Professional Documents
Culture Documents
8
14
5
1
hari
hari
hari
hari
ZONE-1
ZONE-2
ZONE-3
ZONE-4
Bongkar
Bongkar
Bongkar
Bongkar
Pasang
Cor
Pasang
Cor
Pasang
Cor
Pasang
Cor
41
46
51
56
19
27 24
32 29
37 34
42
10
F
32
18 15
G
37
23 20
H
42
28 25
A
47
33
1
A
23
9 6
B
28
14 11
C
33
19 16
D
38
24
0.00
4.8
25.42
9.21
0.00
4.8
25.42
9.21
Pekerjaan persiapan
Pekerjaan Sub structure (Perhitungan pekerjaan awal Blok B)
Upper structure (B-A-C-Dakhir zone-1)
Penutup atap (Perhitungan pekerjaan akhir Blok D zone-1)
0.00
4.8
7
14
0
14
35
0.00
4.8
hari
hari
hari
hari
hari
8
14
5
1
hari
hari
hari
hari
ZONE-1
ZONE-2
ZONE-3
ZONE-4
Bongkar
Bongkar
Bongkar
Bongkar
Pasang
Cor
Pasang
Cor
Pasang
Cor
Pasang
Cor
41
46
51
56
19
27 24
32 29
37 34
42
K
L
M
N
10
F
32
18 15
G
37
23 20
H
42
28 25
I
47
33
1
A
23
9 6
B
28
14 11
C
33
19 16
D
38
24
0.00
4.8
25.42
9.21
0.00
4.8
25.42
9.21
Pekerjaan persiapan
Pekerjaan Sub structure (Perhitungan pekerjaan awal Blok B)
Upper structure (B-A-C-Dakhir zone-1)
Penutup atap (Perhitungan pekerjaan akhir Blok D zone-1)
0.00
4.8
7
14
0
14
35
0.00
4.8
hari
hari
hari
hari
hari
Perhitungan Resiko
Bahan
Volume
Beton
4,641.25
Besi
770,070.40
Bekisting
31,164.55
Tambah Kuat Desak Beton
Lain-lain (bodeman + GT24 tepi)
Mobile crane substitusi TC
Upah
Satuan
M3
Kg
M2
Harsat
Total
Resiko
256,500
1,190,480,625.00
7.50%
2,550
1,963,679,508.07
2.27%
29,000.00
903,771,842.45
3.50%
Subkon
Post Tension
Biaya Umum
Total DC
33.00
4.17%
89,286,046.88
44,629,079.73
31,632,014.49
38,219,900.00
10,634,444.96
10,000,000.00
1.38
45.00
315,699,250.0
9.52%
0.00%
4.29
0.00
344,356.00
-315,354,894.00
44.00
44.000%
JENIS PEKERJAAN
Pile cap
Tie beam
Plat lantai dasar
Dinding (RW)
Kolom
Balok
Plat
Tangga
Listplank, parapet, kantilever
Balok dan plat ramp
Beton K300
Bahan
264,203.50
264,194.72
264,195.00
264,204.73
264,198.32
264,194.66
264,194.66
264,205.87
264,205.87
264,194.66
Upah cor
6,837.74
6,837.78
5,157.14
10,535.88
12,052.88
6,214.28
6,214.28
12,052.74
12,052.74
6,214.28
Besi
Alat Bantu
199.94
199.96
200.00
200.05
200.02
200.00
200.00
199.95
199.95
200.00
Bahan
2,711.75
2,711.75
2,711.75
2,711.75
2,711.75
2,711.75
2,711.75
2,711.75
2,711.75
2,711.75
Upah
Alat bantu
183.28
5.00
183.28
5.00
183.28
5.00
183.28
5.00
183.28
5.00
183.28
5.00
183.28
5.00
183.28
5.00
183.28
5.00
183.28
5.00
Bekisting
Bahan
23,014
23,014
23,014
8,522
3,560
20,860
7,810
16,773
16,773
7,810
Upah
6,610
6,610
6,610
10,010
13,850
7,886
7,900
9,500
9,500
7,900
Alat
100
100
100
7,365
8,698
8,156
13,745
1,000
1,000
13,745
Total
29,724
29,724
29,724
25,898
26,108
36,902
29,454
27,273
27,273
29,454
No
=
=
=
Item
Qty
Unit
Koef
BAHAN
Beton K300
1 m3
1.03
UPAH
Mandor
Tukang
Pekerja
1 mh
1 mh
6 mh
0.50
1.00
1.00
ALAT
Alat bantu
1 ls
0.10
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
3.5
3.5
3.5
0.143
0.286
1.714
Total
Kuantitas
149.19
5,000
4,286
2,857
Material
Grand
Total
Rp.
