You are on page 1of 3

COMMENTS

RESOLUTION SHEET [
CRS ]
CONTRACT NUMBER : GC14104300

QP PROJECT
3788
NUMBER
CONTRACT TITLE : EPIC FOR NEW SOUR GAS COMPRESSOR AT NGL-3 PLANT, MESAIEED
QP EXTERNAL TRANSMITTAL REFERENCE :
EDM/GC14104300/EXT/TN/2828
DOCUMENT NUMBER : 3788-M3MP-1-19-0017

DATE

05-05-16

DOCUMENT
0
REVISION
DOCUMENT TITLE : Method Statement for Installation of Temporary Supports for Valve Assembly in
Cooler Area

No.
10

QP COMMENTS
All weld joints carried out for the purpose of providing
temporary support to be approved after conducting
proper inspection tests.
In JSA 1. Activity no.3 - Add: No simultaneous works below
the scaffolding.
2. Activity no.6 - Add: in control measures for
electrocution, ensure proper earthing to the
equipment and records to be kept at site. All power
tools to be double insulated.
3. Activity no.6 - In Hazards column, add sharp
edges.
4. 4. Add activity - refixing of existing support to the
newly cast concrete. Include
the corresponding
hazards and control measures.
5. 5. Include waste management as separate activity.
In JSA 1. Activity no.3 - Add: No simultaneous works below
the scaffolding.
2. Activity no.6 - Add: in control measures for
electrocution, ensure proper earthing to the
equipment and records to be kept at site. All power

CONTRACTOR RESPONSE
Noted and added. See Item 8.7

1. Activity no.3 has been revised,


2. Note, and added. See Activity no.6
3. Added in Activity no.6.
4. Noted, please see revised activity no.08
5. Noted, new section added. Please see activity no.09

Comments repeated (See CONTRACTOR response above in No#02)

tools to be double insulated.


3. Activity no.6 - In Hazards column, add sharp
edges.
4. Add activity - refixing of existing support to the
newly cast concrete. Include the corresponding
hazards and control measures.
5. 5. Include waste management as separate activity.

Cutting, demolition of the existing pavement below


and very near the existing pipes, cable trays, and
structures shall be done manually.
For any use of Mechanical equipment for the
works, It shall be discussed on site and after QP
NGL Safety &
Operations approval the work may proceed.
A Full time Safety Officer shall be placed on this
area specifically to monitor the Safe work
procedure.
Finally, this shall be subject to approval from the
End User.

In Section :1. Upon completion of the inspection stated in item #


7, all existing anchor bolts connecting the supports
to the existing pavement slab shall be removed
prior to pavement breaking. These bolts shall be
cast in during the reinstatement of the same
pavement.
2. Concrete chipped and the post drilled bolt holes
made on existing pavement as per item # 4 of this
section shall be repaired and re-instated with
approved concrete repair grout and mortar after
removal of the temporary supports.
3. Cast in site temporary pipe support foundation /
sleeper (item # 2) shall be provided with proper
lifting hooks or sleeves to enable removal of this
foundation after the removal of the temporary
supports.
Item 5 states: Beams will be placed manually?
Please specify the weight of these beams.

Noted. Please see Item 8.11

All equipment will be inspected prior to mobilization and will


be indicated in permit. Approval of permit will be considered
as approval of operations to commence work.

A full time safety Office will be placed in the area during


working period.

Approval of this method statement and permit will be


considered as approval from end user.

Noted and incorporated. Please see Item 8.10 & 8.15

Noted and incorporated. Please see Item 8.16

Temporary foundation will be demolished and debris disposed


in designated area. Please see item 8.17

Maximum member weight is 400 Kg.


Shifting of beams under the pipe rack to the location by using Manual
Hydraulic trolley, Placing the Temporary supports to its location by
using lifting tools (Slings, Ropes, etc.) & Manual Hydraulic trolley.
Please see item 8.4

Also consider adding: "...or by use of mechanical aids


(chain blocks)".

6 7.3 If there is a likelihood that the excavation could


reach 1.2m depth, then it is much better to focus on the
higher severity risk and treat this activity as a confined
space and have all the standard controls in place i.e. all
personnel shall undergo confined space training, gas
monitoring, access/egress, emergency response etc.

Due to the existing services and the space constraint, mechanical


lifting is not possible.

IP-OPS-027 - Gas Operations-Confined Space will be followed.


Please see 7.3.6

Please add: Detailed review of the latest as-built underground information/drawings with QP Asset Holder.

Noted and incorporated. Please see Item 7.1.4

Add Vibrator to the list of equipment

Added. Please see Item 6.1.13. Works will be carried out as per
Approved Method statement for concrete works referred in Item 3.
Due to the existing services lifting operations cannot be carried out
using equipment. Hence, lifting will be manual means only.

Item 7.2.4, Contractor to include Approved lifting plan


prior to work start.
b) Item 8.0.9, Contractor to include Surround equipment
as-built elevation, to provide survey report reference to
monitor if any settlement occurred during construction &
completion of work.
c) Item 8.0, Contractor to include requirements for civil
activities for compaction test for formation level prior to
blinding & backfilling layer by layer as per projects specs
requirements.
d) Temporary support requires design calculations &
approval by engineer prior to implementation /
execution.

Approved project survey bench mark will be used to record level.


Please see Item 8.9

Works will be carried out as per Approved Method statement for


Earthworks referred in Item 3. Please see Item 8.14
Document approved in Code-2. AFC document will be available prior
to commencement of work.

You might also like