Professional Documents
Culture Documents
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
F i g u r e 1 - R a m m e r ( s o u r c e - c o n s t r u c t o r . o rg )
2.
F i g u re 2 - V i b ra t i n g P l a t e
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
1.
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
Sheep-foot roller:- Suitable for fine grained soil types with clay. Use for
damp construction, embankment, pavements and rail -way construction
projects. Up to 14kg/cm pressure can be applied.
Pneumatic tired roller: - Can be used for fine -grained soils and generally
they are used to compaction of both earth and bituminous work in road
projects. Gross weight could be 11 -25tons.
F i g u r e 5 - S h e e p - f o o t r o l l e r ( s o u r c e - c o n s t ru c t o r. o rg )
F i g u re 6 - P n e u m a t i c r o l l e r
There were three major temporary works are carried out in this bridge
construction. First, shoring work was carried out at both end of the bridge
using steel sheet piles in order to prepare temporary platform and scour
protection of foundation (see appendix A for detail drawings). Second,
Temporary working platforms were constructed at both ends inside the shori ng
area by earth filling up to the ground level in order to facilitate the bored pile
driven machine (see appendix B for detail drawings). Third, Removal of working
platform and demobilization by excavating the temporary earth filling up to the
foundation level (MSL -1m) and hack the piles at this level. And smooth
formwork was done at super structure in order to support the concrete deck.
When comparing cost in relation to the all the temporary works of this project,
it can be displayed as follow according to the priced BOQ (see appendix C as
an example).
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
According to those details cost of temporary works had been accounted for
25% of the total project cost and it has significant impact on it.
Soil investigation for this project was conducted by Geotechnical Company in
2013. Upon investigation, geo engineering crew had conducted by drilling 6nos
of boreholes in the both side of the stream bank to ascertain the
characteristics of soil and engineering properties of each soil layer to design
the foundation through Geo technical investigation report submitting.
Hydraulically operated rotary drilling machine was used for the drilling work
on this project. (See the appendix D for detail report and borehole log data)
Cost of this soil testing according to the BOQ is 12,645.00 for 1 linear meter
and for the total of 60 meters its Rs.758,700.00. Its nearly 0.8% of the total
project cost.
When considering the equipment/machinery used for the above
Raththanapitiya Bridge project, no. of different types of ma chines used for
different types of tasks. First, for the shoring work, 25 ton mobile crawler crane
and Pneumatic hammer were used to drive sheet piles. Then to preparation of
temporary working platform excavator is used to load soil to the 8T dump truck
which was transport soil to the site. Then 10T vibrating smooth wheeled roller
used to light compaction and mini loader was used to material spreading.
Finally, the removal of working platform consists excavation of earth material
up to the bottom level of f oundation using 0.8 cu.m excavator, and disposal
material was transported using 8T dump truck. After removing the working
platform sheet piles were removed and then crawler crane was demobilized
using low loader. Cost of all the equipments used for above mentioned works
was Rs. 3.159 million and it accounted 3.2% of total cost of the project. (See
appendix C for complete cost breakdown for the equipments)
The tunnel I chose for this report is new Hatton Kotagala tunnel which is
constructed in 2014 2016, under Improvement of Hatton Nuwara Eliya
Road [A07] Project. It was the first ever tunnel which is under passing live
railway track, totally constructed by Sri Lan kan engineers. This 75.35m long
tunnel excavation was commenced simultaneously at both end of it. Hatton
end (HE) of the tunnel consists of hard rock surface and Nuwara eliya end
(NEE) of it had weak rock surface. This tunnel has working height of 6.5m and
road width of 7.1m which could facilitate two 40ft. long vehicles to cross the
tunnel both ways at same time. Total project cost of this large scale tunnel is
about Rs. 552 millions.
There were no. of special temporary works carried out in this tunneling project.
First, since the NEE of the tunnel had weak rock surface soft grou nd tunneling
techniques were practised to progress the excavation of that end. Therefore
lattice arches and 12m long fore -poles were used as temporary support to the
soft ground tunneling. Second, Special formwork was fabricated by means of
C channels, H iron and special board called Euroform (imported from
korea) to support the 600mm thick permanent concrete lining of the tunnel.
(See appendix E for detail drawings) Third, when rock blasting was carried out
in the tunnel, shield which built up using sheet piles was handled by crane as
an additional precaution to prevent fly -rocks as there were houses at the
vicinity of the HE portal. Additionally benches and scaffoldings were fabricated
in order to facilitate drilling of blast holes at higher elevatio ns and installation
of waterproof membrane. Cost of those temporary works according to the BOQ
was Rs. 66.28 million and it accounted about 12% of total project cost.
(Dr.Samaradieakara, 2016)
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
Soil investigation of this tunnel had been done by conducting 5no. of bore
holes in 2012. Those boreholes were drilled, one close to the HE portal,
another close to the railway track and remaining three at NEE. Borehole
locations and cross section which demonstrate hard rock spread in the
tunneling area can be show as follows. ( See appendix F for detail drawing) Also
some pull-out tests were carried out at site for weak -rock soil nailing and hard rock dowelling. According to the Dr. Sa maradiwakara who was the project
manager of Kotagala tunneling project, those soil investigations had
significant impact on total project cost.
F i g u re 1 7 - R o c k - d o w e l p u l l - o u t t e s t
F i g u re 1 9 - S M - 4 0 0 C r a w l e r m o u n t e d r i g
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
F i g u re 2 1 - H a rd r o c k b l a s t i n g
Conclusion
Temporary works, soil investigation and equipment/machinery used in bridge
construction is totally different from the tunneling construction. In bri dge
construction lots of temporary works are form of false -work, formwork or
temporary working platforms or retaining structures. But in tunnel
construction, high technological knowledge and expertise involving with
temporary works. Also in bridge construc tion low initial cost and shorter lead
time to construction can be expected opposed to the tunneling construction
due to complexity and high end technology. Also the special
equipment/machinery used in tunneling project accounts more cost than the
equipment used in bridge project. By critically analyzing the above mentioned
facts and points, total cost tunneling project has greater impact comparing to
the bridge construction project.
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
References
10
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
Appendices
11
Appendix A:
Appendix B:
Appendix C:
Appendix D:
Appendix E:
Appendix F:
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
12
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
13
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
14
15
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
16
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
17
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
18
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
19
20
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
21
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311
22
23
Importance of Temporary works, Earth Compaction Equipment and Soil Tests in Large-Scale Civil Engineering Projects | Student No: @00321311