38,267,235
264,204
103,550
177,514
709,314
715
1,226
4,897
28,960
28,960
200
103,550
177,514
709,314
14.5
Total
Alat
Others
38,267,235
20.7
41.4
248.3
2000
Total Biaya
Upah
38,267,235
990,378
28,960
39,286,573
264,204
6,838
200
271,241
271,241
No
Item
=
=
=
Qty
Unit
Koef
BAHAN
Beton K300
1 m3
1.03
UPAH
Mandor
Tukang
Pekerja
1 mh
1 mh
6 mh
0.50
1.00
1.00
ALAT
Alat bantu
1 ls
0.10
Total
TOTAL UNIT RATE
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
3.5
3.5
3.5
0.143
0.286
1.714
Total
Kuantitas
186.78
5,000
4,286
2,857
Material
Alat
Others
47,909,070
25.9
51.9
310.8
2000
Total Biaya
Upah
47,909,070
264,195
129,650
222,257
888,056
715
1,226
4,897
36,260
36,260
200
129,650
222,257
888,056
18.1
Grand
Total
Rp.
47,909,070
1,239,963
36,260
49,185,293
264,195
6,838
200
271,232
271,232
No
=
=
=
Item
Lantai Dasar
1.00
m3
Qty
BAHAN
Beton K300
UPAH
Mandor
Tukang
Pekerja
Unit
Koef
1 m3
1.03
1 mh
4 mh
14 mh
1.00
1.00
1.00
1 ls
0.10
ALAT
Alat bantu
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
12
12
12
0.083
0.333
1.167
Total
Kuantitas
1.03
5,000
4,286
2,857
Material
Alat
Others
264,195
0.1
0.3
1.2
2000
Total Biaya
Upah
264,195
264,195
400
1,414
3,343
400
1,414
3,343
200
200
200
400
1,414
3,343
0.1
Grand
Total
Rp.
Total
264,195
5,157
200
269,552
264,195
5,157
200
269,552
No
Item
BAHAN
Beton K300
UPAH
Mandor
Tukang
Pekerja
ALAT
Alat bantu
Total
TOTAL UNIT RATE
=
=
=
Dinding (RW)
129.17
m3
Qty
Unit
Koef
1 m3
1.03
1 mh
2 mh
10 mh
1.00
1.00
1.00
1 ls
0.10
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
4
4
4
0.250
0.500
2.500
Total
Kuantitas
133.05
5,000
4,286
2,857
Material
Alat
Others
34,127,325
32.3
64.6
322.9
2000
Total Biaya
Upah
Grand
Total
Rp.
34,127,325
161,450
276,814
922,656.22
12.9
161,450
276,814
922,656
25,840
25,840
34,127,325
1,360,920
25,840
35,514,085
264,205
10,536
200
245,195
269,552
No
=
=
=
Item
Qty
BAHAN
Beton K300
UPAH
Mandor
Tukang
Pekerja
Unit
Koef
1 m3
1.03
1 mh
4 mh
10 mh
0.20
1.00
1.00
1 ls
0.10
ALAT
Alat bantu
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
3
3
3
0.067
1.333
3.333
Total
Kuantitas
1.03
5,000
4,286
2,857
Material
Alat
Others
264,195
0.1
1.3
3.3
2000
Total Biaya
Upah
Grand
Total
Rp.
264,195
350
5,700
9,514
0.1
350
5,700
9,514
200
200
Total
264,195
15,564
200
279,959
264,195
15,564
200
279,959
No
Item
BAHAN
Beton K300
UPAH
Mandor
Tukang
Pekerja
ALAT
Alat bantu
Total
TOTAL UNIT RATE
=
=
=
=
Qty
Unit
Koef
1 m3
1.03
1 mh
4 mh
14 mh
1.00
1.00
1.00
1 ls
0.10
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
10
10
10
0.100
0.400
1.400
5,000
4,286
2,857
Total
Kuantitas
Material
3,547.13
909,838,845
344.4
1,377.5
4,821.4
2000
Total Biaya
Upah
Alat
Others
909,838,845
264,195
1,721,900
5,903,694
13,775,272
500
1,714
4,000
688,760
688,760
200
1,721,900
5,903,694
13,775,272
344.4
Grand
Total
Rp.
909,838,845
21,400,866
688,760
931,928,471
264,195
6,214
200
270,609
270,609
No
=
=
=
=
Item
Kolom
Beton
378.17
m3
Qty
Unit
Koef
BAHAN
Beton K300
1 m3
1.03
UPAH
Mandor
Tukang
Pekerja
1 mh
1 mh
3 mh
0.20
1.00
1.00
ALAT
Alat bantu
1 ls
0.10
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
1.15
1.15
1.15
0.174
0.870
2.609
Total
Kuantitas
389.52
5,000
4,286
2,857
Material
Grand
Total
Rp.
