Professional Documents
Culture Documents
INTRODUCTION
The project includes three major buildings integrated with a new parking deck. A
pedestrian bridge spans a drive and connects two of the buildings to allow for foot
traffic between the buildings. Refer to Figure 1 for general plan view of the bridge
area.
One end of the connector bridge is supported off the Life Science Building on the
south, the other end of the bridge is supported on two columns designated AA-19 and
AA-20 on Figure 1, located adjacent to Commons Building on the north. The Life
Science Building has a below-grade level that extends about 7.6 meters (25 feet)
below the ground surface, and this building is supported on drilled shafts (caissons)
which extend into dense sands. The Commons Building also has a lower level, but is
supported on spread footings.
__________________________
1
Principal, Soil and Materials Engineers, Inc. 43980 Plymouth Oaks Blvd.,
Plymouth, Michigan 48170, USA., bedenis@sme-usa.com
2
Principal, Soil and Materials Engineers, Inc. 43980 Plymouth Oaks Blvd.,
Plymouth, Michigan 48170, USA., jedele@sme-usa.com
3
President, Spartan Specialties, Ltd., Sterling Heights, Michigan, USA
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
Caissons with a diameter of 1.5 meters (5 feet) support the two 96-cm square by 8.2meter high (36-inch by 2 feet) concrete columns. The columns in turn support a grid
of reinforced concrete beams which support the concrete slab for the connector
bridge.
Initially, the caissons for the two bridge columns were constructed to bear at a depth
of about 4.6 meters (15 feet) below the ground surface. The Commons Building, on
the north, was constructed after the two bridge caissons were installed and the
temporary retaining wall for the lower level of the building was within 1.5 meters (5
feet) of the two bridge caissons. An underground utility tunnel, linking the Commons
and Life Science building with the floor matching the basement level 7.6 meters (25
feet) below the ground surface, along with numerous utilities, were subsequently
constructed.
Settlement of the caissons occurred after the concrete deck for the bridge was placed.
The magnitude of the settlements ranged from about 50 to 100 mm (2 to 4 inches).
The loading on the columns was 535 kN and 1070 kN (120 kips and 240 kips),
respectively. Additional construction on the bridge deck was expected to further
increase the column loadings to 1070 kN and 2140 kN (240 kips and 480 kips),
respectively.
2
Copyright ASCE 2005
A supplemental soil boring was performed between the two bridge columns after the
settlement was reported. The soil profile at the soil boring is summarized in Table 1:
Depth
(m)
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
(1)
0 to 2.4
2.4 to 4.0
4.0 to 8.5
8.5 to 12.2
Shear
Strength
(kPa)
(4)
130 to 220+
35 to 60
-
The soil boring indicated the drilled shafts were constructed over the stiff to medium
clay layer. Further analysis indicated the shear strength of the clay was not sufficient
to support the applied bearing pressure for the existing loading conditions, resulting
in large plastic deformations (i.e., bearing capacity failure).
Since the bridge deck was not physically tied to the Commons Building to the north,
the effect of the column settlement was a vertical drop at the joint between the deck
and upper building floor slab. Therefore, very little damage to the bridge deck was
observed. Some small hairline cracks were visible at the connection between
concrete beams supporting the deck and the top of the concrete columns.
JET GROUTING
Jet grouting consists of using high pressure pumps to erode or jet soils from a
radially-shaped zone around a small diameter drill rod. The jetting is done with a
cementbased grout mix, air, water, or some combination of all three. The liquefied
soils are either mixed with the injected grout or displaced by the grout. The grout
typically consists of a mixture of cement and water (i.e., neat cement grout), but other
additives can be used to improve grout properties.
Jet grouting was chosen for the underpinning because it provides a number of
advantages over other techniques. The jet grouting could be done in the relatively
confined area between the edge of Palmer Drive and the Commons Building and does
not require a large excavation around the columns. Relocation of utilities was not
required and there would be little interference with existing structures. Since the soils
below the caisson would be improved, load transfer with a pile cap was not required.
The jet grouting process is relatively fast and jacking of the columns could begin as
soon as the jet grouting was completed.
