Professional Documents
Culture Documents
February 2013
RISK WATCH
Personal
injury
1 Longshoremen claims in the USA
Longshoremen
claims in the USA
Navigation
and seamanship
3 Damage to shore cranes at
Japanese ports
Risk
management
4 Hatch covers weathertight issues
5 Mooring snap-back zones and
hazard identification
Containers
and cargoes
8 Fire in palm kernel expellers (PKE)
Regulatory
update
7 MARPOL Annex VI
7 MARPOL pre-washes and discharging
of slops to shore-side
Miscellaneous
8 Publications
Personal injury
The Association has recently been notified of a number of cases where ships have made contact with
shore cranes when departing from Japanese ports.
As there are generally no harbour regulations
in Japan which provide that shore cranes
should not operate in berthing/unberthing
areas, there is usually a legal burden on the
ship to prove that the stevedores or terminal
had a duty to re-position the crane.
In the cases reported to the Association, the
Master had made a verbal request for the
crane to be repositioned by the stevedores.
However, the stevedores failed to carry out
the request before the ship un-berthed and
the ship was still held responsible for the
damage. The ship could not then pass this
liability to the stevedores, the terminal or the
operators, as there was no written record of
the request made by the Master to move the
cranes. The position is the same where the
ship has been requested by the port
authority to shift along the berth and as a
consequence, contact is made with shore
cranes or with other objects on the jetty.
The situation is aggravated by the fact that
terminal owners at Japanese ports expect
Owners to contract directly with the crane
manufacturer to repair damaged cranes and
it is not acceptable to the terminal for an
independent repair contractor to be appointed.
Often the manufacturer will insist that the
damaged part is completely replaced, even
in circumstances where minor repairs could
be carried out to rectify the damage. This can
important that the Master refuses to unberth the ship until the shore crane has
been moved. Alternatively the Master may
consider an alternative un-berthing
manoeuvre, perhaps with the use of
additional tugs.
Risk management
Best practice
Point of
failure
A simple mooring
system illustrating
the potential snapback zone area
Point of
restraint
Snap-back
zone
Point of
failure
A complex mooring
system illustrating
the potential snapback zone area
Point of
restraint
Pedestal
roller
Old man
Snap-back
zone
Recently, one of our Members ships suffered a hold fire while loading palm kernel expellers (PKE) in
Kuantan, Malaysia. The dangers associated with PKE are well known, but this recent fire investigation has
highlighted issues and concerns that should be noted.
There was intermittent rain throughout the
loading process and loading had to be
stopped many times. After one of these
stoppages, when the hold was reopened, it
was found to be full of smoke but no flames
could be seen. The hatches were closed
immediately in order to deprive the fire of
oxygen and, following an inspection by
the port safety officer, CO2 was released into
the hold.
The CO2 did not completely extinguish the
fire and smoke continued to build up. The
decision was made to excavate and
discharge cargo to try and find the seat of
burning and then to extinguish the fire with
water. This meant the ship had to be moved to
a different berth where a crane was available
for the discharge operations. Discharge and
intermittent fire-fighting continued over 3
days before the fire was put out and all the
burnt material removed. The low water
pressure ashore meant that shore based
water jets were unable to reach across the
ship to the seat of burning. Therefore the
ships own seawater lines were eventually
used to douse the fire.
With the fire eventually extinguished, all cargo
was discharged from the affected hold and
the hold walls were inspected. P&I surveyors
and experts were called on to investigate the
fire and they designed a procedure to ensure
that the re-loaded cargo was safe.
PKE production appears to have been very
high during this recent season, with storage
spaces full, and so manufacturers want to
export the cargo as quickly as possible.
Regulatory update
Miscellaneous
Publications
ISBN: 9789280115642
Price: GBP 10.00
ISBN: 9789280115666
Price: GBP 10.00
Editors message We are always looking for ways to maintain and increase the usefulness, relevance and general interest of the articles within
Risk Watch. Please forward any comments to: rwatched@triley.co.uk