This appendix provides the default navigator paths for the windows used in the Oracle Enterprise Asset Managment.
The following table provides the default navigation paths. Brackets [ ] indicate a button.
Default Navigation Paths for Standard Application Windows
Table: eAM-Related Windows and Navigation Paths
Window Name

Navigation Path

Activity and Asset Number/Rebuildable Enterprise Asset Manager: Asset Activities > Asset Activity Association
Association
Activity Workbench

Enterprise Asset Manager: Activities > Activity Workbench

Advanced Pricing (Price Lists)

Order Management: Pricing > Price Lists > Price List Setup

Area

Enterprise Asset Manager: Setup > Area

Asset Genealogy Import

Interfaces > Import Asset Genealogy

Asset Meter

Enterprise Asset Manager: Meters > Asset Meter Association

Asset Number Import

Interfaces > Import Asset Number

Asset Status

Enterprise Asset Manager: Assets > Asset Numbers > Asset Statuses

Bills of Material (Activity BOM)

Enterprise Asset Manager: Asset Activities > Maintenance BOM

Bills of Material (Asset BOM)

Enterprise Asset Manager: Assets > Asset BOM

Categories

Enterprise Asset Manager: Setup > Category > Category Codes

Category Sets

Enterprise Asset Manager: Setup > Category > Category Sets

Close Rebuild Work Order

Enterprise Asset Manager: Work Orders > Close Rebuild Work Orders

Close Work Order

Enterprise Asset Manager: Work Orders > Close Work Orders

Collection Elements

Quality Manager: Setup > Collection Elements

Collection Plans

Quality Manager: Setup > Collection Plans

Define Asset Number

Enterprise Asset Manager: Assets > Asset Numbers

Define Asset Route

Enterprise Asset Manager: Assets > Asset Route

Define Rebuildable Serial Number

Enterprise Asset Manager: Rebuildables > Rebuildable Serial Numbers

Departments

Bills of Material Manager: Bills of Materials > Routings > Departments

Department Approvers

Enterprise Asset Manager: Setup > Department Approvers

Descriptive Flexfield Segments

Enterprise Asset Manager: Setup > Flexfields > Descriptive >


SegmentsOrder Manager: Setup > Flexfields > Descriptive > Segments

EAM Asset Documents

Enterprise Asset Manager: Assets > Asset Numbers > Documents

EAM Work Order Documents

Enterprise Asset Manager: Work Orders > Documents

Enter Quality Results

Enterprise Asset Manager: Quality > Results > Entry > Enter Quality
Results

Enterprise Asset Managment


Parameters

Enterprise Asset Manager: Setup > Parameters

Financials Options

Purchasing Manager: Setup > Organizations > Financial Options

Find Asset Number

Enterprise Asset Manager: Assets > Asset Numbers > Asset Number field >
[Find] icon

Find Meter Readings

Enterprise Asset Manager: Interfaces > Pending Meter Readings

Find Pending Work Orders

Enterprise Asset Manager: Interfaces > Pending Work Orders

Find Preventive Maintenance


Schedules

Enterprise Asset Manager: Preventive Maintenance > Schedule Template


Definition

Find Projects

Project Manufacturing Manager: Projects > Project Definition > Projects

Find Project Status

Project Manufacturing Manager: Project Status > Project Status Inquiry

20/05/2016 09:18

Windows and Navigation Paths (Oracle Applications Help)

2 sur 3

https://eqextportal.qantas.com.au/OA_HTML/help/topics/iHelp/HelpS...

Find Rebuild Work Orders

Enterprise Asset Manager: Work Orders > Rebuild Work Orders

Find Requests (PRC: Refresh Project


Summary Amounts)

Project Manufacturing Manager: Other > Requests > Run OR View menu >
Requests

Find Requisition Lines

Enterprise Asset Manager: Purchasing > AutoCreate

Find Work Orders

Enterprise Asset Manager: Work Orders > Work OrdersEnterprise Asset


Manager: Billing > Work Order Billing

Generate Preventive Maintenance


Work Orders

Enterprise Asset Manager: Preventive Maintenance > Generate Work


Orders

Import Items

Enterprise Asset Manager: Interfaces > Import Items

Import Jobs and Schedules

Enterprise Asset Manager: Interfaces > Import Work Orders or Import Meter
Readings

