Professional Documents
Culture Documents
TABLE OF CONTENTS
3.4 Resources
3.4.1 Helpful Links
3.4.2 Tools
3.4.3 Contacts
3.4.4 Business Systems
1- INTRODUCTION............................5
1.0 Overview
1.1 What is a project manager?
1.2 How will this guide help?
1.3 How is this guide organized?
4.0 Purpose
4.1 Managing the Scope
4.1.1 Monitor
4.1.2 Investigate
4.1.3 Take Action
4.1.4 Report
4.2 Managing the Schedule
4.2.1 Monitor
4.2.2 Investigate
4.2.3 Take Action
4.2.4 Report
4.3 Managing the Budget
4.3.1 Monitor
4.3.2 Investigate
4.3.3 Take Action
4.3.4 Report
4.4 Managing the Team
4.4.1 Monitor
4.4.2 Investigate
4.4.3 Take Action
4.4.4 Report
4.5 Chapter Summary
4.6 Resources
4.6.1 Helpful Links
4.6.2 Tools
4.6.3 Contacts
4.6.4 Business Systems
2.0 Purpose
2.1 Groups that Generate Projects
2.1.1 UDOT Program Managers
2.1.2 UDOT Portfolio Managers
2.1.3 Metropolitan Planning Organizations
2.1.4 Joint Highway Committee
2.1.5 UDOT Fund Fact Sheets
2.2 Different Types of Project Funding
2.2.1 Federal-aid Funding
2.2.2 State Funding
2.3 Process for Creating Projects
2.4 Chapter Summary
2.5 Resources
2.5.1 Helpful Links
2.5.2 Tools
2.5.3 Contacts
2.5.4 Business Systems
6- CONTRACT
ADMINISTRATION.....................31
6.0 Overview
6.0.1 Need for Contracting
6.0.2 Conflict of Interest
6.1 Contracting for Engineering Services
6.1.1 Contract Types
6.1.1.1 Project Specific Contract
6.1.1.2 Current Expense Contract
6.1.1.3 On Call Contract
6.1.2 Consultant Selection Methods
6.1.2.1 Work Task Orders
6.1.2.2 Direct Pool Select
6.1.2.3 Request for Pool Letter of
Qualifications (RPLOQ)
6.1.2.4 Streamlined RFQ
6.1.2.5 Request for Letters of Interest (RLOI)
6.1.2.6 Standard RFQ
6.1.2.7 Engineer of Record for Local
Governments
6.2 Third Party Contracts and Agreements
6.2.1 Utility Agreements
6.2.2 ROW Purchases
6.2.3 Federal Aide Agreements
6.3 Alternative Delivery Contracts
6.3.1 Design Build (DB)
6.3.2 Contract Manager/General Contractor
(CMGC)
6.3.3 Procurement Contracts
6.4 Construction Contracts
6.5 PM Responsibility in Contracting
6.5.1 Consultant Selection Method
6.5.2 Request Contract in Contract Management
System (CMS)
6.5.3 Select the Selection Team
6.5.4 Prepare Scope of Services and Schedule
GLOSSARY............................................47
Key
Definitions
Examples/Hints
Local Government
1.0 OVERVIEW
UDOT Project Management was created as an
organizational tool in 1997 to build on UDOTs
commitment to strengthen the coordination and
delivery of our projects. The Project Managers
(PMs) role to lead a team of skilled technical experts
to meet a projects goals (scope, schedule, budget,
and quality) and objectives is important in todays
challenging transportation environment.
Does it increase safe and efficient travel, not only through its project limits but by how it
connects travelers with the transportation system?
Rather than hold project resources for its own expansion, does the project consider
efficiencies to benefit the whole program?
These are some of the high-level challenges a PM may have to deal with as they lead their team
of specialists through concept development, design, advertisement, and construction.
This leadership role also requires strong communication skills: the ability to ask penetrating
questions, detect unstated assumptions, resolve conflicts, and guide a team through unknown,
changing obstacles. While the structure of the project team can vary widely from project to project,
the one constant is the PMs role as the leader of the project team, regardless of their authority
over the team members.
5
Chapter 1
2.0 PURPOSE
It is important for PMs and teams to know how projects are created and who is creating them.
It is also important to be familiar with the different types of project funding and know the unique
rules and limitations of each funding type. The following information will provide PMs with an
understanding of how projects receive their funding.
PROGRAM MANAGER
ROLES AND RESPONSIBILITIES
Chapter 2
require a funding match from either State or local government sources. Each funding category is
designated for certain types of projects and work. For example, National Highway Performance
Program funding is to be used only for projects on the National Highway
High
g wayy System.
Sy
ystem. FHWA has
prepared a Guide to Federal-Aid Programs and
MAJOR FEDERAL FUNDING
Projects to provide basic information concerning
PROJECT TYPES
the Federal-Aid Highway Program.
