You are on page 1of 2

NEW RETAIL OUTLET

WORK SCHEDULE - BAR CHART

S.
No.

Item Of Work

1 Initial Levels & Finalisation of FDL


2 Filling Murrum

week 1
3

week 2

week 3

3 Earth Pit ( HD ) Tank works

a) Marking, Excavation & Dressing

b) PCC & Bar bending works


c) Setting out for HD beam

e) Brick Masonry Wall

f) Lowering the Tank

g) Back filling & Consolidation

h) Tank kerb wall

a) Marking, Excavation & Dressing


b) PCC

c) RR Masonry

e) Brick Masonry Wall

f) Plastering

g) Painting compound wall


a) Marking, Exc., & Dressing
b) PCC & Bar bending

d) RCC Footing Concrete


e) RCC Canopy Column

f) Back Filling & Consolidation


a) Marking & Exc. ( Entry Side )
b) PCC

c) Laying Hume pipe

d) Back filling & Consolidation

a) Marking & Exc. ( Exit Side )


b) PCC

c) Laying Hume pipe

d) Back filling & Consolidation

7 Sales Building

a) Marking & Exc. & Dressing

b) PCC & Reinforcement works


c) Placing Reinforcement

d) RCC Footing Concrete


e) RCC Column upto Plinth bottom

2
2

2
3

k) RCC Column upto Lintel

l) BW upto FFL

m) Back filling basement

n) Sand filling & PCC for flooring


o) Brick work up to Lintel level

p) Lintel bar bending & shuttering

q) RCC for Lintel

r) RCC Column upto Roof beam


s) BW upto Roof beam

t) Bar bending & Shuttering for roof


u) RCC Roof Concrete
v) Curing Period
w) Deshuttering

x) Plastering Internal & External


y) Plumping, Sanitary

z) Electrical Consealed works


aa) Weathering course
ab) Flooring works

ac) Panel Board fixing & wiring

ad) Aluminium Joineries Erection


ae) Painting works

11 Product Pipe Line Works / trench


13 BM Inspection Chambers
14 Driveway WBM / WMM

week 14

#
3

j) RCC for Plinth Beam

12 Yard Light

week 13

#
1

i) Shuttering for PB

9 Construction of Pump Island

week 12

h) Placing of PB Reinforcement

10 MPD & STP Installation

week 11

g) Exc., & PCC for Plinth beam

8 Hume Pipe Laying

week 10

f) Back filling foundation

af) Fixing Elect. Fittings

week 9

c) Positioning of Reinforcement

6 Culvert ( Hume Pipe )

week 8

d) RCC Grade beam

5 Canopy Foundation

week 7

d) HD Beam Concrete

4 Retaining Wall & Fencing

DURATION : 90 DAYS
week 5
week 6

week 4

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94

#
5

3
8
6

NEW RETAIL OUTLET


WORK SCHEDULE - BAR CHART

S.
No.

Item Of Work

15 Kerb Wall, Buffer & Monolith Foundation

week 1
3

week 2

week 3

week 4

DURATION : 90 DAYS
week 5
week 6

week 7

week 8

16 Laying Cables

17 Approach Cutting & WBM / WMM


18 Pump Island Finishing

19 Panel Board Commissioning


20 Driveway CC Pavers

6
2

21 Kerb Beam for CC Pavers


22 Approach FINISHING

23 Painting Work for Buffer & Kerb


24 CANOPY FAB ERECTION
25 Erecting Signages

HINDRANCES

week 9

week 10

week 11

week 12

week 13

week 14

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94

TOTAL DURATION = 90 Days

4
3

You might also like