Professional Documents
Culture Documents
Tracking Number:
Customer Number:
Customer:
Customer Problem Description:
Part Number:
Step
Action
0
The Planning Stage
1
Establishing
the Team
2
Problem
Definition /
Statement &
Description
3
Developing
Interim
Containment
Action
5
Identifying
Permanent
Corrective
Actions (PCA)
6
Implementing
&
Va
lid
ati
ng
P
C
A
7
Preventing
Recurrence
8
Recognizing
Team Efforts
Team Goals:
Name
2A
4
Identifying &
Verifying Root
Cause
Open Date:
Due Date:
Part Name:
Team Objectives:
Skills
Responsibility
Page 1 of 9
2012
Correct Process?
Y
Y
Y
Y
Y
Y
Y
N
N
N
N
N
N
N
Correct Tool?
Y N
Y N
Y N
Y N
Are tools, fixtures, gages, &/or error proofing in place & being used?
Are tools functioning correctly (ie: not broken, bypassed, not worn, set correctly, etc.)?
Are machines functioning correctly (ie: PM done, fixtures/ locators maintained, etc.)?
Was the gage(s) mastered and properly functioning?
1 Correct Parts?
Y
Y
Y
N
N
N
Is the correct part for the application clearly identified & being used?
Is workplace org. effective (ie. part# marked, storage area/racks labeled)?
Is the part storage effective (ie. keep parts free of debris, damage, breakage)?
Parts in Spec?
Y
Y
Y
N
N
N
Problem Description
3
2C
4
Developing Interim Containment Actions
Page 2 of 9
2012
Therefore
Specific
Therefore
(special cause)
Why
Therefore
Why
Therefore
Therefore
Why
Therefore
Detection
Therefore
Why
Why
Therefore
Why
Root Cause
Therefore
Why
Therefore
Why
Root Cause
Therefore
Systemic
Therefore
(common cause)
Why
Therefore
Why
Therefore
Why
Therefore
Why
Root Cause
Action Plan
4C
Page 3 of 9
2012
6
7A
7B
Who Responsible
When
Document
Completion Date
Who Responsible
Planned
Actual
Was this problem solving exercise effective? Has it been verified with a follow-up?
Yes
No
Findings
General Manager
Quality Manager
Page 4 of 9
2012
Page 5 of 9
2012
1.
Containment / Corrective
Action
How Verified
Action
Who Responsible
Planned
Actual
Parts
produced
with no
lead-in
Material
needed
in
pipeline
Contain in house
and at customer
NCR in house
and Customer
notification
Wes
Shepherd
02Aug1
3
02aug
13
Arrange certified
shipments using
PIC group
PIC worksheets
Wes
Shepherd
02Aug1
3
02Aug
13
Understa
nd
problem
Conference calls
Notes, action
plan for
supplying parts
Wes
Shepherd
03Aug1
3,
05Aug1
3
03Aug
13,
05Aug
13
Investiga
te
CFT investigation
Action plan
Jim Traynor,
Danny Brooks
06Aug1
3
06Aug
13
Status
8-D is a quality management tool and is a vehicle for a cross-functional team to articulate thoughts and provides scientific determination to
details of problems and provides solutions. Organizations can benefit from the 8-D approach by applying it to all areas in the company. The 8-D
provides excellent guidelines allowing us to get to the root of a problem and ways to check that the solution actually works. Rather than healing
the symptom, the illness is cured, thus, the same problem is unlikely to recur.
Page 6 of 9
2012
Environment
Page 7 of 9
2012
Measurement
Material
Method
Machine
Man
Page 8 of 9
2012
Page 9 of 9
2012