99,911,880
264,198
329,000
1,410,041
2,818,997
870
3,729
7,454
75,640
75,640
200
329,000
1,410,041
2,818,997
37.8
Total
Alat
Others
99,911,880
65.8
329.0
986.7
2000
Total Biaya
Upah
99,911,880
4,558,039
75,640
104,545,559
264,198
12,053
200
276,451
276,451
No
Item
=
=
=
=
Tangga, Ramp
Beton
80.22
m3
Qty
Unit
Koef
BAHAN
Beton K300
1 m3
1.03
UPAH
Mandor
Tukang
Pekerja
1 mh
1 mh
3 mh
0.20
1.00
1.00
ALAT
Alat bantu
1 ls
0.10
Total
TOTAL UNIT RATE
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
1.15
1.15
1.15
0.174
0.870
2.609
Total
Kuantitas
82.63
5,000
4,286
2,857
Material
Alat
Others
21,194,595
14.0
69.8
209.3
2000
Total Biaya
Upah
21,194,595
264,206
69,800
299,100
597,971
870
3,728
7,454
16,040
16,040
200
69,800
299,100
597,971
8.0
Grand
Total
Rp.
21,194,595
966,871
16,040
22,177,506
264,206
12,053
200
276,459
276,459
No
Item
=
=
=
=
Shearwall
Beton
1.00
m3
Qty
Unit
Koef
BAHAN
Beton K300
1 m3
1.03
UPAH
Mandor
Tukang
Pekerja
1 mh
1 mh
3 mh
0.20
1.00
1.00
ALAT
Alat bantu
1 ls
0.10
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
256,500
0.42857143
0.42857143
0.42857143
0.467
2.333
7.000
Total
Kuantitas
1.03
5,000
4,286
2,857
Material
Alat
Others
264,195
0.5
2.3
7.0
2000
Total Biaya
Upah
264,195
264,195
2,350
9,986
20,000
2,350
9,986
20,000
200
200
200
2,350
9,986
20,000
0.1
Grand
Total
Rp.
Total
264,195
32,336
200
296,731
264,195
32,336
200
296,731
296,731
HargaDasar
HARGA BAHAN
No Item
Satuan
Harga Satuan
m3
271,000
2 Beton (K300)
m3
256,500
240,000
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
Beton K225
Beton K125
Besi BJTP dia 8
Besi BJTP dia 10
Besi BJTP dia 12
Besi BJTD dia 13
Besi BJTD dia 16
Besi BJTD dia 19
Besi BJTD dia 8 -16
Besi BJTD dia 25
Besi BJTD dia 32
Kawat beton
Paku 4", 3",2"
Plywood 9 mm WBP
Plywood 12 mm
Plywood 15 mm
Plywood 18 mm
Plywood 21 mm
Phenol Film 12 mm
Phenol Film 15 mm
Phenol Film 18 mm
Phenol Film 21 mm
Plywood 12 mm
Phenol Film 12 mm
Plywood 18 mm
Phenol Film 15 mm
Kayu 5/7
Kayu 5/10
Kayu 6/12
Kayu 8/15
Semen
Pasir pasang
Pasir urug/ pasir sedot
Sirtu
AM 50
Lantai keramik roman 30 x30
Lantai keramik roman 20 x20
Plint keramik 10/30
Cat enamel
Stair nossing 10/20
Batu bata
Olie bekas
Pipa sparing
Hambaro bambu
Besi siku 70.70.7
Batu kali
Tanah urug
m3
m3
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
m3
m3
m3
m3
Kg
m3
m3
m3
Kg
m2
m2
m'
Kg
m'
Bh
Ltr
Btng
M'
Kg
m3
m3
215,200
2,700
2,600
2,575
2,575
2,550
2,575
2,600
2,575
2,575
3,100
3,200
65,000
85,000
95,000
125,000
120,000
100,000
115,000
120,000
125,000
35,000
40,000
45,000
50,000
725,000
750,000
750,000
775,000
450
85,000
45,000
60,000
1,200
27,000
27,500
13,500
75,000
14,000
250
700
6,000
30,000
3,000
80,000
20,000
Page 10
GALIAN
Nomor Item
Kuantitas
Unit rate
No
=
=
=
Item
1,224.30
m3
Qty
BAHAN
UPAH
Galian tanah,
Tukang gali
Menaikkan ke bucket
Tukang gali
II.3
ALAT
Tower crane
Alat bantu
Unit
Unit Equip
Kapasitas
Jam
Koef
Material
Unit rate
Upah
Total
Kuantitas
Alat
Total Biaya
Upah
Material
Grand
Total
Rp.
Alat
mh
1.00
0.4
2.500
4,286
3,060.8
13,117,487
13,117,487
10,714
mh
0.10
0.4
4,286
ls
ls
14.4
0.10
61,215
61,215
50
500
122.4
Total
13,117,487
61,215
13,178,702
10,714
50
10,764
10,764
AsumsUntuk bangunan utama, galian manual, untuk R. M/E & Ramp dengan excavator
Galian secara manual, buangan dengan tower crane
Vol dikerjakan sehari
2.8 m3
Waktu kerja
7 jam
Kaps galian
0.4 m3/jam
Tower crane
Kaps. Bucket
Waktu hauling TC
Kaps TC
1.2 m3
5 menit
14.40 m3/ jam
Vol. Galian
Vol. Urugan kembali
% tanah diangkat
1,224 m3
#REF! m3
#REF!