Chapter 2
2.5 RESOURCES
2.5.1 HELPFUL LINKS
2.5.2 TOOLS
2.5.3 CONTACT
2.5.4 BUSINESS SYSTEMS
ePM
Project Scheduling
eGIS
ProjectWise
CADD
PDBS
10
3.0 PURPOSE
Preserve Infrastructure
Optimize Mobility
Zero Fatalities
Strengthen the Economy
SOURCES OF PROJECT
INFORMATION
11
Chapter 3
Project Sponsor
The Senior Leader or Portfolio Manager:
Defines the project objectives and
expected outcomes
Champions the project
Obtains project funds
Supports the PM with the project
Scope, Schedule, and Budget
Supports the Project Manager
resolving escalated issues
Proposed Advertise/
Proposed Due Date
The PA/PD Date is established by
the Program or Portfolio Manager,
prior to project funding, and is
used to communicate project
delivery expectations.
The size and composition of the Definition Team depends on the project characteristics. It should
consist of two to seven team members, with the main criteria for selection based upon the major
components of the project. Definition Team members are responsible to represent their area of
expertise in developing the strategy to deliver the project. A Definition Team member may also be
part of the Project Delivery Team.
Federal Aid Local Government projects will have at least one representative from the local entity
and/or MPO on the Definition Team. On UDOT projects
with major impacts to local governments, the PM may
Example Definition Teams consider including a representative from the local entity
Pavement Preservation Project
on the Definition Team.
Project Manager
Region Pavement Engineer
New Traffic Signal Project
Project Manager
Region Traffic Engineer
Central Traffic Engineer
Preconstruction Engineer
Capacity Project with New Bridge
Project Manager
UDOT Structures Engineer
Region Utility Coordinator
Central ROW Representative
Preconstruction Engineer
Maintenance
12
The Project Objective Statement is a brief highReconstruct and widen (to 12 lanes)
level summary of the major work elements to be
I-15 from 11400 South Interchange to
accomplished, the expected delivery date and project
Bangerter Highway by December 31st
2014 for $160 Million.
value. The summary should be less than 25 words
and serve to focus the Definition and Project Delivery
Teams throughout the development and execution of the
Project Goals and Metrics
project.
Project Scope
Statements
Overlay Project
Overlay road with 2 to 3 inches of
HMA in travel lanes and shoulders
Replace all safety signs on
project limits
Mill and fill existing asphalt in
Provo River bridge
Do not install, replace, or improve
guardrail
Do not replace drainage pipes
Capacity Project
Goal: Improve Level of Service on
corridor from E to D
Metric: Use traffic data prior to and
after project completion
Safety Spot Improvement Project
Goal: Reduce crashes at intersection
by 50%.
Metric: Use Central Traffic and Safety
data to compare crashes before and
after the project completion
3.1.4.3 PROJECT
SCOPE STATEMENTS
Project Scope Statements define the work that needs to be
accomplished to satisfy the Project Goals. These statements
document the major components of the project. The team
should also document what is not included in the project.
The is not statements are important because they help
to reduce scope creep during delivery of the project. The
Project Delivery Team will use these statements to better
understand their role and effort on the project.
UDOTs Practical Design initiative eliminates over designing
improvements by aiming to achieve, but not exceed,
the project objectives. The documented project scope
13
Constraint Matrix
Most
Scope
Schedule
Moderate
Least
X
X
Budget
14
individuals will work on the project based on their availability and skill set, relative to the project
needs.
The Project Delivery Team can consist solely of UDOT employees, or both UDOT and consultant
team members. If a consultant is needed on the Project Delivery Team, then the PM should
initiate consultant selection and contracting as soon as possible. The PM can then use the Project
Scope Statements to help develop the Scope of Services for consultant selection and hiring. The
consultant should be under contract prior to the Kickoff meeting. More information on consultant
procurement can be found in Chapter 6 Contract Administration of this UDOT PM Guide.
Local Government (LG) projects are always designed by consultants and a LG representative
assists with the consultant selection and project management.
15
Chapter 3
Building and Uniting the Team in the Team UDOT: Team Building Guide.
Most projects should have a Kickoff Meeting but some simple projects can be commenced via
email or other coordination. Any consultant working on the design phase of the project is selected
and under contract prior to project Kickoff.
Baseline Schedule
16
3.4 RESOURCES
Project Definition Document
Engineers Estimate
3.4.3 CONTACTS
Region Program Managers
Innovative Contracting & Project Controls
Manager
UDOT MS Project
17
Chapter 4
4.0 PURPOSE
The PMs role changes when the project transitions from the Definition process to the Delivery
process. During the Definition process, the PM actively leads the Definition and Project Team to
develop the Project Plan. Once developed, approved, and initiated, the PMs role is to oversee
and manage the execution of the Project Plan and adopt the teams efforts as changes occur.