3
Copyright ASCE 2005
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
The size and strength of the resulting jet grouted column is determined by a number
of factors including the following:
For the underpinning of the caissons, it was determined by the jet grouting contractor
that a triple tube jet grouting system would be the most efficient method, primarily for
4
Copyright ASCE 2005
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
5
Copyright ASCE 2005
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
Since a portion of the soils below the caissons would be in a semi-liquid state until
the cement grout had set, some additional settlement of the caissons was likely.
Therefore, temporary steel columns were installed below the concrete beams to
support the deck during the jet grouting until the grouting was completed (see Figure
3 and Figure 4).
The following equipment was used for the jet grouting operation.
The drill rig was relatively small and compact and could be positioned around the
columns with conventional construction loaders and lifts (see Figure 5). The pumps,
compressors, and grout mixing equipment could be located off to the side of the
columns so as not to interfere with the drilling operations. Only one set-up was
required for the pumping and mixing operations, while the drilling rig could be easily
moved from one location to another within a short period of time. The silo and
batching stations allowed sufficient quantities of grout to be mixed prior to and
during the jet grouting to allow a continuous flow of grout when required.
A total of eight jet grouted columns were required at the two caisson locations (four
at each column). Figure 5 shows the jet grouting rig installing the grout column next
to the bridge column. The locations of the grout columns were alternated from one
bridge column location to the next to allow at least 24 hours of cure time between jet
6
Copyright ASCE 2005
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
installed at each of the bridge columns. The purpose of the shoring system was to
support the upper portion of each bridge column, while a lower section of the column,
just above the top of the caisson, was removed. The vertical steel for the column and
dowels extending up from the caisson were overlapped in this zone. Therefore, once
the concrete was removed in this area (leaving the reinforcing steel), the columns
would be completely disconnected from the caisson. The column and bridge deck
could then be raised to near their original position with the use of hydraulic jacks.
To support the columns, steel collars were installed around the columns above the
cut-off level (see Figure 6). The collars consisted of two deep channels on opposite
sides of the column with two I-beams connecting the channels. High strength
threaded steel bars were installed through holes cored between the vertical reinforcing
steel of the columns. Grout was placed in the annulus around the threaded bars. The
channels were then bolted to the columns while the bars and I-beams were welded to
the channels to complete the collar.
Cribbing with timber mats and steel beams was placed on either side of the columns
to act as temporary footings (see Figure 7). Heavy steel transfer beams were placed
on the temporary footings and on either side of the columns. Hydraulic jacks (two per
column) were placed on top of each beam directly below the I-beams of the steel
8
Copyright ASCE 2005
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
9
Copyright ASCE 2005
Downloaded from ascelibrary.org by Auburn University on 10/02/13. Copyright ASCE. For personal use only; all rights reserved.
Each of the columns were independently raised by activating the hydraulic jacks in
small load increments. The vertical position of the bottom of the columns and
selected points on top of the deck were measured to the nearest 0.4 mm (1/64 inch) at
each load increment. The sequencing of the loads on each column was adjusted until
the deck was back to within 0.8 mm (1/32 inch) its original position. The jacks were
then locked off and the position of the deck rechecked.
Forms were installed around the base of each column and new concrete placed at the
base of each column to within 100 mm (2 inches) of the bridge column extending
down from the deck. The concrete was allowed to cure for 2 weeks to allow most of
the shrinkage in the new concrete to occur. A non-shrink cement grout was then hand
packed into the gap between the old and new concrete. After the grout reached the
required strength, the jacks were unloaded to transfer the load back to the caissons.
The temporary shoring and steel collar were removed to complete the repair.
Survey points on columns indicate no measurable movements upon completion of the
jet grouting and reconstruction of the base of the columns.
CONCLUSIONS
Jet grouting techniques have been used for a number of years. In the past, jet grouting
was generally limited to larger projects due to the relatively high cost associated with
the development, purchase and maintenance of the specialized equipment. The recent
availability of newer, less costly, easier to use, and more efficient jet grouting
equipment has increased its use for smaller specialized projects. The versatility of the
jet grouting process makes this method especially appealing for underpinning of
foundations, either in new construction or for remedial measures. The ability of the
jet grouting to extend relatively deep without the requirement of open excavations is
especially useful in underpinning drilled shaft or caisson foundations.
ACKNOWLEDMENTS
The authors would like to thank the Barton Malow Construction Co., and J.T.
Crawford, Inc. for their help and assistance in this challenging project.
10
Copyright ASCE 2005