No
=
=
=
Item
II.4
1.00
m3
Qty
Unit
Unit Equip
Kapasitas
Jam
Koef
BAHAN
UPAH
Mengurug tanah kembali
Tukang gali
mh
1.00
ALAT
Alat bantu
ls
0.10
1.000
Material
Unit rate
Upah
Total
Kuantitas
Alat
4,286
Total Biaya
Upah
Material
1.0
500
Grand
Total
Rp.
Alat
4,286
0.1
4,286
4,286
50
50
50
Total
4,286
50
4,336
4,286
50
4,336
Page 11
4,336
AsumsUntuk bangunan utama, urugan secara manual, untuk R. M/E & Ramp dengan excavator
Vol dikerjakan sehari
8 m3
Waktu kerja
8 jam
Kaps galian
1 m3/jam
Page 12
Urug pasir
Nomor Item
Kuantitas
Unit rate
No
=
=
=
Item
II.5
222.37
m3
Qty
Unit
Unit Equip
Kapasitas
Jam
Koef
Material
BAHAN
Pasir sedot
m3
1.20
UPAH
Mengurug pasir
Tukang gali
mh
1.00
1.000
ALAT
Tower crane
Alat bantu
ls
ls
0.40
0.10
14.40
Unit rate
Upah
Total
Kuantitas
Alat
45,000
266.84
4,286
500
AsumsTransfer disamping galian digunakan alat bantu talang seng, diratakan secara manual
Transfer material di daerah tak terjangkau talang digunakan Tower Crane,
Vol meratakan sehari
8 m3
Waktu kerja
8 jam
Kaps galian
1 m3/jam
Kaps. Bucket
Waktu hauling TC
Kaps TC
Vol yang dilayani TC
1.2 m3
5 menit
14.40 m3/ jam
40%
Page 13
Total Biaya
Upah
Grand
Total
Rp.
Alat
12,007,800
222.4
Total
Tower crane
Material
12,007,800
53,999
953,013
4,286
11,120
11,120
50
953,013
22.2
12,007,800
953,013
11,120
12,971,933
53,999
4,286
50
58,335
58,335
#
Nomor Item
Kuantitas
Unit rate
No
=
=
=
Item
II.9
#REF!
Ls
Qty
1 Pemadatan Jalan
2 Urugan Sirtu
3 Beton K225
Unit
105
15.75
6.3
Unit Equip
Kapasitas
Jam
Koef
1.00
1.00
1.00
Unit rate
Upah
72,000
475,555
29
91
38,750
Alat
480
671
Total
Kuantitas
#REF!
#REF!
#REF!
Total Biaya
Upah
Material
Grand
Total
Rp.
Alat
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Total
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
m2
m3
m3
Material
#REF!
#REF!
#REF!
#REF!
30 m'
3.5 m'
0.15
0.06
75
0.21
Vol.
Vol.
kg/ m3 ---->
Vol.
105
15.75
15.75
6.3
472.5
22.05
m2
m3
m3
m3
Kg
m3
Pemadatan tanah
Nomor Item
Kuantitas
Unit rate
No
A
B
C
=
=
=
Item
BAHAN
UPAH
Pekerja
ALAT
Mini Vibroll
II.9
105.00
m2
Qty
Unit
Unit Equip
Kapasitas
Jam
Koef
mh
1.00
200.00
0.010
jam
1.00
200.00
0.005
Material
Unit rate
Upah
Alat
2,857
Total
Kuantitas
Total Biaya
Upah
Material
1.1
95,000.00
Grand
Total
Rp.
Alat
3,000
0.5
3,000
29
50,350
50,350
480
Total
3,000
50,350
53,350
29
480
508
Page 14
508
Urugan Sirtu
Nomor Item
Kuantitas
Unit rate
No
A
B
C
=
=
=
Item
II.9
15.75
m3
Qty
BAHAN
Sirtu
UPAH
Pekerja
ALAT
Bulldozer
Mini Vibroll
Unit
Unit Equip
Kapasitas
Jam
Koef
m3
1.20
mh
1.00
1
1
jam
jam
1.00
1.00
Material
Unit rate
Upah
Alat
60,000
0.032
150.00
40.00
Total
Kuantitas
18.90
2,857
0.007
0.025
Material
1,134,000
1,429
72,000
1,429
0.1
0.4
Total
Grand
Total
Rp.
Alat
1,134,000
0.5
0.00
0.00
Total Biaya
Upah
1,134,000
1,429
1,135,429
72,000
91
72,091
72,000
No
=
=
=
Item
BAHAN
Beton K225
Bekisting
Besi
Bendrat
UPAH
Upah ngecor
Upah bekisting
Upah pembesian
ALAT
Concrete vibrator
Alat bantu cutting
II.9
6.30
m3
Qty
Unit
Unit Equip
Kapasitas
Jam
Koef
1
0.5
75
1.5
m3
m2
Kg
Kg
1.05
1.00
1.03
1.03
1
0.5
75
m3
m2
kg
1.00
1.00
1.00
1
75
jam
ls
1.00
1.00
Material
Unit rate
Upah
Alat
240,000
20,000
2,700
3,100
6.62
3.15
486.68
9.73
25,000
5,000
150
24.00
0.042
Total
Kuantitas
Material
Total
TOTAL UNIT RATE
Page 15
Grand
Total
Rp.
