Professional Documents
Culture Documents
Hydraulic Study
Prepared by:
September 2014
Authors:
Study for:
File Reference:
WF18/44
Version history
Version Comments/changes
Changed by Reviewed
Reviewed
and date
by and date by and date
1.0
Draft
BB 08/13
MK 11/13
2.0
EC 11/13
HM 01/14
3.0
EC 11/13
HM 01/14
4.0
EC 03/14
HM 03/14
5.0
EC 09/14
HM 09/14
EC 11/13
Distribution list
Name
Title
Directorate
Branch
Paul Novy
Assets
Engineering Services
Namrata Mathur
Project Manager
Projects
Engineering Services
NH Library
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 2 of 180
Table of contents
1.
2.
Introduction............................................................................................................... 14
2.1
2.2
2.3
2.4
3.
Overview ..........................................................................................................................14
Study objectives ...............................................................................................................14
Limitation statement .........................................................................................................15
Acknowledgements ..........................................................................................................15
Background............................................................................................................... 16
3.1
3.2
3.3
4.
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 3 of 180
18.
19.
List of figures
Figure 1
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
Figure 7
Areas of the Rocky Point cane lands considered unsuitable for crop production
(Source: CSIRO 2007) ............................................................................................... 24
Figure 8
Figure 9
Figure 10
Figure 11
Figure 12
Figure 13
Figure 14
Figure 15
Figure 16
Figure 17
Figure 18
Figure 19
Figure 20
Figure 21
Figure 22
Additional MIKE 11 branches added to the 2004 MIKE 11 branches (shown in cyan)
56
Figure 23
Figure 24
Figure 25
Figure 26
Figure 27
Figure 28
Figure 29
Figure 30
Figure 31
Figure 32
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 4 of 180
Figure 33
Figure 34
Figure 35
Figure 36
Figure 37
Figure 38
Figure 39
Figure 40
Figure 41
Figure 42
Figure 43
Figure 44
Figure 45
Figure 46
Figure 47
Figure 48
Location of proposed upgrades from the 1994 study (Ref 2) and status of those
upgrades ................................................................................................................... 87
Figure 49
Location of proposed upgrades from the 2004 study (Ref 3) and status of those
upgrades ................................................................................................................... 88
Figure 50
Location of proposed upgrades from the 2004 supplementary study (Ref 4) and
status of those upgrades ......................................................................................... 88
Figure 51
Figure 52
Location of Behms Creek and Kerkin Road weir tidal gates ................................. 90
Figure 53
Figure 54
Figure 55
Figure 56
Figure 57
Figure 58
Figure 59
Figure 60
Figure 61
Figure 62
Figure 63
Figure 64
Figure 65
Figure 66
Figure 67
Figure 68
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 5 of 180
Figure 69
Figure 70
Figure 71
Urbanisation of Upper Woongoolba, aerial photos 2001 (left) and 2011 (right) . 121
Figure 72
Urbanisation of Upper Woongoolba, aerial photos 2001 (left) and 2011 (right) . 122
Figure 73
Changes around Marks Road, aerial photos 2001 (left) and 2011 (right) ............ 123
Figure 74
SKMs 1994 hydrological and hydrodynamic model extent (Ref 2)..................... 124
Figure 75
City of Gold Coasts 2004 hydrological and hydrodynamic model extent (Ref 3)125
Figure 76
City of Gold Coasts 2004 hydrological and hydrodynamic model extent (Ref 4)126
Figure 77
Depth of inundation (peak) for one-in-10-year ARI flood with 72-hour storm
duration (HAT) ........................................................................................................ 127
Figure 78
Depth of inundation (after four days) for one-in-10-year ARI flood with 72-hour
storm duration (HAT) .............................................................................................. 128
Figure 79
Option 1 (additional culverts at Behms Creek) compared with base case (four
days) ........................................................................................................................ 129
Figure 80
Option 2 (automated gates) compared with base case (four days) ..................... 130
Figure 81
Option 3 (Behms Creek straightening) compared with base case (four days) ... 131
Figure 82
Option 4a (10m3/s pump) compared with base case (four days) ......................... 132
Figure 83
Option 4b (15m3/s pump) compared with base case (four days) ......................... 133
Figure 84
Option 5 (widening of Behms Creek and Pimpama River) compared with base case
(four days) ............................................................................................................... 134
Figure 85
Option 6 (detention basin) compared with base case (four days)....................... 135
Figure 86
Figure 87
Figure 88
Figure 89
Figure 90
Figure 91
Figure 92
Figure 93
Figure 94
Depth of inundation (peak) for one-in-2-year ARI flood with 72-hour storm duration
(HAT) ........................................................................................................................ 178
Figure 95
Depth of inundation (after four days) for one-in-2-year ARI flood with 72-hour
storm duration (HAT) .............................................................................................. 179
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 6 of 180
List of tables
Table 1
Table 2
Table 3
Summary of future (2100) climate storm tide estimates (Ref 14) .......................... 42
Table 4
Table 5
Table 6
Unified River Basin Simulator (URBS) model parameters for Pimpama and Logan
River catchment ........................................................................................................ 49
Table 7
Table 8
Table 9
Table 10
Table 11
Inundated area and volume of water from different upgrade scenarios ............... 96
Table 12
Difference in inundation area and volume of water compared with base case .... 97
Table 13
Cane cultivation level and easement width by comparison location. ................. 102
Table 14
Table 15
List of photos
Photo 1
Photo 2
Photo 3
Photo 4
Photo 5
Photo 6
Photo 7
Photo 8
Photo 9
Photo 10
Photo 11
Photo 12
Photo 13
Photo 14
Photo 15
Photo 16
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 7 of 180
Photo 17
Photo 18
Photo 19
Photo 20
Photo 21
Photo 22
Photo 23
Photo 24
Photo 25
Photo 26
Photo 27
Photo 28
Photo 29
Photo 30
Photo 31
Photo 32
Photo 33
Photo 34
Photo 35
Photo 36
Photo 37
Photo 38
Photo 39
Photo 40
Overtopping of Zipfs Road near Loves Road (Courtesy of Barry Brooking) ...... 163
Photo 41
Photos taken during 15 December 2012 high tide (Courtesy of Barry Brooking)163
Photo 42
29 January 2013 photo of Pimpama River culvert (Courtesy of Blake Boulton) 164
Photo 43
29 January 2013 Photo of Behms Creek Culvert (Courtesy of Blake Boulton) .. 165
Photo 44
29 January 2013 photo of Zipfs Road inundation (Courtesy of Blake Boulton) . 165
Photo 45
Photo 46
Photo 47
Photo 48
Photo 49
Photo 50
Photo 51
Photo 52
Photo 53
Photo 54
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 8 of 180
Photo 55
Photo 56
Photo 57
Looking west from concrete bridge (note brewery in background) 10/11/04 ..... 175
Photo 58
Photo 59
Looking south-west from bridge (note quarry on Ormeau Range) 10/11/04....... 176
Photo 60
Looking east from concrete bridge behind Richard Skopps farm 10/11/04....... 176
Photo 61
Photo taken 24/11/04 showing the dead cane plants resulting from inundation
(note quarry) ........................................................................................................... 177
Photo 62
Photo taken 24/11/04 showing cane plants on our farm with good drainage ..... 177
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 9 of 180
1. Executive summary
The Woongoolba Flood Mitigation Scheme (WFMS) was constructed in the 1960s to mitigate
the impacts of flooding and to promote agricultural activity around the Woongoolba area.
This area, located between the Logan and Pimpama Rivers, is quite low-lying and prone to
flooding, although farming has existed here for many generations. The suburbs of Pimpama,
Norwell, Gilberton, Jacobs Well and Steiglitz are all located within the WFMS.
The WFMS was created in line with Section 47 of the Local Government Act 1936, which
allowed scheme drainage to be constructed for agricultural purposes. The scheme covers
most of the lower floodplain, with a catchment area of about 190km2. The floodplain can also
be affected by flooding of the Logan/Albert River which covers an area of about 3878km2.
The scheme involved the construction of tidal gates and man-made and natural drainage
systems to enable drainage of a 10-year Average Recurrence Interval (ARI) flood event in 11
days (based on estimates from this study). Later, the Department of Primary Industries (DPI)
released data indicating that sugar cane should not be inundated for more than three days.