Interface Managers

Enterprise Asset Manager: Inventory > Setup > Transactions > Interface
Managers

Item Costs Summary

Enterprise Asset Manager: Inventory > Items > Master Items > (M) Tools,
Item Costs

Launch MRP

Enterprise Asset Manager: Material Planning > MRP > Launch

Maintenance Workbench

Enterprise Asset Manager: Work Order Planning > Maintenance


Workbench

Maintenance Work Orders

Enterprise Asset Manager: Work Orders > Work Orders

Maintenance Work Order Value


Summary

Enterprise Asset Manager: Work Orders > Work Orders > [Costs] > [Value
Summary]

Master Demand Schedules

Enterprise Asset Manager: Material Planning > MDS > Names

Master Item

Enterprise Asset Manager: Assets > Asset Groups or Asset Activities

Material Transactions

Enterprise Asset Manager: Work Order Transactions > Material


Transactions

Meters

Enterprise Asset Manager: Meters > Meter Definition

Meter Reading

Enterprise Asset Manager: Meters > Meter Readings

Miscellaneous Documents

Enterprise Asset Manager: Setup > Miscellaneous Documents

MRP Names

Enterprise Asset Manager: Material Planning > MRP > Names

Operation Completion

Enterprise Asset Manager: Work Completion > Operation Completion

Organization

Inventory Manager: Setup > Organizations > Organizations > [New]

Organization Parameters

Enterprise Asset Manager: Setup > Parameters

Oracle Manufacturing Lookups

Enterprise Asset Manager: Setup > Lookups

Pending Meter Reading

Enterprise Asset Manager: Meters > Meter Readings > Pending Meter
Reading

Personal Profile Values

Enterprise Asset Manager: Setup > Profiles > Personal

Purchase Orders

Purchasing Manager: Purchase Orders > Purchase Orders

Preferences

Time and Labor Administration: Preferences

Preventive Maintenance Schedules

Enterprise Asset Manager: Preventive Maintenance > Schedule Definition

Project Parameters

Project Manufacturing Manager: Projects > Project Definition > Project


Parameters

Rebuild Completion

Enterprise Asset Manager: Work Completion > Rebuild Work Order


Completion

Requisitions

Enterprise Asset Manager: Purchasing > Requisitions > Requisitions

Resource Usage

Enterprise Asset Manager: Assets > Asset Numbers > Asset Numbers

Resource Transactions

Enterprise Asset Manager: Work Order Transactions > Resource


Transactions

Routings

Enterprise Asset Manager: Asset Activities > Maintenance Routings

Run AutoInvoice

Order Manager: Receivables > Interfaces > AutoInvoice

20/05/2016 09:18

Windows and Navigation Paths (Oracle Applications Help)

3 sur 3

https://eqextportal.qantas.com.au/OA_HTML/help/topics/iHelp/HelpS...

Select Work Order

Enterprise Asset Manager: Work Order Details > Operations, Material


Requirements, or Resource Requirements

Scheduler Workbench

Enterprise Asset Manager: Work Order Planning > Scheduler Workbench

Shop Floor Invoice Variance

Enterprise Asset Management Cost > Work Order Shop Floor Invoice
Variance

Submit Request

Enterprise Asset Manager: Reports

Supply/Demand

Enterprise Asset Manager: Material Planning > MRP > Workbench >
[Supply/Demand] > [Find]

Time

Self-Service Time and Expenses: Time Entry

Transaction Sources

Order Manager: Receivables > Setup > Transactions > Sources

Users

System Administrator: Security > User > Define

View Operations

Enterprise Asset Manager: Work Order Details > View Operations

View Material Requirements

Enterprise Asset Manager: Work Order Details > View Material


Requirements

View Resource Requirements

Enterprise Asset Manager: Work Order Details > View Resource


Requirements

View Resource Transactions

Enterprise Asset Manager: Work Order Transactions > View Resource


Transactions > [Find]

Work In Process Parameters

WIP Manager: Setup > Parameters

Work Order Completion

Enterprise Asset Manager: Work Completion > Work Order Completion

Work Order

Enterprise Asset Manager: Work Orders > Work Orders

ImF