Professional Documents
Culture Documents
RESOLUTION SHEET [
CRS ]
CONTRACT NUMBER : GC14104300
QP PROJECT
3788
NUMBER
CONTRACT TITLE : EPIC FOR NEW SOUR GAS COMPRESSOR AT NGL-3 PLANT, MESAIEED
QP EXTERNAL TRANSMITTAL REFERENCE :
EDM/GC14104300/EXT/TN/2828
DOCUMENT NUMBER : 3788-M3MP-1-19-0017
DATE
05-05-16
DOCUMENT
0
REVISION
DOCUMENT TITLE : Method Statement for Installation of Temporary Supports for Valve Assembly in
Cooler Area
No.
10
QP COMMENTS
All weld joints carried out for the purpose of providing
temporary support to be approved after conducting
proper inspection tests.
In JSA 1. Activity no.3 - Add: No simultaneous works below
the scaffolding.
2. Activity no.6 - Add: in control measures for
electrocution, ensure proper earthing to the
equipment and records to be kept at site. All power
tools to be double insulated.
3. Activity no.6 - In Hazards column, add sharp
edges.
4. 4. Add activity - refixing of existing support to the
newly cast concrete. Include
the corresponding
hazards and control measures.
5. 5. Include waste management as separate activity.
In JSA 1. Activity no.3 - Add: No simultaneous works below
the scaffolding.
2. Activity no.6 - Add: in control measures for
electrocution, ensure proper earthing to the
equipment and records to be kept at site. All power
CONTRACTOR RESPONSE
Noted and added. See Item 8.7
Please add: Detailed review of the latest as-built underground information/drawings with QP Asset Holder.
Added. Please see Item 6.1.13. Works will be carried out as per
Approved Method statement for concrete works referred in Item 3.
Due to the existing services lifting operations cannot be carried out
using equipment. Hence, lifting will be manual means only.