In recent years, the drainage time criterion was increased by Council so that cane will not be
inundated for more than four days for a one-in-10-year 72 hour ARI storm event.
The scheme is bounded by the system of constructed levees to the north and east and by
the Pacific Motorway in the west. Within the scheme itself, the drains intersect the major flow
paths to ensure localised flooding can be drained to the nearest outlet as efficiently as
possible.
Sugar cane cultivation is the main agricultural activity within the WFMS. During the past 30
years, the effectiveness of the WFMS has allowed sugar cane cultivation to expand further
into low-lying areas. Cane is grown in some areas as low as 0.5 metres Australian Height
Datum (AHD) and more than 35 per cent of the land within the scheme has an elevation of
less than one metre AHD. About 55 per cent of the cane cropping land is below Highest
Astronomical Tide (HAT) level.
During the past decade, concerns have been raised on the capacity of the WFMS due to the
ever-changing land use of the upper reaches of the catchment. The catchment has
experienced significant residential, commercial and industrial development. The concerns
relate to over the ability of the drainage scheme to meet the drainage time criteria, which in
turn affects cane crop yield.
To determine the drainage performance, a number of hydraulic models has been developed,
internally and externally over the years, for the WFMS. They were the 1994 WBM Study and
the 2004 study by City of Gold Coast, formerly Gold Coast City Council (GCCC). Both
studies used the one dimensional (1D) hydrodynamic model (MIKE 11) to simulate the flood
flows of the scheme drains. The input of the model is based on the RORB hydrology
software which WBM developed as part of its 1994 study. The 2004 study further refined the
1994 study to take into account new survey data. This 2004 study was subsequently
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 10 of 180
adopted by Council in 2005, with the new drainage criteria of a one-in-10-year Average
Recurrence Interval (ARI) flood, with a rainfall event of 72 hours duration, being contained by
the schemes drains within a four-day period.
To determine whether the one-in-10-year ARI of 72 hours duration was still valid in 2013 and
beyond, a new 1D/2D hydrodynamic model was developed using the latest hydrological input
and new survey information. Further, the hydrological and hydraulic models are now
calibrated to flood events, especially the January 2013 event. Previous studies were never
calibrated to any flood events. With the development of this new hydrodynamic model, this
study aimed to test the drainage performance criteria in 2013 and to recommend strategies
to ensure the WFMS performs to its design, ensuring flood water drains out of the system
and reduces crop losses.
A number of scenarios were tested to determine if improvements to the drainage
performance could be achieved in the study area.
The analysis indicated minor
improvements can be achieved with major upgrades. However, simple cost benefit analysis
would indicate that the costs far outweigh the benefits. It would be far more beneficial to
ensure that drains and drainage structures were maintained, given the probability of a rain
event occurring annually.
Other than the hydraulic development and assessment, this study also compared various
surveyed information to determine the magnitude of siltation in the schemes drains. The
results of the comparison show that siltation has occurred at most locations.
In summary, the key outcomes of this study are:
Analysis of aerial photography shows significant further expansion of cane farming into
low-lying land between 1973 and 2009.
Analysis of aerial photography and terrain shows that substantial cane farming activity
occurs on land below one metre AHD.
Pimpama River conveys the most flow out of the system, followed by Behms Creek and
Sandy Creek.
Survey works in 1994 and 2012 show that siltation has occurred along most scheme
drains during this period. Maintenance of the schemes drains is critical to ensure the
areas drainage performance is met.A number of mitigation scenarios was tested to
improve the existing WFMS drainage time criteria. The results of the scenario testing
shows there is a fine balance between the cost of the upgrades and the benefit of those
upgrades. For example, among the scenarios tested, the most effective was to construct
a stormwater pump station at high cost. While the least effective, was constructing
automated tidal gates leading to a worsening flooding situation.
The WFMS generally meets City drainage performance criteria (Figures 57 to 66).
However, some low-lying areas along the western boundary of the scheme do not fully
meet the performance criteria. This will lead to localised ponding during minor storm
events due to insufficient grade. It is worth noting that these low-lying areas were
previously wetlands where cane cultivation has expanded during the past 30 years.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 11 of 180
Key recommendations:
Collect headloss and flow data across flap gates. The information can be used to inform
future hydrodynamic modelling and to test structure performance, for example, Structures
12 (Photo 2) and 33 (Photo 18).
Monitor drainage time at a number of control points during future flood events for future
hydrodynamic model calibration.
Define a new service level (drainage time criteria) for cane farming land lower than one
metre AHD to take into account the effects of ponding and the expansion of sugar cane
cultivation. Consideration of the 2007 CSIRO study that identified the areas of land which
are unsuitable for crop production to be included in future land use planning.
The results from this study should be used as the basis for future impact assessment
across the WFMS catchment.
Due to the rapid development within the WFMS catchment, for instance, Gainsborough,
Marks Road etc, the hydrodynamic model needs to be updated every two years to take
into account changes in the floodplain and in the upper reaches of the catchment.
For future hydraulic studies, consider the impacts of climate variability including a
projected rise in sea level. Future studies should also take into account infiltration losses
into the groundwater table and evaporation losses.
The cost estimates presented in this report are approximates and no cumulative benefit
for drainage upgrades has been undertaken (including the cost of replanting fully
damaged crops). It is recommended that a detailed cost benefit analysis be undertaken
to assess the exact viability of drainage upgrades.
Prepare a detailed database of all hydraulic structures within WFMS for future
hydrodynamic modelling.
Undertake an airborne laser survey of the cane area during planting season and at low
tides, to develop an accurate digital elevation model for hydrodynamic modelling.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 12 of 180
Description
Remove or Replace
Structures 39 and 40
Comments
Replace Structure 2
(minor road crossing)
New easements:
Behms Creek
Kerkin Drain
10
Private crossing.
Private crossing.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 13 of 180
2. Introduction
2.1
Overview
In the 1960s, the Woongoolba Flood Mitigation Scheme (WFMS) was constructed to promote
agricultural activity within the flood-prone Woongoolba region. The scheme was first
conceived to enable drainage of a 10-year ARI flood event to 0.9 metres AHD in five days
(based on estimates of this study). The drainage time criteria was later revised, based on
data from the Department of Primary Industries (DPI) which indicated cane should not be
inundated for more than three days. In recent years, the City of Gold Coast has adopted
drainage time criteria of a one-in-10-year ARI flood, with a storm of 72 hours duration being
contained by scheme drains within four days.
It is worthwhile to note that the flood estimation methodology in 1972 is very different to the
present time.
The scheme entails tidal gates and man-made and natural drainage systems, as well as
levees, and was completed in 1977. Since then, the scheme has undergone continuous
improvement from both landholders and the City of Gold Coast. This has included the
installation of large, custom gates at the three major outlets from the system (Pimpama
River, Behms Creek and Sandy Creek) to limit tidal inflow into the scheme. More importantly,
the catchment has experienced significant residential, commercial and industrial
development in the upper reaches. This has raised concerns over the ability of the drainage
scheme to meet the drainage time criteria, thus affecting cane crop yields.
The Citys Natural Hazard Team, in association with Water Modelling Solutions Pty Ltd,
developed a hydrodynamic model using the best available information and methodology to
ascertain the existing WFMS performance. This report documents the modelling
methodology and presents the new one-in-10-year ARI flood maps. It also summarises the
performance of recommended strategies to alleviate the existing flooding problems within the
WFMS.
2.2
Study objectives
determine the performance of the present WFMS relative to the adopted drainage criteria
investigate siltation of bed level of different rivers, creeks and drains based on available
surveyed cross sections along channels in different years
test different scenarios to find viable drainage upgrades that would improve drainage
performance of the study area
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 14 of 180
2.3
Limitation statement
The hydraulic report was prepared based on information available at the time of writing.
The analysis and overall approach adopted by this study are specifically for internal use.
For this reason, no third parties are authorised to use any content from this report and its
use is prohibited unless written approval is obtained from City of Gold Coast.
City of Gold Coast believes the assessment is accurate for its intended purpose and
disclaims any responsibility for any loss or damage suffered as a result of reliance being
placed on information provided in this report.
The model grid is based on airborne laser surveys conducted between 30 April 2009 and
9 June 2009. Any development or a topographical change to the model grid after this
date is not documented in this report.
The airborne laser survey data acquisition and post-processing have been controlled to
achieve a vertical accuracy of 0.15 metres (rms) and horizontal accuracy of 0.45 metres.