Alat
1,588,800
63,000
1,314,036
30,163
6.3
3.2
472.5
9,000.00
4.00
Total Biaya
Upah
1,588,800
63,000
1,314,036
30,163
252,190
10,000
208,577
4,788
157,500
15,750
70,875
25,000
2,500
11,250
2,340
1,890
2,340
1,890
371
300
157,500
15,750
70,875
0.3
472.5
2,995,999
244,125
4,230
3,244,354
475,555
38,750
671
514,977
514,977
LANTAI KERJA
Nomor Item
Kuantitas
Unit rate
No
=
=
=
Item
BAHAN
Beton Bo
III.1
2,223.80
m2
Qty
Unit
Unit Equip
Kapasitas
Jam
Koef
0.05
m3
1.00
UPAH
Mandor
Tukang
Pekerja
1
1
2
mh
mh
mh
0.10
1.00
1.00
ALAT
Alat bantu
ls
0.10
Material
Unit rate
Upah
Total
Kuantitas
Alat
215,200
10
10
10
0.010
0.100
0.200
111.19
5,000
4,286
2,857
Material
Total
TOTAL UNIT RATE
TOTAL UNIT RATE PER M3
Page 16
Alat
23,928,088
22.2
222.4
444.8
500
Total Biaya
Upah
23,928,088
10,760
111,200
953,056
1,270,742
50
429
571
111,190
111,190
50
111,200
953,056
1,270,742
222.4
Grand
Total
Rp.
23,928,088
2,334,998
111,190
26,374,276
10,760
215,200
1,050
21,000
50
1,000
11,860
237,200
11,860
No
=
=
=
=
Item
BAHAN
Besi Beton
Kawat beton
UPAH
Menurunkan
Mandor
Tukang
Pekerja
Stapel 25 m
Mandor
Tukang
Pekerja
Pabrikasi
Mandor
Tukang
Pekerja
Angkut
Mandor
Tukang
Pekerja
Stel
Mandor
Tukang
Pekerja
ALAT
Alat bantu
Total
TOTAL UNIT RATE
BETON BERTULANG
Pembesian Poer
16,890
kg
Qty
Unit
1 kg
0.015 kg
Koef
Unit Equip
Kapasitas Jam
1.025
1.01
Material
Unit rate
Upah
Alat
2,600
3,100
Total
Kuantitas
17,312.60
255.89
Material
Total Biaya
Upah
Grand
Total
Rp.
Alat
Others
45,009,187
793,259
45,009,187
793,259
2,665
47
0 mh
0 mh
4 mh
0.10 1666.667
1.00 1666.667
1.00 1666.667
0.002
5,000
4,286
2,857
33.8
96,514
96,514
0 mh
0 mh
3 mh
0.10
1.00
1.00
948
948
948
0.003
5,000
4,286
2,857
50.7
144,771
144,771
1 mh
2 mh
4 mh
1.00
1.00
1.00
1000
1000
1000
0.001
0.002
0.004
5,000
4,286
2,857
16.9
33.8
67.6
84,450
144,771
193,028
84,450
144,771
193,028
5
9
11
0 mh
0 mh
2 mh
0.10
1.00
1.00
400
400
400
0.005
5,000
4,286
2,857
84.5
241,285
241,285
14
1 mh
3 mh
1 mh
0.10
1.00
1.00
125
125
125
0.001
0.024
0.008
5,000
4,286
2,857
13.5
405.4
135.1
67,550
1,737,298
386,057
67,550
1,737,298
386,057
4
103
23
1 ls
0.00
84,460
84,460
2000
42.2
45,802,446
3,095,726
84,460
48,982,632
2,712
183
2,900
2,900
Bekisting Kolom
Sub Pekerjaan =
Sistem Bekistin =
Unit rate
=
No
Item
BAHAN
Plywood 15 mm
- tinggi kolom 4-0,6=3.4
diambil
3.66
Pak(untuk 1 modul)
PakPanel & klem
Penop. Postshore
Penop. Postshore
Lot
Panel
Peri Sistem
1 modul
Type
Unit
Perhit.
