Professional Documents
Culture Documents
Project
Plan
2013
ARTEFACT 1
S0222184 - Jonghardi,
Cardven
S0224244 - Nemkul, Bishnu
S0213317 - Teran Montero,
Christian
Table of Contents
Introduction........................................................................................................... 3
Objective............................................................................................................... 3
Constraint of the project:....................................................................................... 3
Project Organisations............................................................................................. 5
First Period:......................................................................................................... 5
Second Period:.................................................................................................... 6
Third Period:....................................................................................................... 6
Requirement:......................................................................................................... 8
Client Requirement:............................................................................................ 8
Server Requirement:........................................................................................... 8
WBS & Schedule.................................................................................................... 9
Risk Plan................................................................................................................ 9
Monitoring and reporting..................................................................................... 11
Project Plan
Introduction
We are employed as software engineers by XYZZY company to design and
implement a proof of the concept information kiosk for DVD store. So 12 weeks
were given for the demonstration. If the demonstration is successful, it will be
further taken to prototype development. The basic functionalities for both
customers and manager for both customers and managers are provided in
demonstration. So for this we formed the group of three as the company has
budgeted for three people and started our project.
Objective
The Application will need to be finished before 27 September 2013.
Most of the functionality for both customers and managers be provided
The scope must be working according the use.
: 3 person
Software available
:
NetBeans IDE will be used for this project as
a java technology is to be used to design the
system. Because it is easy to develop Java
desktop , mobile and web applications with
NetBeans IDE.
GlassFish is an open source development
project was build for Java EE5 application
server
2. Time Constraint:
12 hours per person for 12 weeks. Total work hours: 432 hours
3. Scope Constraint:
Design and Implement a proof of concept information kiosk for DVD
stores.
Web driven Application with 3 tier layer.
Basic functionality for the Customers and the Managers.
Project Organisations
The project will have a different project management to ensure the output quality
of the project.
The Project organisation has been categorise by the delivery time of the project.
First Period:
Week 1-4
Project Manager:
He will be the in charge of the project planning and dividing the work
load among the group. WBS, project organisation will be done by project
manager.
Application Analyst:
As for the current period both analyst are to work on a risk plan,
hardware and software requirement,
Second Period:
Week 5-8
Project Manager:
The project manager will be the in charge of weekly progress reports.
Web Designer:
He will be in charge of Document design for designing
Software Analyst:
He will be in charge of requirement specification
Third Period:
Week 9-12
Project Manager:
For this period project manager will be reporting the progress report and
in the final week he will be responsible for the project review
Software Engineer:
Work on the implementation of design to implementation
Developer:
Work on the required coding of the project
Requirement:
We are required to create GUI - driven the three tier system using the Java
technology more importantly suing the Java database to store the information.
The hardware and software requirement are as given below:
Client Requirement:
Server Requirement:
1. Hardware Requirement:
- Desktop or Tablet with more than
7 screen
- At least 500 MB RAM.
- At least 100 MB free HDD space
1. Hardware Requirement:
- At least 2 GB RAM
- At least 300 GB free HDD space
- 32 bit or 64 bit processor
- 500 GB bandwidth
2. Software Requirement:
- HTML5 compatible web browser.
2. Software Requirement:
- Glassfish
- Derby database
- Java SDK 7.0
Risk Plan
Risk is required to be considered in all kinds of scenario because danger is
inevitable all the time. Some of the risks are very unlikely to happen but still need
to be accounted for to make sure the countermeasure is ready on the side so
problem can be solved if it arises.
Risk
Date
Mitigation Strategy
Workload from
other courses
becomes
excessive in
weeks 7-12
One of the
member getting
hospitalised
Work load from
the work place
being excessive
01/07/13
1.0
Could
occur
anytime
Could
occur
anytime
0.5
1.0
Could
occur
anytime
1.0
10
10
Change of the
project during
implementation
period
08/07/1
3
0.3
10
0.1
10
Client cancelling
the project