2.4
Acknowledgements
City of Gold Coast acknowledges the Griffith University, Bureau of Meteorology and Marine
Safety Queensland for providing calibration data for this project.
City of Gold Coast also acknowledges the Rocky Point District Cane Growers Organisation
for providing valuable information and assistance to the project team.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 15 of 180
3. Background
3.1
The Woongoolba catchment extends from the Darlington Range in the west to McCoys
Creek in the south-east and Logan River in the north-east. The suburbs of Pimpama,
Norwell, Gilberton, Jacobs Well and Steiglitz are all located within the WFMS. The total
catchment area of the Woogoolba floodplain is about 190km2 with potential flooding from the
Logan/Albert River catchment, which has an area of about 3878km2. Three major rivers and
creeks flow through the Woongoolba floodplain, the Pimpama River, Behms Creek and
Sandy Creek. The upper catchment consists of steep hills to the east of the Pacific Motorway
while the lower catchment is a flood-prone, flat landscape. About 55 per cent of the floodplain
is below Highest Astronomical Tide (HAT) level.
The Woongoolba Flood Mitigation Scheme (WFMS) covers most of the lower catchment area
(Figure 1). It is bounded by a system of constructed levees to the north and east and by the
Pacific Motorway in the west. It also entails scheme drains and natural creeks and rivers
which transect the floodplain, discharging flood flows to the north and east of the scheme,
mainly through Pimpama River and its tidal outlet.
It is worth noting that regional flooding from the Logan or Albert River can also inundate the
Woongoolba area. However, for the purpose of this study, the scheme is not intended to
resolve this type of regional flooding, but rather is intended to mitigate local flooding within
the Woongoolba catchment from the Pimpama River, Behms Creek and Sandy Creek.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 16 of 180
Figure 1
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 17 of 180
3.2
The WFMS was created in line with Section 47 of the Local Government Act 1936 to enable
land owners to create a drainage scheme to alleviate flood losses and to increase cane
production (shown by the original plan in Figure 2. The planning for drainage within the
Woongoolba floodplain commenced in the 1960s, entailing the construction and operation of
tidal gates and open drains as well as a number of flood levees (Ref 1). The Local
Government Act 1936 was later repealed by the Local Government Acts of 1993 and 2009,
as outlined below. City of Gold Coast is obliged to maintain the schemes drains in line with
Councils resolution (Ref 18) and the Citys Stormwater Drainage Management Strategy.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 18 of 180
The flood levees were mainly constructed at 1.8 metres AHD (or RL 6.0ft) to prevent the
maximum recorded level during a storm surge of 1.73 metres AHD (RL 5.7ft) from
overtopping and flooding the Woongoolba area. A basin to store and attenuate the flood
flows before they entered the WFMS area was also proposed but never constructed.
Figure 2
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 19 of 180
Figure 3
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 20 of 180
Figure 4
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 21 of 180
Figure 5
This expansion to low-lying areas is also evident in the topographical information (2m DTM)
as shown in Figure 6. An estimated 35 per cent of the area within the Woongoolba Flood
Mitigation Scheme has an elevation of less than one metre AHD (Error! Reference source
not found.). To mitigate persistent flood problems, the cane farmers constructed numerous
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 22 of 180
local drainage channels. The City is responsible for maintaining drains within easements and
private land owners are responsible for maintaining their own drains. Based on a 2007
CSIRO study, these low-lying areas in the WFMS were found to be unsuitable for crop
production (Figure 7, Ref 5). Figure 8 shows these minor drains and the layout of the
drainage scheme today.
Figure 6
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 23 of 180
Figure 7
Areas of the Rocky Point cane lands considered unsuitable for crop
production (Source: CSIRO 2007)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 24 of 180
Figure 8
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 25 of 180
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 26 of 180
Figure 9
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 27 of 180
3.3
Previous studies
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 28 of 180
A RORB hydrologic model and a MIKE11 hydraulic model of the region were developed for
the study. The model boundaries and extents are provided in Section 13.
The summary of the study is as follows:
WFMS layout was based on 1991 aerial photos with drains and structures based on 1994
ground surveys.
An estimated rainfall Intensity Frequency Duration (IFD) of 236mm for the one-in-twoyear ARI flood with 72-hour storm duration
A 1D hydrodynamic model (MIKE 11) was developed using 1994 survey information,
subdivided into various catchments (Old Sandy Creek, Wolfs Drain, Kerkins Drain and
Sandy-Behm Creek). A total of 38 structures was included.
The flood storage for the model was estimated from the 0.5 metre contours and 1991
aerial photos.
As a model boundary, the study used an artificial tidal prediction at Jacobs Well,
Cabbage Tree Point and the Logan/Albert River confluence using Brisbane Bar tidal
constituents.
The study considered future development based on the 1994 Strategic Plan.
Performance Criteria: one-in-two-year ARI 72-hour storm contained within three to four
days.
Maintenance is important.
The study found that the western and upper portion of the WFMS were susceptible to
flooding. A number of upgrade scenarios was tested using the hydrodynamic model, with
recommendations to replace and upgrade structures made in the report.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 29 of 180
The WFMS layout was based on the 1991 aerial photos and drains and structures were
based on 2004 ground surveys
Some modification to the Yatala inflows were made based on the RAFTS model.
The one-in-10 year ARI was estimated based on a factor of 1.6 from the one-in-two-year
ARI event.
An estimated rainfall IFD of 236mm for the one-in-two-year ARI flood with 72-hour storm
duration
A single 1D hydrodynamic model (MIKE 11) was developed using 2004 survey
information. A total of 38 structures was included.
The flood storage for the model was estimated from the 0.5 metre contours and 1991
aerial photos.
As a model boundary, the study used an artificial tidal prediction at Jacobs Well,
Cabbage Tree Point, the Logan/Albert River confluence and Pimpama using tidal
constituents.
Performance Criteria: one-in-two-year ARI 72-hour storm contained within three to four
days.
Structure 26 ($240,000)
Structure 10 ($150,000)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 30 of 180
The present condition was evaluated and compared with the previous 1D study.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 31 of 180
Further discussion of this hydrology study is contained in Section 4.4 of this report.
3.3.9 Pimpama River Catchment and Stormwater Management Plan (Ref 11)
Gold Coast City Council commissioned BMT WBM in 2008 to undertake the Pimpama
Stormwater and Catchment Management Plan.
The study determined a number of stormwater management strategies was required to
ensure the water quality of the river and creeks as well as the estuarine system are not
affected by pollution. The plan is currently being implemented by Catchment Management.
tide level measurements (10 sites at 15-minute intervals for three months from midSeptember to mid-December 2003)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 32 of 180
tide current measurement (ADCP measurement at six locations every 30 minutes for one
complete tidal cycle during a spring and a neap tide.
3.3.13 Aquifer Storage and Recovery Assessment (Ref 25, 26, 27 and 28)
Gold Coast Water (GCW) engaged SKM to undertake a study to determine seasonal storage
to maximise the use of recycled water and minimise discharges of recycled water to the
environment as part of the Pimpama Coomera Water Future project.
The Aquifer Storage and Recovery (ASR) project could provide this seasonal storage
whereby a number of investigations that will be required prior to the establishment of an
operational ASR scheme.
A groundwater model was developed for this study using MODFlow.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 33 of 180
4.1
The general approach of simulating a regional flood event is to develop and to calibrate the
hydrological model to derive parameters that are used to determine design discharge. The
output is then used as input into the hydrodynamic models to develop flood levels.
In simple terms, the science of hydrology is to convert rainfall data into discharges (or flows).
On the other hand, the science of hydrodynamic modelling is to convert those discharges
into water level and velocity.
A regional flood occurs where heavy rainfall falls into the water catchment areas, especially
in the upper reaches, and flows down along the river then out to the floodplain. Severe
flooding occurs when these flood flows coincide with very high tides (for example storm
surges). A regional model, using a 2D approach, is generally developed to simulate the
complex flows in the floodplain and to simulate flows in constricted areas such as bridges
with piers.
Other types of flooding that can occur include stormwater flooding (due to blockage), and
flash flooding (due to very heavy rainfall within a short period of time). These are generally
categorised as localised flooding for which a 1D local stormwater model is generally
developed.