100x100
90 x90
80 x80
70 x70
60 x60
50 x50
dia 50
m2
m2
m2
m2
m2
m2
m2
4*1*3.66
4*0.9*3.66
4*0.8*3.66
4*0.7*3.66
4*0.6*3.66
4*0.5*3.66
3.66*2*3.14*0.25
4"
4"
3"
3"
2"
Bh
Bh
Bh
Bh
Bh
(20*4)+(30*4)
(8*4)+(30*4)
(20*4)+(30*4)
(8*4)+(30*4)
(20*4)+(30*4)
Oli bekas
Pipa Sparing
B
UPAH
Pabrikasi
Angkut girder+plywood
Ukur+potong kaso+set
Merangkai panel
Angkut + stok
Melumasi oli
Menyetel
Loading panel ke TC
Unload panel dari TC
Loading main elemen
Unload main elemen
Setel on site
Ps. klem & tie rod
Ps. Shoring
Lot
Bongkar bekisting
Bongkar p. Shore
Bkr. Klem + tie rod
Bongkar panel
Dikumpulkan u/ pindah
ALAT
Main girder GT 24
Main element
Accesoriess
Consumable
Total
TOTAL UNIT RATE
Perhitungan
Ltr
Btng
(1*3.66*4)/8
+(1m*5*3)/4
kenek
menit
tukang
tukang
kenek
kenek
menit
menit
menit
menit
kenek
kenek
kenek
kenek
tukang
tukang
tukang
tukang
kenek
kenek
kenek
kenek
1
1
1
1
Volume
14.64
13.18
11.71
10.25
8.78
7.32
5.75
200.00
152.00
200.00
152.00
200.00
1.83
3.75
Total Volume
Satuan
0.00
0.00
0.00
0.00
2.95
2.46
1.93
lembar
lembar
lembar
lembar
lembar
lembar
lembar
6.66
4.40
Kg
Kg
1.76
Kg
0.50
Kg
1.83
3.75
Ltr
Btng
63.00
272.00
480.00
40.00
40.00
menit
menit
menit
menit
menit
menit
menit
menit
30.00
30.00
40.00
20.00
240.00
360.00
120.00
40.00
menit
menit
menit
menit
160.00
240.00
120.00
30.00
ls
ls
ls
ls
Bekisting Kolom
Sub Pekerjaan
Sistem Bekisting
Unit rate
=
=
=
No
Item
Peri Sistem
1 modul
Type
Unit
Perhit.
Paku
Rangka Panel
Penop. Postshore
Penop. Postshore
Panel
5/10
5/10
5/10
5/7
m'
m'
m'
m'
(0.5*4*4*2)
(2.4*2*2)
(2*3)
(0.3*2.4/0.2)
4"
4"
3"
2"
Bh
Bh
Bh
Bh
(16*2*4)*2
(6*2*3)*2*2
(6*2*3)*2*2
(19*5+2*4*4)*2
Ltr
Btng
(2.4*3.6*2)/8
+(0.4m*3*3)/4
kenek
tukang
tukang
kenek
kenek
menit
menit
menit
menit
menit
96.00
132.00
200.00
80.00
30.00
kenek
kenek
kenek
kenek
tukang
tukang
tukang
tukang
menit
menit
menit
menit
menit
menit
menit
menit
60.00
60.00
48.00
48.00
480.00
270.00
90.00
10.00
kenek
kenek
kenek
kenek
menit
menit
menit
menit
240.00
240.00
120.00
60.00
Oli bekas
Pipa Sparing
Volume
Total Volume
Satuan
BAHAN
Kayu
Rangka Panel
Penop. Postshore datar
Penop. Postshore tegak
Pengaku
Perhitungan
UPAH
Pabrikasi
Angkut girder+plywood
Ukur+potong kaso+set
Merangkai panel
Angkut + stok
Melumasi oli
Menyetel
Loading panel ke TC
Unload panel dari TC
Loading main elemen
Unload main elemen
Setel on site
Ps. klem & tie rod
Ps. Shoring
Lot
Bongkar bekisting
Bongkar p. Shore
Bkr. Klem + tie rod
Bongkar panel
Dikumpulkan u/ pindah
ALAT
Main girder GT 24
Main element
Accesoriess
Consumable
Total
TOTAL UNIT RATE
1
1
1
1
ls
ls
ls
ls
0.159
0.080
0.048
0.030
0.001
m3
16.00
9.60
6.00
0.14
256.00
144.00
144.00
254.00
6.36
3.20
1.80
0.72
0.64
Kg
Kg
2.16
0.90
2.16
0.90
Ltr
Btng
Kg
Kg
Per m2
corewall
SHEAR WALL 1
Item
Qty
Sat
Koef
Durasi
Sewa/Bhn
TOTAL
BAHAN
Phenol Film 18 mm
Paku
28.75571 lembar
10
kg
1.1
1.1
120,000
3,200
3,795,754
35,200
711.55
85.6
3,830,954
ALAT
Peri vario for shear wall h.3.95 m
Main girder GT 24
Main element
Accesoriess
Consumable
Peri Climbing Platform for shear wall
Climbing Scafold KG 200/150
Consumbale Part for KG200/150
Climbing Platform UBR
Special form
1
1
1
1
ls
ls
ls
ls
3.5
3.5
3.5
3.5
1,809,280
1,118,720
1,612,880
1,501,440
6,332,480
3,915,520
5,645,080
5,255,040
1
1
1
1
ls
ls
ls
ls
3.5
3.5
3.5
3.5
924,000
1,210,720
-
