Dear Mrs.

Edna Mapa,

In response to your text messages, wala man kmi naga pressure sa inyo, ang sa
amon lng nga nag stick lng kmi sa gin-agreehan ta sang last meeting nga e
prioritize namon ang Plan nyo para mka start na in any Monday of September which
is kung lantawon ta very rare and tight n aka schedule para sa preparation kag
mobilization thats why gnprioritize namon kamo bsan nalapakan namon ang iban
na schedule since nabanggit nyo na kung indi kamo mka start this September sa
January 2016 na ang next target nyo. Para matigayon ang deal napag agreehan
naton both parties ang tanan na gusto nyo which is in favor sa inyo; a. remove all
overhead expenses and contingencies; b. Technical supervision and Professional fee
(PF) of 5% of TCP turn down to 120k for duration of 6 month as per request by your
husband; c. Terms of payment changed to 10% Mobilization, 30% DP and 60%
progress billing as compared to your previous contractor. All of these changes are in
your favor plus a discount to close a deal with a Total Contract Price (TCP) of 5Million
which we agreed last text conversation that this transaction is deal thats why we
rush up the Perspective, Plans and Blueprints to be signed and sealed for the
application of building permit.
Lately, you send us again another terms of payment sa iban mo nga reference
which is very impossible for us to agree. Then, nag liwat ang tono ka isturya nga
wala nyo na gna dali-an ky ang cash on hand nyo is 2M lng which is enaf lng sa 40%
DP kag nka problema kamo about sa 60% na progress billing basi ma compromise
kmo sa amon and mabitin ang ubra since my contrata.
Ang sa amon lng mam na medyo na saying ang effort namon sa pag rush up sang
tanan nga gulpi lng mag hambal kmo nga wala nyo na ginadali-an ang ubra. Sa
amon mam gna take gd namon seriously ang kada transaction nga parehas kita indi
ma perwesyo. Thats why kung d kamo sure ma stick nlng kmi sa signed and sealed
plans for application of building permit. Then after na ma comply namon ang signed
and sealed plans kamo na bahala kng ano ang next move nyo. But syempre since
nasuguran na sang team ARMCAD ang tanan sayang ang effort and mas masayang
pagd kng indi ta pag dayunun.
Willing gd kmi nga maging contractor nyo but my systema and terms man kmi nga
gnasunod. Kung willing man kmo gyapon nga kmi ang ma ubra may mga thing nga
dapat ta man e consider. List below are mga advantage and disadantages:
1. Validity of quotation are 3 months only since prices of services, materials and
permits varies every 3 months.
2. Total down payment of 30% of TCP plus 10% mobilization which amounting to
2 Million is consumed/consumable or malab-ot more or less 60 days. Which
we believe nga sa 60 days mka pangita naman na kmo siguro sang
pambayad para sa nabilin nga 60% which is pwede nga manging progress
billing or will devided in 4 months since this project duration is 6months.

Breakdown:

TCP

- 5M

10% mobilization

- 500K

30% Down Payment

60% will be paid thru


or DIVIDED in 4months
750K per month.

Good for 2 months work


load

1.5M
PROGRESS BILLING
which will fall in

Being a Designer and Contractor of this project gusto namon ma meet ang gusto
sang amon client na fair sa both parties and we believe that this breakdown is

reasonable and we will be the bridge from your imagination to reality and make
your dreams come true