4.2
Datums
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 34 of 180
4.3
Data availability
A large amount of data is required to develop a hydraulic model. This includes, but is not
limited to, topographic and bathymetric surveys, structure surveys, etc.
For model calibration, surveyed and recorded water levels, as well as anecdotal evidence,
are required.
Year
Region
1993
2004
2007
Hotham Creek and Pimpama River downstream of rail line to Kerkin Road
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 35 of 180
Year
Region
2009
2010
Behms Creek
2012
Intercon Drain
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 36 of 180
Figure 10
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 37 of 180
Figure 11
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 38 of 180
Figure 12
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 39 of 180
The following figure shows the tidal planes for semi-diurnal tides. The actual values have
been obtained from Marine Safety Queenslands 2013 tidal plane chart (Refer Section 11).
Figure 13
Figures 25 and 27 show the HAT reference points and modelled HAT extent
As well as tidal planes, storm surges can also influence outflow from WFMS. For the
purpose of this study, these storm surge values were not adopted for the one-in-10-year ARI
flood event. However, future studies must consider climatic variability (refer Table 2 and
Table 3
Table 2
ARI
2.04
2.50
2.10
2.58
20
2.23
2.70
50
2.33
2.80
100
2.41
2.90
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 40 of 180
ARI
200
2.50
3.05
500
2.58
3.30
2,000
2.68
3.60
ARI
1.16
1.60
1.25
1.69
20
1.37
1.80
50
1.47
1.88
100
1.54
1.94
200
1.62
2.00
500
1.69
2.10
2,000
1.78
2.36
Table 4
ARI
2.04
2.50
2.10
2.58
20
2.23
2.70
50
2.33
2.80
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 41 of 180
ARI
100
2.41
2.90
200
2.50
3.05
500
2.58
3.30
2,000
2.68
3.60
No
Location
Flood Level
(m AHD)
Date
Photo (refer
Section 18)
Remarks
Mischke Property
3.08
Jan 1974
Photo 48
Near Structure 26
1.51
25/1/2012
Photo 47
Skopp Property
0.67
10/11/2004
Photo 42
See photos
Near Structure 19
1.45
25/1/2012
Photo 40
Near Eggersdorf
Rd
1.60
2010
Photo 49
Various events in
2010
Near Structure 9
1.36
25/1/2012
Photo 41
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 42 of 180
Figure 14
An estimated one-in-10-year flood occurred between 27 January 2013 and 1 February 2013
due to the path of Ex-Tropical Cyclone Oswald. Heavy rainfall was experienced in the upper
reaches of the Logan River, Albert River, Pimpama River and the Gold Coast Hinterland.
Refer to Section 16 for photos of WFMS on 29 and 30 January 2013.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 43 of 180
For the rainfall report, please refer to the Bureau of Meteorology (BOM) report on this event
(Ref 15).
4.3.7 Alert stations
A number of BOM alert stations, which collect real time water level (WL) and rainfall data
(RF),.exist within the Woongoolba catchment This data is useful to calibrate against
historical flood events as it provides the shape and the magnitude of flood hydrographs.
Table 5 lists the locations of the alert stations and their date of installation and Figure 15
shows the locations graphically.
In addition, alert stations provide an indication of the water level within the schemes drains
at the beginning of a flood event. The long-term average water level may also be derived.
Table 6
CBM
Location
Date
installed
Owner
Type
540295
Steiglitz Wharf
4/4/2003
the City
WL & RF
540294
Kerkin Road
21/5/2002
the City
WL & RF
540408
Norwell
9/12/2010
the City
WL & RF
540377
Stewarts Road
Unknown
the City
WL & RF
540376
Hotham Creek
Unknown
the City
WL & RF
540236
Carbrook
(Riedel Rd)
18/3/1998
BOM/LCC
WL & RF
A survey was undertaken in April 2013 to determine the extent of discrepancies in alert
station recordings. It is worth noting that future model calibration to recorded water levels
must be checked against the estimated error as shown below:
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 44 of 180
Figure 15
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 45 of 180
Figure 16
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 46 of 180
Figure 17
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 47 of 180
4.3.10 Evaporation
Although evaporation is important, in terms of flood extent after four days, there is a lack of
information that can be used in the hydrodynamic modelling. It is envisaged that future
hydrodynamic modelling should take into account evaporation losses.
Evaporation data can be obtained from the Long Paddock website longpaddock.qld.gov.au/
4.4
Hydrological inputs
The hydrological model derives design discharges for the hydrodynamic models based on
the methodology outlined in Section 2 of Volume 1 of Australian Rainfall and Runoff 1998
(Ref 16). It is divided into the Logan/Albert River and Pimpama region as shown in Figure 19.
The rainfall data is based on the citywide study undertaken by AWE in 1992 (Logan) (Ref 9)
and 1998 (Pimpama), (Ref 19). On the other hand, the temporal patterns (rainfall distribution)
are based on the 2008 WRM Review Study (Ref 17) and other hydrological factors are based
on the recent hydrological study (Ref 7) which is summarised in Table 6 below.
The temporal patterns used in the present study and those used in the 1994 and 2004
studies are shown in Figure 18. This shows that rainfall peaked in the first four hours from
previous studies. For the present study, the rainfall peaked at the middle of the 72-hour
storm. This has some ramifications as the earlier peak flood will flow out of the WFMS
before the next peak (which is about 32 hours away) which is evident in the three peaks of
the previous floods. More importantly, the semi-diurnal nature of the tide in this region will
peak about every 12 hours which can influence the flood extent of the design storm event.
Table 7
Unified River Basin Simulator (URBS) model parameters for Pimpama and
Logan River catchment
Parameter
Pimpama
Logan
0.3
0.2
2.5
0.75
0.75
Forest factor
0.5
0.5
The one-in-2-year ARI flood and one-in-10-year ARI flood and 72-hour duration storm for the
2010 planning horizon was used for this study as this was the basis of the Council resolution
for the drainage time performance (Ref 18). No climate variability factors have been applied
to the rainfall intensities.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 48 of 180
Termporal Pattern
25.0%
20.0%
15.0%
10.0%
5.0%
0.0%
1
10
11
12
13
14
15
16
17
18
Figure 18
Figure 19
A brief description of Logan/Albert Rivers and Pimpama River catchment hydrology is briefly
described as follows:
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 49 of 180
4.5
A hydrodynamic model was developed to convert the discharges from the hydrological model
into water levels and to dynamically simulate complex flood flows and velocity in a floodplain.
These models are based on the MIKE software platform which is capable of simulating
complex flow, especially in areas where there are complex canal and hydraulic structures
(Ref 20). The software takes advantage of the 2D topographical grid, that simulates complex
flow paths and flood plain storage, and the 1D hydraulic structures that simulate flow
constriction.
The software version used for this study is MIKE Flood 2011 Service Pack 7. For further
details of the MIKE software, please refer the MIKE User Manual (Ref 20).
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 50 of 180
catchment centroids (Figure 20). For the 1D component, it is incorporated as a point and
distributed source.
A total of 58 inflows, 19 in MIKE 11 and 39 in MIKE 21 was assigned in the Woongoolba
hydraulic model.
Figure 20
In addition to the rainfall source, the Woongoolba hydrodynamic model has seven tidal
boundaries and two river boundaries (the Logan and Albert Rivers). The tidal boundaries are
based on the modelled 2013 tidal planes using a calibrated estuarine model (Ref 13). The
tidal planes are provided in Section 11.
4.5.3 Eddy viscosity
A global eddy viscosity (velocity-based) value of 1.0m2/s, estimated based on the following
equation, is applied for the floodplain. It is used mainly to parameterise flow eddies.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 51 of 180
e = 0.1 Depth
4.5.4 Model roughness
The key calibration parameter for the hydrodynamic model is the floodplain roughness or
Mannings M roughness coefficient. Based on literature review and past studies, the
following roughness values were adopted (Table 7).
Table 8
Description
Mannings M
Mannings n
Road
50
0.020
Waterways
40
0.025
30
0.033
Forest/dense brush
8.33
0.120
Mangroves
16.67
0.060
Seagrass
28.5
0.035
25
0.040
22.22
0.045
13.33
0.075
Chapter 4 of the Department of Main Roads Road Drainage Design Manual (Ref 22)
Appendix C of Brisbane City Councils Natural Channel Design Guidelines (Ref 23)
A roughness map was developed from aerial photography and City of Gold Coasts Landuse
GIS layers, as shown in Figure 21 (below).