3,234,000
4,237,520
28,619,640
SHEAR WALL 2
Item
Qty
Sat
Koef
Durasi
Sewa/Bhn
TOTAL
BAHAN
Phenol Film 18 mm
Paku
28.75571 lembar
10
kg
1.1
1.1
120,000
3,200
3,795,754
35,200
711.55
3,830,954
ALAT
Peri vario for shear wall h.3.95 m
Main girder GT 24
Main element
Accesoriess
1
1
1
ls
ls
ls
3.5
3.5
3.5
1,809,280
1,118,720
1,612,880
6,332,480
3,915,520
5,645,080
Consumable
ls
3.5
1,501,440
5,255,040
1
1
1
1
ls
ls
ls
ls
3.5
3.5
3.5
3.5
924,000
1,210,720
-
3,234,000
4,237,520
28,619,640
TOTAL WALL
Item
Qty
Sat
Koef
Durasi
Sewa/Bhn
TOTAL
BAHAN
Phenol Film 18 mm
Paku
131.685 lembar
40
kg
1.1
1.1
120,000
3,200
17,382,424
140,800
17,523,224
VOLUME TOTAL
- m2
3,259
#DIV/0! / m2
ALAT
Peri vario for core wall h.3.90 m
Main girder GT 24
Main element
Accesoriess
Consumable
Peri Climbing Platform for Core wall
Climbing Scafold KG 200/150
Consumbale Part for KG200/150
Climbing Platform UBR
Special form
1
1
1
1
ls
ls
ls
ls
3.5
3.5
3.5
3.5
1
1
1
1
ls
ls
ls
ls
3.5
3.5
3.5
3.5
8,141,760
5,034,240
7,257,960
6,756,480
4,158,000
5,448,240
-
28,496,160
17,619,840
25,402,860
23,647,680
14,553,000
19,068,840
128,788,380
146,311,604
#DIV/0! /m2
#DIV/0! /m2
0.00
bks_ramp
Bekisting RAMP
Sub Pekerjaan
Kuantitas 1 modul
Unit rate
=
=
=
Item
2.00 modul
modul
Qty
Unit
Koef
Unit Equip
Kapasitas
Jam
Material
Unit rate
Upah
Alat
Total
Kuantitas
Total Biaya
Material
Upah
Depreciati Fuel
Phenol film 18 mm
Paku
Kayu 5/10
Kayu 5/7
UPAH
Mandor
Tukang
Pekerja
Upah las stek
168
29.96757
2.5674
0.744
454.5
909
1818
454.5
lembar
kg
m3
m3
mh
mh
mh
mh
1.10
1.05
1.20
1.20
0.250
1.100
1.100
1.1
120,000
3,200
750,000
750,000
0.08
0.08
0.08
0.08
1,420.313
12,498.750
24,997.500
6,249.375
369.60
62.93
6.16
1.79
5,000
4,286
2,857
4,286
S.parts
Grand
Total
Rp.
44,352,000
201,376
4,620,000
1,342,500
22,176,000
100,688
2,310,000
671,250
14,203,150
107,132,036
142,842,714
53,566,018
7,101,575
53,566,018
71,421,357
26,783,009
3,969,000
1,890,000
4,082,400
2,170,800
2,721,600
4,082,400
21,262,500
776,250
2,500,000
3,969,000
1,890,000
4,082,400
2,170,800
2,721,600
4,082,400
21,262,500
776,250
2,500,000
1,984,500
945,000
2,041,200
1,085,400
1,360,800
2,041,200
10,631,250
388,125
1,250,000
Alat
Others
44,352,000
201,376
4,620,000
1,342,500
2,840.6
24,997.5
49,995.0
12,498.8
14,203,150
107,132,036
142,842,714
53,566,018
Labour
Interest
Insurance
158,871,959
32,900
ALAT
Main Frame
Ladder Frame
Base Plate
Joint Pin
Cross brace
UHJ
Horrybeam
Pipe supprot
Alat bantu
Total
TOTAL UNIT RATE
252
150
504
804
336
504
225
37.5
1
buah
buah
buah
buah
buah
buah
buah
buah
ls
4.5
4.5
4.5
4.5
4.5
4.5
4.5
4.5
1
1,750
1,400
900
300
900
900
10,500
2,300
2,500,000
2,268.00
1,350.00
4,536.00
7,236.00
3,024.00
4,536.00
2,025.00
337.50
1.00
50,515,876
317,743,918
43,454,950
411,714,744
10,461
65,799
8,999
85,259
205,857,372
411,714,744
85,259
Page 22
4,829.0 m2
302.4
16.0
pile cap
=
=
Sub Pekerjaan
Unit rate
=
=
PASANGAN BATAKO
Item
Batako
Semen
Pasir
2,059.49 M2
Qty
Unit
11 buah
0.4379 zak
0.0802 m3
UPAH
Mandor
Tukang
Pekerja
1 mh
1 mh
2 mh
ALAT
Alat bantu
1 ls
Unit Equip
Kapasitas
Jam
Koef
1.10
1.05
1.20
0.200
1.000
1.100
Material
Unit rate
Upah
Alat
800
20,000
43,000
1.75
1.75
1.75
0.114
0.571
1.257
Total
Kuantitas
24,919.86
946.94
198.21
5,000
4,286
2,857
Material
Total
TOTAL UNIT RATE
Page 23
Grand
Total
Rp.