It is important that the PM maintain the proper leadership level as the project plan is carried
out. Some PMs micro-manage the project team members by inserting themselves into their
processes and work. Other PMs know little about the current project issues and they abdicate
their management responsibilities to Delivery Team members. The art of Project Management
is to know where the appropriate leadership level is for each specific project and Delivery Team.
This level will vary from project to project and is dependent on factors, such as team member
experience, project risk, and project type.
The PM manages the execution of the project Scope,
Schedule, Budget, and Team throughout the project
execution phase using the management principle of
MITAR: Monitor, Investigate, Take Action, Report.
As work progresses and changes occur, the PM
investigates the root causes for the change from
the baseline, takes action to resolve the changed
condition, then reports the actions taken to those
affected by the change.
18
MITAR
Monitor
Track and compare project progress to
the baselined Project Plan
Investigate
Explore the causes and possible
resolutions to changes in Scope,
Schedule, Budget, and Team
Take Action
Manage and record the changes, issues,
and risks that emerge as the project
progresses
Report
Communicate actual performance,
progress, variances, and actions taken to
appropriate members of the organization
4.1.1 MONITOR
Scope MITAR
Monitor
During a weekly team meeting, the PM
discovers that the designer has added
the replacement of all the small drainage
culverts that cross the road. This was not in
the original scope of the project.
Investigate
The PM questions the designer and finds
that the Maintenance Engineer requested
that he add these culvert replacements
to the project. The PM follows up with the
Maintenance Engineer and finds a recent
inspection revealed that most of the culverts
were partially collapsed.
Take Action
The PM meets with the Designer, the
Maintenance Engineer and region
management to decide if this additional
scope should be added to the project. If so,
the PM will have to determine if the project
has sufficient funds or if additional funds
are required.
Report
The PM communicates to all team members
the actions taken and consequences of this
resolved issue.
4.1.2 INVESTIGATE
The PM and Delivery Team need to understand
the source of the scope change issues.
These can include: unforeseen conditions,
stakeholder requests, work to be accomplished,
misunderstandings, success criteria, rumors,
changes in quality, and perceptions.
4.1.4 REPORT
Communicate any changes in project scope to all
team members following decisions made by Region
Management or the Utah Transportation Commission.
Scope Creep
Uncontrolled additions in a projects
scope. This occurs when the scope
of a project is not properly defined,
documented, or communicated.
4.2.1 MONITOR
The Critical Path should be monitored with high rigor. Any changes to Activity durations on the
Critical Path will affect the finish date of the project. Analyze activities not on the Critical Path to
determine if delay would put them on the Critical Path. The Project Team reviews and discusses
the project schedule especially at each Milestone Meeting where any variance from the baseline
schedule is identified and noted.
19
Chapter 4
4.2.2 INVESTIGATE
Schedule MITAR
Monitor
During a review of the project schedule, the PM
discovers that the utility coordinator has extended
completion of a critical path activity by 3 weeks.
Investigate
The PM talks with the utility coordinator and finds
that they have been assigned to a large project
and can only work half-time on the other region
projects. This will delay all of their project work.
Take Action
The PM meets with the utility coordinator and
Region Management to brainstorm solutions. They
decide to hire a consultant to work for the utility
coordinator to help relieve the utility coordinators
workload.
Report
The PM reports the resolution to the Delivery
Team.
4.2.4 REPORT
Critical Path
20
4.3.1 MONITOR
The PM regularly compares actual versus negotiated
pre-construction costs. These costs are typically
broken down by scheduled Activity, which helps to
easily identify exceeded Activities.
At a minimum, the PM and Delivery Team develop,
update and review the project construction estimate
at every Milestone meeting. If the construction
estimate has increased and exceeds the construction
budget, the team then identifies which items have
caused the increase.
4.3.2 INVESTIGATE
21
Chapter 4
be necessary if additional project funding is not possible. The PM then notifies the Program
Manager of the potential budget impacts so it can be decided if a budget adjustment request
should be made to the Utah Transportation Commission.
4.3.4 REPORT
Document all report actions taken to resolve budget issues and share reports with the Project
Team.
4.4.1 MONITOR
Its important that the PM continually monitors the
Delivery Team. Some common concerns for a PM
to consider while monitoring the Delivery Team
include changes in team membership, resource
over-allocation, effectiveness of Project Team
communication, and team member participation
and motivation.
4.4.2 INVESTIGATE
If the PM identifies issues and problems within
the Project Team, they should further investigate
the root causes for these problems. The PM
and Functional Manager should review the team
members resource schedule to decide if they are
22
Monitor
While discussing your project with
the Design Leader, she states that the
Structures Lead will not return her calls
or emails about some key elevation
information that is needed to complete the
Plan-in-Hand review package.
