NOTA DE SERVIO

RUA NOBRES
LOCAO E NIVELAMENTO DE VALAS
SORRISO - MT
ESCAVAAO REDE DE ESGOTO / REATERRO

1/2

11/7/2015
ESTACA

COTA TER.
0

i%

NOTAVEIS

COTA/ASF

COTA/FUNDO

CORTE

365.16
1.6% TL81

ESTACA

0+17

364.8945

364.85

363.84
363.80

1.05
1.04

363.54

0.99

363.27

0.91

363.00

0.93

362.73

0.94

362.47
361.95
361.95

1.06
1.30
1.30

361.64

1.31

361.34

1.35

361.03
360.78
360.70

1.34
1.30
1.31

360.28

1.33

359.85

1.35

359.43
trecho parcial

1.39

1.6%
2

364.53
1.8%

364.18
1.3%

363.93
1.3%

363.68
0.7%

363.53
1.4% PV76

6+19,70

363.2522

363.25
1.4%

362.96
1.3%

362.69
1.6%

10

362.38
1.8% TL77

11

362.01

10+16,5

362.076875

2.0%
12

361.61

13

361.20

2.0%
1.9%
14

360.82

OBS:

os corte de 1 a 6 foram alterados a pedido do fiscal da obra, em funcao da imcompatibilidade do


com a situao real da rua.

NOTA DE SERVIO
RUA ROSARIO OESTE
SORRISO - MT

LOCAAO E NIVELAMENTO DE VALAS


ESCAVAO REDE DE ESGOTO /REATERRO

1/2

11/7/2015
ESTACA

COTA TER.
0

i%

NOTAVEIS

C/ASF

C/FUNDO

CORTE

364.29
2.0% TL92

ESTACA

0+17

363.9412

363.88

362.89
362.86

1.05
1.02

362.63

0.99

362.41

0.97

362.19

0.99

361.96

0.97

361.74
361.29
361.28

0.99
1.30
1.30

360.93

1.27

360.58

1.27

360.23

1.32

359.88
359.60
359.47

1.30
1.30
1.33

358.98

1.42

358.49
trecho parcial

1.48

1.3%
2

363.63
1.3%

363.38
1.0%

363.18
1.3%

362.93
1.0%

362.73
0.8% PV83

6+18,98

362.58565

362.58
1.9%

362.20
1.7%

361.85
1.5%

10

361.55
1.9%

11

361.18
1.9% TIL84

12

360.81

11+14,79 360.904385

2.0%
13

360.40
2.2%

14

359.97

OBS:

os corte de 1 a 6 foram alterados a pedido do fiscal da obra, em funcao da imcompatibilidade do


com a situao real da rua.

NOTA DE SERVIO
RUA SANTARM
SORRISO - MT

LOCAAO E NIVELAMENTO DE VALAS


ESCAVAO REDE DE ESGOTO /REATERRO

1/1

11/7/2015
ESTACA

COTA TER.
0

366.02

365.74

365.52

i%

NOTAVEIS

1.1% TL

ESTACA

1+1,6

C/ASF

C/FUNDO

365.7204
0

CORTE

364.67
364.35

1.05
1.17

364.37

0.93

364.09

0.93

363.81

0.91

363.22
362.72

0.89
1.40

1.1%
3

365.30

365.02

1.4%
1.5%
5

364.72

364.12

3.0%
### PV

6+15,70

364.118

trecho

OBS:

cortes de 1 a 6 alteradas com orientacao do fiscal da obra, por imcompatibilidade do pr


a situao real da rua, o pv foi levantado a profundidade de 1,4 devido a falta de inclina at o pv e

NOTA DE SERVIO
RUA VIDEIRAS
SORRISO - MT

LOCAAO E NIVELAMENTO DE VALAS


ESCAVAO REDE DE ESGOTO /REATERRO

1/1

11/7/2015
ESTACA

COTA TER.
0

i%

NOTAVEIS

ESTACA

354.53

C/ASF

C/FUNDO
354.53

CORTE
353.48

1.05

353.28

1.17

353.09

1.21

352.89
352.27
352.69

1.23
1.50
1.05

352.39

1.12

352.10

1.05

351.80
351.73
351.52

1.01
1.30
1.05

351.14

1.18

350.77

1.23

350.39

1.34

350.25

1.30

0.4%
1

354.45
0.8%

354.30
0.9%

354.12
1.9% PV

3+17,37

353.74

353.77
353.74

1.2%
1

353.51
1.8%

353.15
1.7%

352.81
1.2% PV

352.57

3+4,47

352.78
352.57

1.3%
1

352.32
1.6%

352.00
1.3%

351.73
0.9%
351.55

3+7,18

351.55

trecho total

OBS:

cortes com profundidade inferiores a 1m foram alterados em campo com orientao do fiscal de
imcompatibilidade do projeto com a situao real da rua.

TRECHO

i%

122.7

1.34%

77.22

1.52%

97.8

2.12%

297.72

scal da obra, em funcao da imcompatibilidade do projeto

TRECHO

i%

121.08

1.12%

95.81

1.75%

110.83

2.46%

327.72

scal da obra, em funcao da imcompatibilidade do projeto

TRECHO

114.1

i%

1.40%

114.1

ao do fiscal da obra, por imcompatibilidade do projeto com


dade de 1,4 devido a falta de inclina at o pv existente.