19,935,888
18,938,800
8,523,030
9,680
9,196
4,138
23,014
1,176,850
5,039,866
7,396,507
571
2,447
3,591
6,610
205,949
205,949
100
Alat
19,935,888
18,938,800
8,523,030
235.4
1,176.0
2,588.8
100
Total Biaya
Upah
1,176,850
5,039,866
7,396,507
2,059.49
47,397,718
13,613,223
205,949
61,216,891
23,014
6,610
100
29,724
29,724
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
A
B
Jenis Alat
Kapasitas Jumlah
Renc.pakai
(bln/jam)
Tower Crane
2 t/50
0
1,000.00
Passenger Hoist (60 m)
1t
0
0.00
Material Hoist KB 5
1t
0
0.00
Genset TC
225 KVA
0
800.00
Genset PH
125 KVA
0
0.00
Genset Penerangan
75 KVA
1
12.00
Mobile Crane TL 35
35 t
Mobile Crane TL 45
45 t
Bar Cutter
29-40 mm
1
500.00
Bar Bender
41-43 mm
1
500.00
Concrete Pump
100 / 60 m3/ 12
1.00
Scaf keliling Finishing
1
1.00
Scafolding struktur
terpisah
0.00
Horrybeam
terpisah
0.00
Girder GT 24
terpisah
0.00
Air Compressor
175 Cfm
1
4.00
Summersible Pump
4"
4.00
Summersible Pump
3"
4.00
Concrete Vibrator
4mx38mm
4
2.00
Tamping Rammer
1
0.50
Baby Roller
Waterpump
3"
1
1.00
Waterpump
4"
0.00
Concrete Mixer
250 l
1
1.00
Theodolit
1
5.00
Waterpass
0
5.00
Mesin Las
300 Amp
4.00
Travo Las
4.00
EDM
DI 1000
3.00
ADD COST terhadap alat albes (sifat consumable)+mobdemob
Tambahan lain-lain BBM
ls
1
1.00
ME Darurat (masuk DC)
ls
1
1.00
Harga
Satuan +++
SEWA
TOTAL
Harga
Satuan
TOTAL
BBM
jml lt/jam
114,064
4,818,000
5,349,800
41,117
5,416,000
3,983,400
47,800,800
115,250
7,862,400
53,000
5,650,000
4,800,000
57,600,000
114,064
4,818,000
5,349,800
53,000
5,416,000
4,800,000
57,600,000
9,060
6,060
4,530,000
3,030,000
71,088,160
11,250
11,250
1,500,000
71,088,160
1,300,000
2,500,000
2,500,000
625,000
2,440,000
7,500,000
2,500,000
2,500,000
1,500,000
1,500,000
1,500,000
4,100,000
1,000,000
2,000,000
11,250
11,250
1,500,000
71,088,160
787,450
2,500,000
2,500,000
398,100
2,440,000
7,500,000
2,500,000
2,500,000
1,500,000
1,500,000
1,500,000
4,100,000
1,000,000
2,000,000
5,625,000
5,625,000
18,000,000
71,088,160
3,149,800
3,184,800
1,071,300
2,088,800
1,175,000
7,362,000
35,860,000
180,340,660
5,625,000
5,625,000
18,000,000
71,088,160
5,200,000
5,000,000
1,220,000
2,500,000
1,500,000
7,500,000
35,860,000
216,718,160
71,088,160
787,450
1,378,400
1,378,400
398,100
2,142,600
2,088,800
2,088,800
1,175,000
1,472,400
1,407,400
889,600
1,500,000
35,860,000
35,860,000
-
35,860,000
-
Jml BBM
20.00
20.00
12.50
-
harga BBM
16,000
27,000
500
125
500
375
-
3,149,800
2.50
3,184,800
5.00
1,220,000
5.00
2.50
2,500,000
2.50
2.50
1,500,000
7,500,000
35,860,000 Total Biaya BBM
- Asumsi kenaikan BBM 10 %
212,852,760 masuk ke resiko
1,150
1,550
1,550
1,550
-
Total harga
31,050,000
775,000
193,750
581,250
32,600,000
3,260,000
BIAYA LAIN-LAIN YANG MASUK DALAM BIAYA UMUM, MOBILISASI, PEK PERSIAPAN
1 Pondasi TC, Erection, Disman
ls
1.00
ls
ls
1
1
1.00
1.00
4,200,000
2,000,000
4,200,000
2,000,000
4,200,000
2,000,000
4,200,000
2,000,000
Mobilisasi
1 Angkut Scafolding+ Horry
2 Mob-Demob alat besar
MOBILISASI-DEMOBILISASI
4,200,000
2,000,000
Total
masuk BQ
masuk BU
4,200,000 resume
2,000,000 BIAYA ALAT NON BUAS
212,852,760
6,200,000 RESIKO BBM (incl. Alat non bua
3,260,000
MOBILISASI dan PONDASI TC MASUK BU
TOTAL BU DAN BP