1.
PURPOSE
The inappropriate handling and disposal of solid waste materials can impact on both human safety and
risk contamination of the natural environment.
This plan covers the handling and disposal of waste generated by our operations, inclusive of domestic
and construction waste. The general waste management principles of prevent, minimise, recycle or reuse, with disposal as a last option will apply. Only permitted and registered landfills will be considered as
options for disposal of waste.
2.
COMPONENTS
a.
Waste minimisation
Objectives
To initiate processes to prevent, minimize, recycle and reuse domestic and construction waste material.
Method Statements
Source a dedicated waste collection service to regularly remove separated waste materials.
Prepare a spoil material mass balance to ensure that the optimum spoil material generated as a
result of construction activities are used as fill material.
c.
Waste disposal
Objectives
To ensure that all waste generated during operations is disposed in the correct manner with the least
negative impact on the environment.
Targets
Method Statements
Waste that cannot be re-used or recycled shall be disposed of in the appropriate safe manner.
A sufficient number of refuse bins that are wind and animal / scavenger proof shall be provided.
Method Statements
Hazardous waste shall be placed in separate containers clearly marked for the purpose.
All hydrocarbon (Oils, grease, etc;) waste shall be collected separately and recycled through a
f.
Hazardous Spillages