Investigate
The PM promptly sets up a meeting with the
structures lead. The Structures Lead states
that he was extremely offended by some
comments made by the Design Leader at
the last meeting. He does not think the plan
set needs the requested information and
does not want to talk to the Design Leader,
so he has ignored her information requests.
Take Action
The PM sets up a meeting with the Design
Leader and the structures lead. The PM
initiates the meeting by reviewing the
Developing Trust section in the Team
UDOT: Team Building Guide. The PM should
make certain that the atmosphere in this
meeting is non-threatening and open. It is
important to elicit solutions for this issue
from the two contending team members.
The Team members resolve this conflict by
agreeing to certain rules of communication.
They also agree to treat each other
professionally and respectfully.
Report
This resolution should be reported to
leadership and those team members
affected by this conflict. There is no need
to inform other team members who are
unaware of this conflict.
overscheduled. The PM and Functional Manager should also understand the team members
experience and skill sets to make sure they align with their role on the project. The PM should
recognize and identify personality differences within the team, particularly if those differences are
causing conflict. If appropriate, the PM should reassess the Teams communication plan to make
sure it is efficient and appropriate for the project.
4.4.4 REPORT
Actions taken to resolve Team conflict or communication issues should be shared with both core
and extended team members, as well as management. This allows the opportunity to support and
strengthen the project team.
4.6 RESOURCES
4.6.1 HELPFUL LINKS
UDOT Project Financial Management Guide
UDOT Team Building Guide
4.6.2 TOOLS
Team Meeting Agenda
Milestone Meeting Agenda
4.6.3 CONTACTS
4.6.4 BUSINESS SYSTEMS
ePM
UDOT MS Project
23
Chapter 5
CONSTRUCTION STAGES
Advertising
Project advertisement up to Notice to Proceed
Construction
Notice to Proceed up to Substantial Completion
Construction Closeout
Substantial Completion through Contract Completion
Financial Closeout
Termination of Authority through Financial Closure
24
provided the answer. If the PM or RE is contacted by a contractor, or any other construction related
personnel, with questions concerning a project that has already gone to advertise, the PM and
RE will coordinate the answer and document the response. The RE will provide administrative
resources to document attendance and meeting minutes. FHWA has issued a Pre-bid Meeting
Guidance Document that gives further direction on Pre-bid meetings.
Discussion Items
Specifications
Subcontractors
Materials
Waste Areas
Major Work Operations
Insurance
Goals and Action Plans
Schedule
Utilities/RR Schedules
Prosecution & Progress
Affirmative Action Plan
DBE Participation
Communication
Suppliers
Quarries
Surveying
Contract Administration
Partnering
Traffic Control/Signing
Right of Way
Environmental
Consideration
Issues/Conflict
Escalation Plan
EEO and Labor
Compliance
Partnering Maintenance
If the lowest responsive bid is greater than 110% of the Engineers Estimate, the PM will follow the
UDOT 08B-12 policy for contract award guidance.
UDOT Central Construction maintains the Project Management Forms and Project Advertising
Assistance required during the Advertising Stage.
25
Chapter 5
project is built in accordance with those contract documents. The District Engineer (DE) has
oversight responsibility for change orders, contractor claims, and FHWA stewardship issues.
During construction, all communication with contractors, sub contractors, and suppliers is routed
through the project RE. This single point of contact ensures that all answers to project questions
are consistent. The RE and PM will discuss all significant issues and responses, prior to contractor
communication. Significant issues may include costly change orders, schedule increases, or
additional impact to highway users, residents, and businesses.
If the project requires consultant Construction Engineering or consultant Public Involvement during
the construction stage, select and contract these services prior to the Plans, Specifications, &
Estimate (PS&E) review meeting. If it is determined that such services are necessary at the time
of the Plan in Hand review meeting, its beneficial to have CE or PI under contract in time to attend
the meeting whenever a project is complicated or controversial.
The Construction Manual of Instruction defines and
establishes the responsibilities of a UDOT RE, DE,
and field personnel regarding the administration of
contract provisions.
26
5.3.2 PARTNERING
Partnering with the contractor is a
valuable standard practice for all
UDOT projects. Partnering occurs
when two or more organizations
make long-term commitments to
achieve mutual goals. Effective
partnering requires trust, open
communication, understanding and
teamwork among all participants.
It is recommended that all UDOT
PMs take Partnering Trainings 1,
2, and 3. For additional information
about Partnering, please refer to the
UDOT and AGC Partnering Field
Guide and Partnering Team Weekly
Agenda.