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 52 of 180
Figure 21
Where it has been necessary to use cross-sections extracted from the DEM using GIS, this
has been clearly identified in the models cross-section ID. It should be noted that the
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 53 of 180
proposed design cross-sections for locations with scheduled dredging have not been built
into the model at this stage.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 54 of 180
Figure 22
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 55 of 180
Figure 23
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 56 of 180
4.6
Two known tide recording campaigns have been used to calibrate the regional estuarine
model (discussed in Section 4.8). The 2004 campaign was part of the PREES project
whereby the water levels and ADCP (current) were collected around the Pimpama River (Ref
12). The 2005 campaign was part of the GEMS project (Ref 13 and 24). The water levels
and ADCP (current) were collected at a number of locations along the Logan and Albert
Rivers as well as within the Broadwater.
4.7
In January 2013, very intense rainfall fell on the upper reaches of the Logan and Nerang
catchments. This caused flooding in and around Logan as well as of parts of Woongoolba.
Much data is available for this flood event, making it ideal for model calibration. The first step
was to undertake a hydrological model calibration at a number of key locations (refer Section
17 for photos and calibration plots). Further details of hydrological model calibration are
documented in the 2013 hydrological study (Ref 7). The Bureau of Meteorology also has
prepared a report for this event (Ref 15).
Once calibrated, the hydrological model is used to convert the rainfall to inflows which are
subsequently used as inputs for the hydrodynamic model for calibration. The tidal
boundaries of the model are sourced from the regional estuarine model (Ref 13).
Figure 24 shows that while the model produced a reasonable match, in terms of shape of the
water plot, the peak flow differed by about 0.5 metre to the recorded water level at Kerkin
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 57 of 180
Road. More importantly, the model performed quite well in the falling limb of the hydrograph.
This is useful in determining the drainage time of the WFMS.
0.5
-0.5
-1
26/01/2013
0:00
26/01/2013
12:00
27/01/2013
0:00
27/01/2013
12:00
28/01/2013
0:00
28/01/2013
12:00
29/01/2013
0:00
29/01/2013
12:00
30/01/2013
0:00
Date
Figure 24
4.8
As previously described in Section 3.2, in 2005 Council adopted the one-in-10-year ARI flood
with 72-hour storm duration as the drainage performance criteria for the WFMS (Ref 18).
This was an increase from the original one-in-two-year ARI flood proposed in the 2004 study
(Ref 3). An estimated one-in-two-year ARI is shown in Figure 94.
However, previous modelling attempts were all based on a 1D model approach which is
limited to the cross-sectional information and flood storage assumption (Ref 1, 2, and 3). To
better model the drainage time criteria, the study uses a calibrated 2D hydrodynamic model
with fine model grid resolution. That is, using a 10-metre model grid size and 1D model
network for simulating flows in drains.
More importantly, this study develops a calibrated hydrological model and uses the latest
survey information and data to derive the one-in-10-year ARI flood estimation. The following
table summarises the previous methodology and data to derive the drainage performance
criteria.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 58 of 180
Table 9
SKM
1994 (Ref 2)
GCCC 2004
(Ref 3 and 4)
City of Gold
Coast 2013
(current study)
Hydrological model
NA
RORB
NA
URBS
Hydrology
Estimated
Calculated
Calculated
Calculated
(rainfall data)
(five representative
floods)
(1987 AR&R)
(1987 AR&R)
Hydrology (temporal
pattern/rainfall
distribution)
NA
1987 AR&R
1987 AR&R
2008 WRM
Calibration
NA
None
None
January 2013
One-in-10-year ARI
flood estimation
NA
Estimated
Estimated
Estimated
(1987 AR&R
methodology)
(1987 AR&R
methodology)
Artificial MHWS
Artificial MHWS
Modelled HAT
(three stations)
(three stations)
(modelled)
1991 Aerial
1994 survey
2004 survey
2010 survey
1D
1D
2D (10m) and 1D
(MIKE 11)
(MIKE 11)
(MIKE flood)
Tide
NA
Topography
Structures
NA
Hydrodynamic model
2D verification
(MIKE flood)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 59 of 180
To simulate the one-in-10-year ARI design floods, the highest astronomical tide (HAT) was
simulated and compared to the 2013 tidal planes (Section 11). The 10 tidal boundaries were
then applied to the model as shown in Table 8 and Figure 25.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 60 of 180
Figure 25
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 61 of 180
Location
Tailwater peak
(m AHD)
Tide station
/interpolation
Comments
1.61
1.44
Jacobs Well
1.29
Jacobs Well
Couran Cove
1.03
Couran Cove
BND 10
1.03
Couran Cove
BND 7
1.31
Interpolated
BND 4
1.43
Interpolated
BND 3
1.47
Interpolated
BND 1 and 2
1.53
Rocky Point
A typical tidal cycle, as seen in Figure 26, was used to simulate the HAT tidal conditions.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 62 of 180
1.5
Couran Cove
Rocky Point
0.5
-0.5
-1
10/01/2010 0:00
9/01/2010 0:00
8/01/2010 0:00
7/01/2010 0:00
6/01/2010 0:00
5/01/2010 0:00
4/01/2010 0:00
3/01/2010 0:00
2/01/2010 0:00
1/01/2010 0:00
Figure 26
Time
The figure below shows the regional estuarine performance against the 2013 tidal planes.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 63 of 180
Figure 27
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 64 of 180
Behms Creek
Sandy Creek
Pimpama River
Hotham Creek
Intercon Drain
Based on the analysis, the results show that siltation has occurred in most locations. The
results also show that recent dredging activity has increased the depth of some of the drains.
The comparisons are shown as Figure 29 to Figure 40.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 65 of 180
Figure 28
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 66 of 180
Figure 29
1.5
0.5
-0.5
-1
2012 (source: M11 2012)
1994 (source: M11 2004)
-1.5
-2
0
10
20
30
40
50
60
70
80
90
Chainage (m)
Figure 30
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 67 of 180
Behms Creek
1.5
0.5
-0.5
-1
-1.5
2012 (source: M11 2012)
1994 (source: M11 2004)
-2
-2.5
20
30
40
50
60
70
80
Chainage (m)
Figure 31
A clear trend towards siltation is shown for Behms-Centre drain between 1994 and 2009
(refer Figure 32 below).
Figure 32
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 68 of 180
Behms Centre
1
0.5
-0.5
-1
-1.5
2009 (source: M11 2012)
-2
-3
10
15
20
25
30
35
40
45
50
Chainage (m)
Figure 33
Figure 34
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 69 of 180
Sandy Creek
1.5
0.5
-0.5
-1
2012 (source: M11 2012)
1994 (source: M11 2004)
-1.5
-2
0
10
15
20
25
30
Chainage (m)
Figure 35
Figure 36
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 70 of 180
Pimpama River
1
0.5
-0.5
-1
-1.5
2007 (source: M11 2012)
1994 (source: M11 2004)
-2
-2.5
20
25
30
35
40
45
50
55
60
Chainage (m)
Figure 37
Figure 38
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 71 of 180
Hotham Creek
2
1.5
1
0.5
0
-0.5
-1
-1.5
-2
-2.5
10
20
30
40
50
60
70
Chainage (m)
Figure 39
Figure 40
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 72 of 180
Intercon
1
0.5
-0.5
-1
-2
10
15
20
25
30
35
40
45
50
Chainage (m)
Figure 41
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 73 of 180
6.1
Sugar cane is highly tolerant to short-term flooding in comparison to other crops. However,
sugar cane losses occur when the flood inundation persists over extended periods (Ref 2).
Furthermore, according to SKMs report, waterlogging within the sugar cane root zone over
long periods can lead to lower yields. The optimal ground water level should fluctuate
between 0.5 to two metres below the soil surface to ensure adequate soil moisture during
prolonged dry periods.
These flooding and waterlogging criteria provide the basis for the design of the WFMS.
The drainage time criteria starts at the onset of the flood, that is the start of the hydrograph
rising limb. This means that the peak flood is about one day after the onset of the flood
(based on the adopted temporal pattern).
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 74 of 180
In simple terms, a development should not cause any nuisance flooding impacts on
properties upstream or downstream. The SMP should achieve the principles and intentions
of the policies and guidelines of the:
City of Gold Coasts Constraint Code, especially its Flood Constraint Code
The Department of Energy and Water Supplys Provisional Queensland Urban Drainage
Manual (Ref 21).
