This project includes the analysis of the conditions of the current operation
and the year 2020 of the primary feeders, belonging to Substation No 4
(Calpi-San Juan), EERSA, for this was used CYMDIST program, a tool that
allows to simulate The behavior of the primary feeders, that is, calculate the
operating conditions of the primary and its power losses at maximum
demand. In the primary feeder 104, operating with the demand projected to
the year 2020, a reconfiguration was realized that includes: division into 2
circuits, with the denomination San Juan and Espoch, then it was proceeded
to reconfigure the San Juan circuit, where it is contemplated: From Load,
change of gauge and the installation of a voltage regulator. For the feeder
204, 2 alternatives of the solution are developed, in the first alternative,
reconfiguration divided into 2 circuits with the denominations: 204 (San
Andrs) and 204 (Urbano), then the reconfiguration of the San Andrs circuit
was carried out that contemplates the change Driver's gauge; In the second
alternative, the reconfiguration is performed: the change of gauge in a small
section and the installation of a voltage regulator, the two alternatives are
taken first, which produces better profitability and less time to recover
capital. For feeders 304 and 404, their operating conditions for the year
2020 are within the norm, therefore, no investment is needed to improve or
justify an economic analysis.