REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF AGRICULTURE-RFU XII


KORONADAL CITY
STATEMENT OF WORK ACCOMPLISHED (Monitoring purpose only)
As of May 07, 2015
Project Title
:
CONCRETING OF MONTAY-SINAPANGAN FMR
Project Location
: Brgy. Montay, Libungan, North Cotabato
Project Contract Cost
:
4,887,836.52
Date Started
:
December 5, 2014
Target Date of Completion : May 5, 2015
% Accomp. To Date
:
81.39%
Status Of Project
:
substantially completed and subjected for correction and rectification
Contractor
: LLABAN CONSTRUCTION

Item No.

Description

103
104
105
200
311
500
506
Note:

Unit

Structure Excavation
Embankment
Subgrade Preparation
Aggregate base Course
PCCP
RCCP (0.91 m dia)
Stone Masonry
GRAND TOTAL PROJECT COST

cu.m
cu.m
sq.m
cu.m
sqm
ln.m
cu.m

Qty.
15.00
361.00
4,160.00
832.00
2,600.00
18.00
10.00

Unit Cost
10,261.97
550.99
329.55
468.82
1,025.24

4,724.63
2,334.60

Amount (P)

PHYSICAL ACCOMPLISHMENT, %
PHYSICAL ACCO
%
Relative
Previous Present
To Date Previous
Weight

3.15%
153,929.55
4.07%
198,907.39
1,370,928.00 28.05%
7.98%
390,058.24
2,665,624.00 54.54%
1.74%
85,043.34
0.48%
23,346.00
4,887,836.52 100.00%

15.00
361.00
4,160.00
598.00
1,820.00
18.00
10.00

15.00
361.00
4,160.00
598.00
1,850.00
18.00
10.00

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

pls. See attached separate monitoring report

Prepared by:

Checked by:

Noted by:

Reccomending Approval:

Approved by:

ENGR. NOLITO R. GARCIA JR.

ENGR. CLAIRE J. RUDAS

ENGR. ERWIN A. ARGUELLES

ZALDY M. BOLORON, MPA

AMALIA JAYAG-DATUKAN, M

Chief, RAED

RTD for Operations

Regional Executive Director

RAED Staf

Engr.1/ FMR Focal Person

YSICAL ACCOMPLISHMENT, %
% Relative
Present
To Date
Weight
100.00% 100.00%
3.15%
100.00% 100.00%
4.07%
100.00% 100.00%
28.05%
71.88%
71.88%
5.74%
70.00%
70.00%
38.18%
100.00% 100.00%
1.74%
100.00% 100.00%
0.48%
81.39%

by:

G-DATUKAN, MBA

utive Director