A PM supports the RE in resolving
project issues by staying sufficiently
involved to ensure that constructive
relationships are being maintained
among team members. If conflicts
arise see the TeamUDOT Team
Building Guide for conflict resolution
ideas.
Chapter 5
The PM will participate in the final inspection and communicate any concerns to the RE. This
inspection is set up by the RE and includes all relevant project stakeholders. The contractor
is responsible to immediately resolve and repair any unsatisfactory work. Upon correction or
resolution of unsatisfactory work, the RE notifies the contractor in writing on the date of final
acceptance.
The RE completes all the necessary construction paperwork and collects all required documents
from the Contractor. He then submits all appropriate documents to the Region Contract Specialist
(RCS). The RCS reviews and quality checks all submitted documents, verifying that the construction
contract is ready for closure. The RCS then submits all the appropriate documentation to Central
Construction. Central Construction issues the Construction Final Letter once they verify
completeness of the construction documentation
and distribution of the contractors final payment.
5.5.5 AUDIT
Utility and consultant contracts are subject to internal UDOT audit. Audits are triggered by dollar
amount thresholds, identified in the UDOT Project AUDIT Cost Estimates sheet. Upon completion
of final utility and railroad payments, Central Construction forwards the contracts for audit. If a
Consultant contract warrants an audit, the Comptrollers office forwards the contract to the UDOT
Auditor.
29
Chapter 5
distributes the Final Voucher (FV). Program Finance reconciles the final project funding and
closes the business systems (FINET, ePM, FMIS).
5.7 RESOURCES
5.7.1 HELPFUL LINKS
Construction Manual of Instruction
Innovative Contracting
Addendum Manual: Pre-bid Guidance
Document
UDOT Policy 08-12
FHWA Pre-bid Meeting Guidance Document
5.7.2 TOOLS
Partnering Team Weekly Agenda
Construction Overrun Funding Need (COFN)
Consultant Project Evaluation Form
5.7.3 CONTACTS
Innovative Contracting and Project Controls Manager
Region District Engineer
UDOT Advertising
CONTRACT ADMINISTRATION
6.0 OVERVIEW
UDOT contracting
methods
encourage
innovation and speed, and seek a fair and
equitable balance for everyone, including the
consultant, the contractor, and the general
public.
Consultants provide a valuable service to UDOT
project teams, supplementing internal staff
resources and bringing specialty experts as
you need them. Other benefits are a scalable workforce, bringing experience to an inexperienced
team, and sharing innovations learned from work on other projects. All PMs will eventually hire
consultants to perform work for their projects. Services could range from small tasks to complete
design. The PM is responsible to direct this work through executed contracts.
This chapter will focus on the contract administration responsibilities of the PM. The Consultant
Services Manual of Instruction provides
further assistance for contract procurement.
The primary reason for contracting is the limited
The Consultant Services Manual of Instructions Conflict of Interest section should be reviewed
prior to every project.
31
Chapter 6
to minimize design errors and reduce rework. A UDOT PM must always maintain high ethical
standards and confidentiality throughout the advertisement, selection, negotiation, and execution
of the contract. (See UDOT Ethics Policy for more information and clarification of responsibilities.)
32
contract up to $150,000, the PM may select a consultant that has available pool funding directly
from the qualified pool lists. The contract is then negotiated and executed. Special caution must
be exercised because the $150,000 cap is a hard limit and cannot be exceeded. Select this
method for straight forward tasks that slightly exceed the amount for WTOs, or when the desired
consultant does not have an On Call contract in place.
33
Chapter 6
SOQ ranking.
34
and budget. Agreements with each utility company are necessary for cost reimbursement. Utility
companies will often seek to improve their facilities during the project through a betterment.
These improvements are not reimbursable. Accurate cost estimates and schedules need to be
established and monitored.
35
Chapter 6
36
to evaluate each consultants proposal. The criteria should align with the projects goals. For
example, if the project is very unique and controversial, the highest weighting may be assigned
to similar project experience.
37
Chapter 6
necessary. Contract modifications may include added or modified scope that increase the work
and cost, or a simple no-cost time extension. The PM must ensure available project funds exist
to cover any cost increases.
6.6 RESOURCES
6.6.1 HELPFUL LINKS
6.6.2 TOOLS
Federal Aid Agreements (most used)
Consultant Evaluation Form
6.6.3 CONTACTS
Innovative Contracting and Project Controls
Manager
UDOT Procurement
Consultant Services
Region Program Manager
Region Functional Managers
38
Risk
7.1 DEFINITIONS
7.1.1 FLAVORS OF RISK
To better understand the types of risks that UDOT
faces and who is responsible for managing them,
we have divided them into three broad categories:
programmatic, formal, and project-level.