6.2
In the previous study, three areas were divided geographically to determine the performance
criteria of the WFMS (Ref 2). For this study, the same three geographical areas were used
(as shown in Figure 42):
Pimpama River and its tributaries (Hotham Creek, Kerkins Drain, Norwell Drain and
Oppman Drain
Behms Creek and its tributaries (Gross Drain, Gilberton Drain and Schoff Drain)
Sandy Creek, Old Sandy Creek, Gems Drain, Wolfes Drain and Bremmerhavers Drain).
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 75 of 180
Figure 42
To evaluate the performance of the present WFMS, the one-in-10-year ARI flood was
estimated, as discussed in Section 4.8, for high condition. The performance of the drainage
system was compared against the original flood duration curve (Figure 43 created from
Figure 4) as documented in the 1972 study (Ref 1). A comparison of the 2004 results also
was made.
It is worth noting that the design flood estimation has changed significantly since the 1960s.
Hence the comparisons of the following flood curves are indicative, not absolute.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 76 of 180
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 77 of 180
Figure 44
1.5
Pimpama
0.5
-0.5
-1
0
10
11
12
Days
Figure 45
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 78 of 180
1.5
0.5
-0.5
0
10
11
12
Days
Figure 46
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 79 of 180
After four days, there are still pockets of flood affected areas which can take days to drain or
evaporate.
In comparison with the previous 1994 study, the performance of the WFMS means it can
generally drain within three days in most areas of Sandy Creek, with the exception of the
western region (Ref 2). This is true for the present study as performance of the WFMS here
is within the adopted drainage criteria and well below the 1972 drainage design criteria.
1.5
0.5
-0.5
0
10
11
12
Days
Figure 47
6.3
A number of proposed upgrades to the WFMS was made in the 1994 study (Ref 2) and 2004
study (Ref 3). The proposed works are considered and reviewed by key stakeholders within
the scheme. The following table summarises the status of these upgrades.
Note: The structure numbering is shown in Figure 23.
Table 11 Status of previous upgrades and recommendations (1994 SKM)
Drain
2013 status
Remarks
Not attempted
Ecologically sensitive
Pimpama River
Behms Creek
Completed in 2004
Structure 12 replace
5/2500x3600 radial gates and
(4/3000x3000 gates
lower invert to RL -1.60m
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Behms Gate/Outlet
Refer Error! Reference
Page 80 of 180
Drain
2013 status
Remarks
AHD.
Structure 17 replace
4/3000x1500 RCBC with
4/3000x2100 RCBC at IL 1.50m AHD.
Completed in 2004
(4/3000x2100 gates
constructed at RL -1.4m AHD)
Structure 19 replace
3/3000x1200 RCBC with
3/3000x2100 RCBC at IL 1.00m AHD.
Completed in 2004
Norwell Road
(4/3000x2100 RCBC
constructed at RL -1.0m AHD)
Sandy Creek
Private road
Refer Photo 10 and Photo
11
40 3/1520 RCP
Structure 26 replace 6/1200 Completed between 2010 and
2013
RCP with 3/2400x1500
RCBC, and lower to RL (3/2100x1800 & 2/ 2100x2000)
1.00m AHD.
RCBC constructed at RL -1.0m
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Stapylton-Jacobswell
Road (Gems Drain)
Refer Photo 12 and Photo
13
Page 81 of 180
Drain
2013 status
Remarks
AHD)
Completed (email
confirmation)
Not completed
Sandy Gates
Refer Photo 14
Oppman Drain
Structure 10 lower
1/3050x2100 RCBC to RL 1.30m AHD.
Gems Drain
Private road
Refer Photo 26, Photo 27,
Photo 28 and Photo 29
Burnside Road
Refer Photo 30
27 4/1200x900 RCBC
(existing)
Stapylton-Jacobs Well
Road
Refer Photo 31 and Photo
32
Kerkin Drain
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Private road
Refer Photo 33, Photo 34
Page 82 of 180
Drain
2013 status
Remarks
structures.
structures)
and Photo 35
Not completed
2 1/1500x600 RCBC
(existing)
Wolfes Drain
Repair Structure 33
(Downstream Face/Flap
Gate)*
Not completed
Powerline Road/Marks
Road
Refer Photo 18
Homestead Road
Refer Photo 19
Gross Drain
Gross Road
Refer Photo 19
13 3/1200x1050 RCBC
(existing)
13A 1/900 RCP (existing)
Repair Structure 1 (repair flap Completed (time unknown)
gate)
Schoff Drain
1 3/1800 RCP (existing)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 83 of 180
Drain
2013 status
Remarks
Skopps Road
Norwell Road
Norwell Road
1 3/3050x1650 RCBC
(existing)
Behms Creek
Not completed
Stormwater easement
channel between Structure 22
and 50
Re-grade 800m section of
drain to IL -1.2m AHD.
Completed in 2004
Refer Figure 51
Kerkin Drain
Not completed
Refer Figure 51
Completed in 2004
Sandy Creek
Not completed
Not completed
Schoff Drain
Version 5 November 14
Not completed
woongoolba-hydraulic-study-201409-report.docx
Page 84 of 180
Drain
2013 status
RCP)
Remarks
side drain)
Refer Photo 38
Not completed
Not completed
Sandy Creek
Not completed
Kerkin Drain
Structure 10 lower
2/3050x2100 RCBC to RL 1.30m AHD (flap gates to be
cost evaluated).
Private Road
Refer Photo 10 and Photo
11
Version 5 November 14
Oppman Drain
Stapylton-Jacobswell
Road (Gems Drain)
woongoolba-hydraulic-study-201409-report.docx
Private road
Refer Photo 33, Photo 34
and Photo 35
Page 85 of 180
Drain
2013 status
$30,000)
Remarks
* Marks Road - There are some changes along Marks Road due to the development around the prawn farm and sand mining
area (Refer Section 3.23.2 for details). However, these changes have not been incorporated into this study as the changes
are still ongoing.
Figure 48
Location of proposed upgrades from the 1994 study (Ref 2) and status of
those upgrades
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 86 of 180
Figure 49
Location of proposed upgrades from the 2004 study (Ref 3) and status of
those upgrades
Figure 50
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 87 of 180
It was noted in the 2004 study that a number of easements should be established to ensure
connectivity along the WFMS (Figure 51).
Figure 51
6.4
Upgrade options
The previous sub-section describes the proposed upgrade strategies outlined in the 1994
(Ref 2) and 2004 (Ref 3) studies. Additional upgrade strategies are proposed and tested in
this study. The new strategies are tested against the base case which is the one-in-10-year
ARI 72-hour duration storm with HAT tailwater as the adopted drainage criteria.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 88 of 180
Figure 52
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 89 of 180
6.4.2 Option 2 - Automated tide gates at Behms Creek and Kerkin Road Weir
Previously, automated radial gates were proposed and installed at Behms Creek and
Pimpama (Kerkin Road). These are Structures 12 and 59 shown in Figure 52. However,
they were removed due to vandalism and replaced with steel gates (refer Section 15 for
drawings). To test the functionality of automated gates, a scenario was created in which they
were operated based on the tide prediction at the Gold Coast Seaway tide station.
The operation of the gates was set up as follows:
All gates are open if the tide level is <-0.2 metres AHD or 0.8 metres AHD to lowest at
falling tides.
