Inspection Plan

Purpose
This manual describes how to create an inspection plan.
Scope
This manual describes the creation of inspection plan only. Creation of the basic data required
to create an inspection plan are explained separatly.
Overview
Inspection plan is a Task list for QM as Routing is for Production. An inspection plan has one or
more operation to which inspection characteristics are assigned. For all materials with
Inspection type 01,0101 and0102 you have to create inspection plan. For inspection type
06,08 etc you need not create plans. If you dont have a plan then, you can not record results
for the inspection lot. However you can record defects and take usage decision as usual.

Event
Whenever a new material is created or a new inspection type (eg.0101 and 0102 are added to
01) is added to an existing material, inspection plan has to be created. The person who
maintains the QM view of the material master will inform you to create a plan.
However you can still list down the materials for which you have create plans. You can list
down two types of Missing Inspection Plans: First one is for those materials for which PO has
been placed, but no plan is created and the second one is for all materials for which no plan is
there. Only those materials for which inspect with task list is mentioned in the material
master will be listed here.

Page 1 of 14

Create
Menu path
Transaction

Inspection Plan
Logistics-Quality management-Quality Planning-Inspection Planning-Task listInspection Plan-Create
QP01

Initial Screen

Field Description
Material Number
Plant
Group

Remarks
Enter the Material number for which you want to create an Inspection Plan
Enter your plant.
Do not make any entry. System will assign a number while you save.

Page 2 of 14

Header Details

Operation Overview

Page 3 of 14

Field Description
Work Center
Control Key
Std text
Description

Remarks
Enter the incoming Work center
Enter QI01
Press F4 and choose the required Standard text.
If you have selected a standard text, that description will appear here. If you
havent, enter a description which describes the operation

Page 4 of 14

Operation Details
From this screen, Goto Insp. Char Overview

Page 5 of 14

Page 6 of 14

Inspection Characteristic Overview

Page 7 of 14

In this screen you have to enter the inspection Characteristic for the operation. After choosing a characteristic, in the
next Pop up screen, you can choose any one of the Inspection Method what you have assigned to this characteristic
(while creating the Master inspection Characteristic itself) by pressing F4.
Press Enter.

Page 8 of 14

Assigning the Sampling Procedure:


Note:
You will get this screen only if in the control indicator of the inspection characteristic you have activated the indicator
Sampling Procedure.
Also if you had chosen dynamic modification level as At characteristic level, then this screen would look like as
shown below:

Page 9 of 14

Dynamic Modification Screen (when the modification is at characteristic level)


Press ENTER.

Page 10 of 14

Now you are back to the Characteristic overview screen. In the same way, you can proceed to add more inspection
characteristic.When you have completed all, you can press save to complete the inspection plan.
But before that let us see few possible displays for information purpose.
General Data
You get this screen when you press General Data from the Inspection Characteristic Overview screen.
Press Quantitative Data if its a quantitative characteristic or Catalogs if its a qualitative characteristic.

Page 11 of 14

Quantitative Data
Press Catalog

Catalogs
Like this you can display various objects like characteristic deails, Sampling procedure, etc through the menu
Environment and Details.
Now you can check whether the inspection plan being created by you ids complete through the menu Extras-plan
Consistency Check-Consistency Check.
Error messages are more serious compared to Warning Messages.

Page 12 of 14

Consistency Check
You have to read the details of the messages, correct the errors, once again do the consistency check and proceed.
When the number of messages becomes 0,your inspection plan is complete.
Now press Back.
Press Save.
Now the system displays the group number of the plan, which you have created.

Page 13 of 14

Page 14 of 14