Chapter 7
PROGRAMMATIC RISK
The process that UDOT has elected to use is a cost based risk
analysis. In this process risks are quantified by their potential
cost to the project in terms of dollars and time. Time, of course,
can also be assigned a dollar value. By quantifying risks using
a common value, risks can be compared relative to each other
allowing the largest potential risks to be identified. This helps the
project team focus their efforts where they will have the biggest
effect.
On simple projects, the Project Manager may elect to lead the Risk Workshop themselves, or
they may ask the Design Lead or RE to lead it. On more complex projects, outside help should be
brought in to assist. This may be a Consultant or a Central resource. See section 7.5 for available
resources.
40
FIGURE 7.1
41
Chapter 7
CEVP and CRA are both probability based risk estimating tools. The basic process is the same
for both tools but the CEVP tool allows a much more sophisticated model. Both tools require
the same input; namely, the current estimate and schedule for the project with all contingency,
FIGURE 7.2
42
allowances, and risks removed. A Risk Assessment Team is assembled and can include members
of the project team and possibly outside experts, depending on the project needs. The team will
hold a workshop to brainstorm potential risks for the project and assign a probability of occurrence,
as well as the range of potential outcomes if the risk does
Value Engineering
occur.
Value Engineering is required on all
FIGURE 7.3
43
Chapter 7
FIGURE 7.4
44
45
Chapter 7
7.5 RESOURCES
Benefits of Risk Management
7.5.2 TOOLS
Risk Assessment Checklist
Project Outreach Planner (POP)
Qualitative Risk Worksheet
7.5.3 CONTACTS
UDOT Risk Manager
Deputy Preconstruction Engineer
Public Involvement Manager
46
GLOSSARY
23CFR
Title 23 Code of Federal Regulations
Regulation to implement and carry out the
provisions of Federal law relating to the
administration of Federal aid for highways.
(FHWA)
ABC
Accelerated Bridge Construction
A method of bridge construction that uses
innovative planning, design, materials,
and construction methods in a safe and
cost-effective manner to reduce the onsite
construction time that occurs when building
new bridges or replacing and rehabilitating
existing bridges. (FHWA)
AC Agreement
Advanced Construction Agreement
An AC agreement allows the State to
advance a federal construction project without
obligating the Federal Aid. The State or Local
Agency bears all expenditure outlay to cover
the agreement. This is typically handled
through Systems Planning & Programming.
AC Conversion
Advanced Construction Conversion
When the intended Federal Aid and/or
Obligation Authority is available, a portion or
the entire AC amount may be converted to
obligated funds. Eligible expenditures may be
billed for reimbursement to the State or Local
Agency after the AC Conversion. (23CFR
Chapter I Subpart G 630.709)
ARRA
American Recovery and Reinvestment Act of
2009
The primary objective for ARRA was to
save and create jobs almost immediately.
Secondary objectives were to provide
temporary relief programs for those most
impacted by the recession and invest in
infrastructure, education, health, and green
energy. (Wikipedia)
ATMS
Automated Traffic Management System
ATMS is a component of an Intelligent
Transportation System (ITS). ATMS integrates
technology primarily to improve the flow of
vehicle traffic and improve safety. Real-time
traffic data from cameras, speed sensors,
etc. flows into the Transportation Operations
47
Glossary
48
CE Budget
Construction Engineering
Is the portion of a project budget that provides
construction engineering oversight on a
project.
CFC
County of the First Class Fund
House Bill 287 from the 2001 General
Legislative Session created a special revenue
fund that receives 25 percent of Salt Lake
County's 0.25 percent public transit sales tax
that was approved by voters in the November
2000 general election. Funds can be used
for I-15 and other state highway projects
within Salt Lake County and for debt service
on bonds issued to pay for such projects as
prioritized by the Transportation Commission.
(udot.utah.gov)
CHF
Centennial Highway Fund
The CHF is an allocation of state and
federal money for use in building capacitydriven transportation projects. Uses include
construction, major reconstruction or major
renovation of state and federal highways,
the most prominent of which was the I-15
reconstruction in Salt Lake County. (udot.
utah.gov)
CHNF
Critical Highway Needs Fund
During the 2007 Utah Legislative Session,
House Bill 314 created the CHNF. This fund
is used on various transportation projects
throughout the state as prioritized by the
Transportation Commission based on
recommendations developed by UDOT under
criteria identified in state law. (udot.utah.gov)
CMAQ
Congestion Mitigation Air Quality
A type of federal funding that may be added to
a project to assist in obtaining or maintaining a
certain standard of air quality.
CMGC
Construction Manager General Contractor
This is a modified Design Build process in
which the owner holds the contract for both the
consultant designer and the contractor.