All gates are closed when the tide level is >= -0.2 metres AHD at rising tide or peak to 0.8
metres AHD at falling tides.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 90 of 180
Figure 53
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 91 of 180
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 92 of 180
Figure 54
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 93 of 180
Figure 55
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 94 of 180
Maximum possible
inundation*
Inundation after
three days (after two
days of tailwater
peak)
Inundation after
four days (after three
days of tailwater
peak)
Area
(hectares)
Volume
(ML)
Area
(hectares)
Volume
(ML)
Area
(hectares)
Volume
(ML)
4,380.57
20,626
2,475.7
5,133
1,775.36
2,421
4,374.37
20,559
2,450.18
5,030
1,757.91
2,367
4,578.59
22,133
2,887.78
7,287
2,196.44
3,797
4,401.64
20,497
2,455.97
4,991
1,755.92
2,343
4,173.37
19,377
2,078.29
3,679
1,498.64
1,811
4,071.07
18,784
1,899.42
3,112
1,446.18
1,742
4,305.45
19,885.49
2,279.7
4,226
1,608.03
1,985
4,192.64
19,174.62
2,316.67
4,613
1,662.43
2,193
Base
Option 1
Two additional gates at Behms
Creek
Option 2
Auto gates
Option 3
Straightening of Behms Creek
Option 4a
3
10m /s pump
Option 4b
3
15m /s pump
Base
Option 1
Two additional gates at Behms
Creek
*calculated from maximum water level at each model cell at any time
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 95 of 180
Table 13 Difference in inundation area and volume of water compared with base case
Reduction of
maximum possible
inundation*
Reduction of
inundation after
three days (after two
days of tailwater
peak)
Reduction of
inundation after
four days (after three
days of tailwater
peak)
Area
(hectares)
Volume
(ML)
Area
(hectares)
Volume
(ML)
Area
(hectares)
Volume
(ML)
6.2
67
25.52
103
17.45
54
-198.02
-1,507
-412.08
-2,154
-421.08
-1,376
-21.07
129
19.73
142
19.44
78
207.2
1,249
397.41
1,454
276.72
610
309.5
1,842
576.28
2,021
329.18
679
75.12
740
196.00
906
167.33
435
187.93
1,451
159.03
520
112.93
228
Option
Option 1
Two additional gates at Behms
Creek
Option 2
Auto gates
Option 3
Straightening of Behms Creek
Option 4a
3
10m /s pump
Option 4b
3
15m /s pump
Option 5
Widening of Behms Creek and
Pimpama River
Option 6
Detention basin
Note: Blue denotes increase; red denotes decrease compared with base
6.5
woongoolba-hydraulic-study-201409-report.docx
Page 96 of 180
Figure 77 shows the flood depth (peak) for a one-in-10-year ARI flood with 72-hour storm
duration and HAT tailwater condition. On the other hand, Figure 78 shows the flood depth
(after four days) for the one-in-10-year ARI flood with storm duration of 72 hours.
6.5.3 Option 2 - Automated tide gates at Behms Creek and Kerkin Road Weir
This option added automated tide gates at Behms Creek and Pimpama outlets. This actually
worsened existing drainage conditions by inundating a greater area and containing a greater
volume of water than the base case scenario (Table 11, Table 12 and Figures 57 to 66). This
may be due to the inefficient operation of the gates combined with the complex natural flood
water flows. Figure 80 shows the increase in flood levels compared with the base case. The
study also shows worsening of flood inundation by 421 hectares (24 per cent of the
inundation area).
It is also worth noting that the automated gates were previously installed but removed due to
vandalism.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 97 of 180
Kerkin Road and Behms Creek tide gates and north and south of Wohlsen Road. It was also
noted that more than 10 centimetres of flood inundation improvement occurred near the start
of the straightening of Behms Creek (Figure 81 and Figure 53).
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 98 of 180
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Page 99 of 180
Figure 56
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Location
Easement width
(m)
Location 1
30
0.85
Location 2
30
0.50
Location 3
35
1.10
Location 4
n/a
0.00
Location 5
30
1.50
Location 6
45
0.30
Location 7
n/a
0.50
Location 8
28
0.50
Location 9
30
0.50
Location 10
n/a
0.30
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 57
Figure 58
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 59
Figure 60
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 61
Figure 62
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 63
Figure 64
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 65
Figure 66
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
expected cane yield of 70 tonnes per hectare and a sugar cane price of $38 per tonne
(provided by City Asset Branch officer and sugar cane grower)
full damage of sugar cane after four days of one-in-10 year ARI 72-hour duration flood
after four days and three days
an approximate drainage upgrade cost provided by the Citys Asset Branch where not
specified.
Table 13 shows preliminary costs of drainage upgrades and the reduction in sugar cane loss
for different upgrade scenarios described in Section 6. It is intended to be used only for the
purpose of capital works budgeting. To access viability of drainage upgrades, calculating
cumulative loss reduction, considering the lifetime of the drainage infrastructure upgrade,
replanting costs etc, is recommended.
Works associated with privately owned farm structures have been excluded.
The results presented in Table 14 show that Option 6 (widening Behms Creek and Pimpama
River) and Option 7 (construction of a detention basin) are not feasible due to high
construction costs.
Table 15 Simplistic cost benefit analysis
Options
Approximat
e cost of
drainage
upgrades
($ million)
Version 5 November 14
3.5
2. ($
million)
1,221
0.07
0.05
woongoolba-hydraulic-study-201409-report.docx
1,786
Options
Approximat
e cost of
drainage
upgrades
($ million)
2. ($
million)
1.5
-29,476
-1.12
-28,846
-1.09
Option 3 - Straightening
Behms Creek
1.0
1,361
0.052
1,381
0.52
20*
19,370
0.74
27,819
1.06
30*
23,043
0.88
40,340
1.53
11,713
0.45
13,720
0.52
7,905
0.30
11,132
0.42
Option 5 - Widening of
Behms:
Behms Creek and Pimpama 7 to 10
River
Pimpama:
10 to 16
50 to 100
Notes:
1. Based on 70 tonnes/hectare
2. Based on $38/tonne
3. Based on 10 per cent probability of a storm occurring every year
4. * Cost of drainage upgrade estimate based on Cairns Regional Councils website
(http://www.cairns.qld.gov.au/about-council/media-and-public-notices/mediareleases/releases/resilient-role-model
5. Far greater benefit gained by diversifying funds elsewhere
6. The risk of not proceeding with drainage capital works may expose the City to insurance
claims for damages, as CSIRO provided evidence that this land was marginal and
therefore unsuitable for crops.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Program of works
Previous studies, 1994 SKM (Ref 2) and 2004 GCCC (Ref 3) recommended a number of
upgrades to increase efficiency of the WFMS (described in Table 10). This study tested
additional drainage upgrades, with the recommended key drainage upgrades presented in
Table 15.
Apart from a capital works program, maintenance of the scheme drains will ensure flood
flows are not restricted. This can be done, either by weed removal or channel re-profiling.
Table 16 Recommended drainage upgrades
Priority
Proposed upgrades
Description
Comments
As seen in Photo 29
(private crossing) the pipe
outlet is blocked by debris
and weed.
Maintenance
Remove or replace
Structures 39 and 40
Replace Structure 2
New easements:
Behms Creek
Kerkin Drain
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Priority
Proposed upgrades
Description
Comments
easement.
10
Although the initial cost of a pump assisted scenario is very high, this scenario produces
better results in terms of reducing crop loss from flood and improving drainage time criteria
(Table 11, Table 13 and Figures 57 to 66).
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
9. Conclusion
The Woongoolba Flood Mitigation Scheme (WFMS) was developed in the 1960s to
encourage agricultural activity in the region. The scheme entails construction and operation
of tidal gates and man-made and natural drainage systems. There is also a system of
constructed levees in the north and east of the Woongoolba region, whose function is to
drain local flooding to the nearest outlet.
During the past 30 years, sugar crop cultivation has expanded further into low-lying areas
which means the performance of the schemes drains is at maximum design capability. In
some areas, cane is grown in areas where the elevation is less than one metre Australian
Height Datum (AHD), which is generally below Highest Astronomical Tide (HAT) level.
Furthermore, the upper reaches of the catchment are constantly changing due to residential
and industrial developments.
Over the years, many hydraulic studies have been undertaken, recommending a number of
drainage upgrades. Since 1994, the scheme has been continuously modified and upgraded
to ensure City of Gold Coasts adopted drainage criteria can be met. Council adopted the
performance criteria that a one-in-10-year ARI flood of 72 hours duration must be contained
within the schemes drains within four days.
To determine the drainage performance, this study used a new and comprehensive 1D/2D
numerically coupled MIKE FLOOD hydraulic model. This has been developed with a
drainage network using the City of Gold Coasts five-metre Digital Elevation Model (DEM)
and extensive cross-sections as well as various structure surveys collected over the years.
The model of this study has been calibrated to the Australia Day 2013 flood event that
showed the model performed reasonably well in terms of the shape of the hydrograph.