TRECHO

i%

77.37

0.98%

64.47

1.48%

67.66

1.88%

209.5

m alterados em campo com orientao do fiscal de obra por


a rua.

NOTA DE SERVIO
RUA NOBRES
SORRISO - MT

LOCAO E NIVELAMENTO DE VALAS


ESCAVAO REDE DE ESGOTO /REATERRO

2/2

11/7/2015
ESTACA
15

COTA TER.

i%

NOTAVEIS

COTA/ASF

360.35
2.5% TIL80

16

ESTACA

15+14,2

360.00

359.86

COTA/FUNDO

CORTE

359.00
358.70
358.51

1.30
1.35

357.84

1.43

357.18

1.55

356.51

1.61

355.85
355.37
355.23

1.49
1.50
1.55

354.32

1.36

353.41
352.62
352.49

1.47
1.50
1.51

351.53

1.47

350.58

1.34

349.62

1.27

348.40

2.50

3.0%
17

359.27
2.7%

18

358.73
3.1%

19

358.12
3.9%

20

357.34
2.8% PV78

21

20+17

356.87

356.78
5.5%

22

355.68
4.0%

23

354.88
4.4% TIL91

24

23+17,20

354.12

354.00
5.0%

25

353.00
5.4%

26

351.92
5.1%

27

350.90

27+5,10

350.68

1.1%
PV79

27+5,10

350.90

trecho total

OBS:

o pv 79 depender da profundidade da rede, e sera medida em loco apesar da cota em projeto, a entr
no mesmo sera de 1,80m conforme indicao do fiscal da obra, e sera medida em loco apesar da cot
os demais cortes ficam inalterados

NOTA DE SERVIO
RUA ROSARIO OESTE
SORRISO - MT

LOCAAO E NIVELAMENTO DE VALAS


ESCAVAO REDE DE ESGOTO /REATERRO

2/2

11/7/2015
ESTACA
15

COTA TER.

i%

NOTAVEIS

ESTACA

C/ASF

359.44

C/FUNDO

CORTE

358.00

1.44

357.50

1.40

357.01
356.87
356.41

1.34
1.30
1.31

355.78

1.31

355.14

1.24

354.50
354.23
353.35

1.34
1.50
1.48

352.37

1.53

351.39
350.93
350.42

1.51
1.50
1.48

349.46

1.39

348.50

1.26

347.26

2.50

2.7%
16

358.90
2.8%

17

358.35
3.1% TIL85

18

17+5,62

358.17

357.73
3.2%

19

357.09
3.6%

20

356.38
2.7%

21

355.84
5.0% PV86

22

21+2,2

355.73

354.84
4.7%

23

353.90
5.0%

24

352.90
5.0% TIL90

25

24+09,34

352.43

351.90
5.3%

26

350.85
5.5%

27

349.76
1.0%

27+5,10

349.55

PV79

27+5,10

349.76

trecho total

OBS:

o pv 79 depender da profundidade da rede, e sera medida em loco apesar da cota em projeto, a entr
no mesmo sera de 1,80m conforme indicao do fiscal da obra, e sera medida em loco apesar da cot
os demais cortes ficam inalterados

NOTA DE SERVIO
RUA MATO GROSSO
SORRISO - MT

LOCAAO E NIVELAMENTO DE VALAS


ESCAVAO REDE DE ESGOTO /REATERRO

1/1

11/7/2015
ESTACA

COTA TER.
0

i%

NOTAVEIS

ESTACA

361.22

C/ASF
361.22

C/FUNDO

CORTE

360.17

1.05

360.05

1.05

359.94

0.99

359.82
359.36

0.95
1.30
1.05

359.19

1.03

359.03

1.06

358.86
358.83
358.65

1.04
1.30
1.05

358.37

1.10

358.09

1.14

357.81

1.29

357.70

1.30

0.6%
1

361.10

360.93

0.9%
0.8%
3

360.77

360.41

1.8% PV

3+17,37

360.77
360.41

0.9%
1

360.22

360.09

0.7%
0.9%
3

359.90

359.70

1.0% PV

3+4,47

359.88
359.70

1.1%
1

359.47

359.23

1.2%
0.6%
3

359.10
0.5%
359.00

3+7,18

359.00

trecho total

OBS:

cortes com profundidade inferiores a 1m foram alterados em campo com orientao do fiscal de
imcompatibilidade do projeto com a situao real da rua.

TRECHO

i%

94.2

3.33%

60.26

4.56%

67.52

4.77%

519.7

edida em loco apesar da cota em projeto, a entrada da rede


da obra, e sera medida em loco apesar da cota em projeto.

TRECHO

i%

76.58

3.19%

67.14

4.91%

55.66

4.80%

527.1

edida em loco apesar da cota em projeto, a entrada da rede


da obra, e sera medida em loco apesar da cota em projeto.

TRECHO

i%

77.37

0.58%

64.47

0.83%

67.66

1.40%

209.5

terados em campo com orientao do fiscal de obra por


ua.