CMGC Project
Construction Manager General Contractor
Project
Contracting process in which a contractor is
selected to aid with the design and is then
49
Glossary
50
FHWA
Federal Highway Administration
The Federal Highway Administration (FHWA)
is an agency within the U.S. Department of
Transportation that supports State and local
governments in the design, construction, and
maintenance of the Nations highway system
(Federal Aid Highway Program) and various
federally and tribal owned lands (Federal
Lands Highway Program). (fhwa.dot.gov)
FMIS
Fiscal Management Information System
Federal system used to enter and track
obligation of funds, expenditures, information
and financial changes and adjustments on
federally funded projects.
FMIS Action
Any adjustment or obligation within the FMIS
system that requires signature authorization.
FMIS Number
A unique number generated for each project
in ePM which identifies it within the FMIS
system.
FONSI
Finding of No Significant Impact
A FONSI is both the decision by FHWA
that the project has no significant impacts
and the documentation of that decision.
A determination that the project will have
no significant impacts is made by FHWA,
following consideration of the analysis
presented in the EA, consideration of
comments on the EA made by agencies and
the public, UDOTs selection of the preferred
alternative, and any changes in the proposed
action based on the comments received.
(UDOT Environmental Process Manual of
Instruction)
Final Voucher (FV)
A document generated by the Comptrollers
office that breaks down all costs on all sub
phases of a project or program. Every penny
that was programmed for the project is
accounted for by this final document.
Federal Aid Program
All federal funds that states are allowed to
expend, providing federal criteria is met.
Federal Bill Reimbursement
A weekly bill submitted to FHWA for
reimbursement to the state for costs incurred
on federal projects. Initially, the state covers
51
Glossary
52
53
Glossary
54
Operating Costs
Project costs that are not used to fund the
physical features of a roadway; such as
studies, design, construction oversight, etc.
Orange Book Project
(See Pavement Preservation Program)
Preservation projects that include pavement
and bridge preventive maintenance. Funding
may consist of state and/or federal funds.
Out Year
Refers to a fiscal year in the future.
Overflow
Project cost in excess of programmed funding
on Federal-Aid projects. Additional funding
sources must be identified for overflow
expenditures.
Overrun
An unexpected contract item cost that exceeds
the contracted quantity due to an underestimation of the item quantity. (LoDaRy)
OSR
Operational Safety Report
A report which includes a review of
accident history, existing features, and a
recommendation to correct these issues.
OSRs are provided at the beginning of
projects during the concept and scoping
phases so that safety planning can be a part of
the entire project development process. (udot.
utah.gov)
PDBS
Project Development Business System
A UDOT software application that allows
UDOT, its consultants, and contractors to
document and control construction projects.
PDC
Project Design Criteria
Established state and national standards and
procedures that guide the establishment of
roadway layouts, alignments, geometry and
dimensions for specified types of roadways
in certain defined conditions; the principal
design criteria for roadways are traffic volume,
design speed, the physical characteristics of
vehicles, the classification of vehicles and the
percentage of various vehicle classification
types that use the roadway. (iowadot.gov)
PDD
Project Definition Document
Defines the project scope, goals, metrics, and
delivery method; identifies major potential
Pass Through
Federal funds that are passed directly through
UDOT to the receiving entity. The state
never deposits the funds, but distributes them
only. Example: The state receives funds
from FHWA and distributes them to the City,
County, private party, or other entity.
Pavement Preservation Program
Consists of preventive maintenance
projects that includes that include pavement
maintenance. Funding may consist of state
and/or federal funds.
Pending Action
Anything entered into FMIS that is waiting for
federal approval and/or authorization.
Planned Funds
Funds that are part of the Federal
apportionment for a fiscal year. These funds
are programmed in the STIP and ePM to be
obligated with specific criteria set by FHWA.
Policy
Defines the broad guidelines by which the
UDOTs administrative groups develop their
administrative rules. (udot.utah.gov)
Post Audit (see Audit)
UDOT Internal Audit Division performs post
audits on utility contracts (over $25K) and
consultant contracts (over $250K). Contracts
less than the threshold amount may also be
selected for post audit if there have been past
audit problems with an entity, the entity is not
familiar with federal regulations, or otherwise
selected for audit review.
Pro Rata
Proportional Ratio
The percentage at which federally funded
projects are matched by either the state or
local funds.
Procedure
States how policy will be implemented.
Program
Programs are approved on the STIP as an
allotment of money that is designated for
a certain type of work. Projects are then
selected by a Program/Portfolio Manager
based on criteria designated for that Program.
(UDOT PM Guide)
Program Finance
The UDOT department responsible for the
obligation and authorization of funding.
55
Glossary
Project
Projects are approved individually on the
STIP. A project is an effort, having a defined
beginning and end undertaken to meet unique
transportation needs. (UDOT PM Guide)
ProjectWise
A Bentley application that UDOT uses for
project file management and collaboration.
Project Definition Document (see PDD)
Project File
Hard and electronic copies of all required
documents and necessary e-mails for a given
project or program for program finance.
