, but target levels not yet established
Some special purpose components combined with available laboratory components
Three view drawings and wiring diagrams have been submitted
Laboratory environment modified to approximate operational environment
Initial assesment of assembly needs performed
Detailed design drawings have been completed
Sigma levels needed to satisfy CAIV targets defined
Draft SEMP addresses integration
Draft SEMP addresses test and evaluation
Draft SEMP addresses mechanical and electrical interfaces
Production processes have been reviewed with Manufacturing and Producibility office(s)
Draft SEMP addresses performance; translate measured to expected final performance
Risk management plan documented
Functions integrated into modules
Configuration management plan in place
Individual functions tested to verify that they work
Individual modules and functions tested for bugs
Integration of modules/functions demonstrated in a laboratory environment
Formal inspection of all modules/components completed as part of configuration management
Configuration management plan documented
Draft Test & Evaluation Master Plan (TEMP)
Algorithms run on processor with characteristics representative of target environment
Preliminary hardware technology system engineering report (Draft SEMP) completed
Customer commits to transition via POM process
Draft Transition Plan with Business Case
Failure Mode and Effects Analysis (FMEA) performed
Value analysis includes analysis of multiple technology and non-material alternatives
IPT develops requirements matrix with thresholds and objectives
Physical work breakdown structure available
Value analysis includes life-cycle cost analysis
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL5
Comments:
#
#
H/SW
Both
Ques
Catgry
B
H
B
H
B
B
B
H
B
B
H
B
T
M
M
P
T
P
P
M
T
P
T
T
% Complete
100
100
100
100
100
100
100
100
100
100
100
100
TRL
##
##
##
##
##
##
##
##
##
##
##
##
B
B
S
B
B
S
S
B
H
H
H
B
S
S
H
S
B
H
S
B
B
B
B
H
S
S
H
H
S
B
B
B
B
B
B
T
P
T
P
P
T
T
P
P
M
M
P
T
T
M
T
P
M
T
T
P
M
P
M
T
P
M
M
P
T
P
P
P
P
P
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
Realistic environment outside the lab, but not the eventual operating environment
Final Systems Engineering Master Plan (SEMP)
Inventory of external interfaces completed
Technology Transition Agreement has been updated
Scaling issues that remain are identified and supporting analysis is complete
Analysis of timing constraints completed
Analysis of database structures and interfaces completed
Have begun to establish an interface control process
Draft production planning has been reviewed by end user and developer
Critical manufacturing processes prototyped
Most pre-production hardware is available
Technology Transition Agreement has been coordinated and approved by end user
Prototype implementation includes functionality to handle large scale realistic problems
Algorithms parially integrated with existing hardware / software systems
Materials, process, design, and integration methods have been employed
Individual modules tested to verify that the module components (functions) work together
Technology system specification complete
Components are functionally compatible with operational system
Representative software system or prototype demonstrated in a laboratory environment
Laboratory system is high-fidelity functional prototype of operational system
Formal configuration management program defined to control change process
Integration demonstrations have been completed
Final Technical Report
Production issues have been identified and major ones have been resolved
Limited software documentation available
Verification, Validation and Accreditation (VV&A) initiated
Process and tooling are mature
Production demonstrations are complete
"Alpha" version software has been released
Engineering feasibility fully demonstrated
Final Transition Plan with Business Case
Acquisition program milestones established
Value analysis includes business case
Technical alternatives include "do nothing case"
Formal requirements document available
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL6
Comments:
#
#
H/SW
Ques
Both
Catgry
H
H
H
H
B
S
S
H
H
H
B
B
H
H
B
H
H
H
H
M
M
T
M
T
T
P
M
M
M
T
M
P
M
P
M
T
P
M
% Complete
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
TRL
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
H
S
H
B
B
H
S
B
B
H
M
M
M
T
T
M
P
T
T
M
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL7
Comments:
#
#
H/SW
Both
Ques
Catgry
B
H
B
B
H
B
S
B
B
B
H
H
S
B
H
H
B
B
S
B
S
H
T
M
T
T
M
T
P
P
P
T
M
M
T
T
M
M
T
M
P
T
P
M
% Complete
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
Components are form, fit, and function compatible with operational system
Cost estimates <125% cost goals (e.g., design to cost goals met for LRIP)
System is form, fit, and function design for intended application and weapon system platform
Form, fit, and function demonstrated in eventual platform/weapon system
Machines and tooling demonstrated in production environment
Interface control process has been completed
Most software user documentation completed and under configuration control
Most training documentation completed and under configuration control
Most maintenance documentation completed and under configuration control
Final architecture diagrams have been submitted
Manufacturing processes demonstrated by pilot line, LRIP, or similar item production
Manufacturing processes demonstrate acceptable yield and producibility levels
Software thoroughly debugged
All functionality demonstrated in simulated operational environmenet
Manufacturing process controlled to 4-sigma or appropriate quality level
All materials are in production and readily available
System qualified through test and evaluation on actual platform (DT&E completed)
Maintainability, reliability, and supportability data collection has been completed
VV&A validation step completed, software works in real world
DT&E completed, system meets specifications
VV&A accreditation step completed, software authorized for use in intended weapon system
Ready for Full Rate Production
TRL
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL8
Comments:
#
#
H/SW
Both
Ques
Catgry
B
H
H
H
B
B
B
B
B
T
M
M
M
T
P
T
P
P
% Complete
100
100
100
100
100
100
100
100
100
TRL
##
##
##
##
##
##
##
##
##
B
B
H
H
B
P
T
M
M
P
100
100
100
100
100
100
100
100
100
100
##
##
##
##
##
##
##
##
##
##
From Top Level
Max TRL9
Comments:
#