Q.1 (a)
Q.1 (b)
Q.2 (a)
: ENGG ZC242
: MAINTENANCE & SAFETY
: Open Book
: 50%
: 3 Hours
: 06/04/2014 (AN)
No. of Pages
=2
No. of Questions = 5
Please follow all the Instructions to Candidates given on the cover page of the answer book.
Assumptions made if any, should be stated clearly at the beginning of your answer.
A XYZ company wants to provide training to its mechanics to upgrade their skill
level. Company has two choices, technical schools/colleges or contract training.
I.
Suggest a better choice to company and justify your choice.
Page 1 of
II.
One week breakdown details of a lathe machine which works on a single shift basis
from 8am to 4pm is given below. Ignore lunch time. Assume all breakdowns are
unplanned shutdowns and numbers of maintenance actions are equal to number of
failures?
[5]
Day
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Determine
(i)
Down time %
Q.3 (b)
Breakdown period
11am to 11:30am
8am to 8:30am
No breakdown
9am to 11am
8:15am to 8:30am
10am to 10:45am
2pm to 3pm
Q.4. A Company is running a CNC milling centre that produced components on a schedule of
two 8 hour shifts, 6 days per week. The company had planned downtime of 20 minutes for
lunch per shift plus four 10 minute break per shift while the total actual downtime losses
(Non-planned) averaged 600 minutes per week. The milling centre produced 11223
components during actual operating time. If design cycle time is 0.2 minutes per
component and total there were 200 rejected components during the week, then determine:
i.
Availability Rate
ii. Performance rate
iii.
Quality rate
iv. Overall Equipment Efficiency
[4 + 2 + 2 + 2 = 10]
Q.5. Consider the seven component system shown in the Figure - 1. Assume that time to failure
for each component has an exponential distribution. The failure rates are as follows: A =
0.0005/h, B = 0.0005/h, C = 0.0003/h, D = 0.0008/h, E = 0.0004/h, F = 0.006/h, G =
0.0064/h,
Page 2 of
i.
ii.
[10]
************
Page 3 of