However, the model was below the estimated peak flood at Kerkin Road Weir Alert. Once
model calibration was completed, a number of scenario tests was undertaken to determine
whether drainage upgrades could improve the drainage performance. The analysis indicated
minor improvements could be achieved with major upgrades. However, simple cost benefit
analysis would indicate that the costs far outweigh the benefits. It would be far more
beneficial to ensure that drains and drainage structures were maintained, given the
probability of a rain event occurring annually.
In summary, the key outcomes of this study are:
Analysis of aerial photography shows significant expansion of cane farming further into
low-lying land between 1973 and 2009.
Analysis of aerial photography and terrain show that substantial cane farming activity
occurs on land below one metre AHD (HAT range from 1.29 to 1.53 metres AHD for this
region). This means that some areas within the WFMS are unable to drain to the
schemes drains leading to local ponded areas.
Pimpama River conveys the most flow out of the system, followed by Behms and Sandy
Creek.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Survey works in 1994 and 2012 show that siltation has occurred along most scheme
drains during this period. Maintenance of the schemes drains is critical to ensure the
drainage performance is met.
The results from this study differ from those of previous studies. There are fundamental
differences between hydrological and hydrodynamic methodologies and datasets
compared with previous studies. This study has undergone more rigor than previous
studies. For instance, the model in this study uses the latest hydrological inputs (rainfall,
temporal patterns etc) with latest survey information and was calibrated to the most
recent flood. Previous studies have not used such comprehensive data and rigor,
especially calibration to historical flood data.
A number of flood mitigation scenarios was tested to improve the existing WFMS
drainage time criteria. Of the scenarios tested, the most effective was constructing a
storm water pump station but this is very costly. On the other hand, constructing
automated tidal gates can actually worsen a flood situation through improper operation of
the gates. The outcome of testing shows there is a fine balance between the cost of the
upgrades and the benefit of those upgrades.
The WFMS generally meets City of Gold Coasts drainage performance criteria (Figures
57 to 66). However, some low-lying areas to the west of the scheme do not fully meet
the performance criteria and insufficient grades will lead to local ponding. It is worth
noting that these low-lying areas were previously wetlands into which cane cultivation has
expanded during the past 30 years. Infiltration into groundwater and evaporation losses
were not accounted in this study. This can influence the flood extent and drainage time.
Key recommendations:
Collect headloss and flow data across flap gates. The information can be used to inform
future hydrodynamic modelling and to test structure performance. For example,
Structures 12 (Error! Reference source not found.) and 33 (Photo 18)
Monitor drainage times at a number of control points during future flood events for future
hydrodynamic model calibration.
Define a new service level (drainage time criteria) for cane farming land lower than one
metre AHD to take into account the effects of ponding and the expansion of sugar cane
cultivation. Consideration of the 2007 CSIRO study that identified the areas of land is
unsuitable for crop production to be included in future land use planning.
The results from this study should be used as the basis for future impact assessment
across the WFMS catchment.
Due to the rapid development within the WFMS, for instance, Gainsborough, Marks
Road, etc, the hydrodynamic model needs to be updated every two years to take into
account changes in the floodplain and in the upper reaches of the catchment.
For future hydraulic studies, consider impacts of climate variability including a projected
rise in sea level. Future studies should also take into account infiltration losses into the
groundwater table and evaporation losses.
A Land Use Planning/Hydraulic Master Plan Study, with consideration to regional and
local plans as well as State Government policies, should be undertaken to determine the
future of the WFMS.
The cost estimates presented in this report are approximates and no cumulative benefit
for drainage upgrades has been undertaken (including the cost of replanting fully
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
damaged crops). A detailed cost benefit analysis to assess the exact viability of drainage
upgrades is recommended.
Prepare a detailed database of all hydraulic structures within the WFMS for future
hydrodynamic modelling.
Undertake Airborne Laser Survey of the cane area during planting season and at low
tides to develop an accurate digital elevation model for hydrodynamic modelling.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
10.
References
CSRIO. Future Use of Rocky Point Cane Landscapes, Gold Coast. July 2007.
10
11
BMT WBM. Pimpama River Catchment and Stormwater Management Plan Report.
12
13
Mirfenderesk, H. Broadwater Study Site Investigation Report. Griffith Centre for Coastal
Management Research Report 26-04. 2006
14
15
16
17
WRM. Revision of Design Rainfall Temporal Patterns for Gold Coast Catchments.
November 2008.
18
19
AWE. Review of Gold Coast Rainfall Data. Final Report. May 1998.
20
21
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Draft Report.
22
Queensland Department of Main Roads. Road Drainage Design Manual. June 2002.
23
24
25
26
27
SKM. Aquifer Storage and Recovery Assessment. Hydraulic Assessment. June 2008.
28
SKM. Aquifer Storage and Recovery Assessment. Recovery Efficiency (RE) Modelling.
May 2008.
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
11.
Figure 67
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 68
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
12.
Figure 69
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 70
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 71
Urbanisation of Upper Woongoolba, aerial photos 2001 (left) and 2011 (right)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 72
Urbanisation of Upper Woongoolba, aerial photos 2001 (left) and 2011 (right)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 73
Changes around Marks Road, aerial photos 2001 (left) and 2011 (right)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
13.
Figure 74
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 75
City of Gold Coasts 2004 hydrological and hydrodynamic model extent (Ref 3)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 76
City of Gold Coasts 2004 hydrological and hydrodynamic model extent (Ref 4)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 77
Depth of inundation (peak) for one-in-10-year ARI flood with 72-hour storm duration (HAT)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 78
Depth of inundation (after four days) for one-in-10-year ARI flood with 72-hour storm duration (HAT)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 79
Option 1 (additional culverts at Behms Creek) compared with base case (four days)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 80
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 81
Option 3 (Behms Creek straightening) compared with base case (four days)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 82
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 83
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 84
Option 5 (widening of Behms Creek and Pimpama River) compared with base case (four days)
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 85
Version 5 November 14
woongoolba-hydraulic-study-201409-report.docx
14.
The following section shows the photographs of key structures taken as part of the 2010
surveys.
Photo 1
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 2
Structure 12
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 3
Structure 17 (road)
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 4
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 5
Photo 6
Structure 50
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 7
Structure 51
Photo 8
Structure 52
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 9
Photo 10 Structure 39
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 11 Structure 40
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 13 Structure 26
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 16 Structure 2
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 21 Structure 1
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 22 Structure 1
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 24 Structure 9
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 26 Structure 70
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 27 Structure 71
Photo 28 Structure 72
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 29 Structure 73
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 33 Structure 59
Photo 34 Structure 60
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 35 Structure 60
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Photo 36 Structure 22
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
15.
Figure 86
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Figure 87
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
Figure 88
Version 5 November
14
woongoolba-hydraulic-study-201409-report.docx
16.
Photo 40 Overtopping of Zipfs Road near Loves Road (Courtesy of Barry Brooking)
Photo 41 Photos taken during 15 December 2012 high tide (Courtesy of Barry Brooking)
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
17.
The post-January 2013 flood high tide is shown in the following photos
Photo 42 29 January 2013 photo of Pimpama River culvert (Courtesy of Blake Boulton)
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Photo 43 29 January 2013 Photo of Behms Creek Culvert (Courtesy of Blake Boulton)
Photo 44 29 January 2013 photo of Zipfs Road inundation (Courtesy of Blake Boulton)
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 89
Figure 90
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 91
Figure 92
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
18.
Figure 93
Version 5
November 14
Photo locations
woongoolba-hydraulic-study-201409-report.docx
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
19.
This section comprises photographs taken by Richard Skopps during the November 2004 floods.
Photo 57 Looking west from concrete bridge (note brewery in background) 10/11/04
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Photo 59 Looking south-west from bridge (note quarry on Ormeau Range) 10/11/04
Photo 60 Looking east from concrete bridge behind Richard Skopps farm 10/11/04
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Photo 61 Photo taken 24/11/04 showing the dead cane plants resulting from inundation (note
quarry)
Photo 62 Photo taken 24/11/04 showing cane plants on our farm with good drainage
Version 5
November 14
woongoolba-hydraulic-study-201409-report.docx
Figure 94
Version 5
November 14
Depth of inundation (peak) for one-in-2-year ARI flood with 72-hour storm duration (HAT)
woongoolba-hydraulic-study-201409-report.docx
Figure 95
Version 5
November 14
Depth of inundation (after four days) for one-in-2-year ARI flood with 72-hour storm duration (HAT)
woongoolba-hydraulic-study-201409-report.docx