Project Value
The total funds available for a project.
Purple Book Project
Projects that address only the pavement
surface, which includes resurfacing for asphalt
pavements or work of similar scope and
function for concrete pavements; work items
are limited to pavement resurfacing and other
work that is necessitated by that resurfacing.
(UDOT Purple Book Scoping & Development
Process Guidelines)
R-76
State-Only Funded Project Funding
Authorization Form
Form generated by Program Finance and
used by UDOT that authorizes the spending of
state funds on a project.
R-77
Termination of Authority Form
Document generated by Program Finance
after receipt of the final letter, or email from
the PM for non-construction projects, that
terminates the spending authority of a project.
R-709
Federal Funding Authorization Form
UDOT Form generated by Program Finance
that authorizes the spending of funds on a
program or specific sub phases of a project.
RE
Resident Engineer
The individual responsible for the day to day
construction management of a project.
RFP
Request for Proposal
An invitation to contractors or consultants to
submit a proposal on a specific project.
56
RFQ
Request for Qualifications
An invitation to consultants to submit a
statement of qualifications on a specific scope
of work for a project. The RFQ process is
a qualifications-based selection following
the Brooks Act in 1972, which requires
that engineering firms are selected based
upon their competency, qualifications, and
experience rather than by price. (Wikipedia)
ROD
Record of Decision
The ROD (signed by FHWA) constitutes the
official federal decision and action for the
project under NEPA, meaning that FHWA
and UDOT can proceed with right-of-way
acquisition and final design of the project.
(UDOT Environmental Process Manual of
Instruction)
ROW
Right of Way
A division within UDOT Project Development
whos primary responsibility is to acquire
property needed for highway purposes and
relocate displaced businesses or persons.
The division is also responsible for the
management of properties acquired, the
oversight of local government highway
projects using state and federal funds, utilities,
access management, statewide permits, right
of way plans, maps and records. (udot.utah.
gov)
ROW, Acquisition
The process of acquiring real property (real
estate) or some interest therein. (UDOT
Acquiring Property Brochure)
ROW, Incidentals
Any expenses incurred from the acquisition of
right of way, i.e. appraisals, relocation costs,
closing costs, lawyer fees, etc.
ROW, Shotgun Estimate
Document created by the Right of Way agent
when properties must be acquired for the
building of roads. The property purchased
could be multiple parcels that are fully or
partially impacted by a road construction
project. The shotgun is a breakdown of the
costs of the acquisition. An R-709 must
be submitted along with this document for
requesting funds from FHWA.
RUE Engineer
Right of Way, Utilities, & Environmental
Engineer that oversees Right of Way, Utilities,
& Environmental.
Red Book Project
Safety Spot Improvement projects, which may
include new signal equipment at warranted
intersections, guardrail end treatments,
intersection lighting route markers, school
zone sign upgrades, turn lanes, shoulder
treatments, passing lanes and other spot
safety work.
Rescission
Legislation enacted by Congress that cancels
the availability of budget authority previously
enacted before the authority would otherwise
expire. (fhwa.dot.gov)
Systems Planning & Programming (SP&P)
Division that supports UDOT's overall
efforts through four major business areas:
1) monitor transportation system conditions,
2) identify transportation needs, 3) establish
transportation plans, 4) determine program.
(udot.utah.gov)
SR
State Route
Roads that comprise the state road system.
STIP
Statewide Transportation Improvement
Program
UDOT's Statewide Transportation
Improvement Program (STIP) is a five-year
plan of highway and transit projects for the
State of Utah. The STIP is approved by the
FHWA and Federal Transit Administration
(FTA) and includes all TIP projects as adopted
by the Metropolitan Planning Organizations
(MPO) and approved by the Transportation
Commission.
SUE
Subsurface Utility Engineering
A branch of engineering practice that involves
managing certain risks associated with utility
mapping at appropriate quality levels, utility
coordination, utility relocation design and
coordination, utility condition assessment,
communication of utility data to concerned
parties, utility relocation cost estimates,
implementation of utility accommodation
policies, and utility design. (ASCE)
Scenic Byway
Roads designated on the National Scenic
Byways Program (NSBP) that have
outstanding scenic, historic, cultural, natural,
recreational, and archaeological qualities.
(fhwa.dot.gov)
Soft Match (see Flexible Match)
State Forces/Furnished
State employed man power or state owned
materials that may be used on a project.
Must have justification for use, due to
noncompetitive selection.
State Funding
Funding that will not be reimbursed by federal
funds. No federal authorization is needed.
Stewardship Agreement
An agreement to formalize the roles and
responsibilities of the FHWA, Utah Division
and UDOT in administering the Federal Aid
Program.
Sub Phase
Each project is sub divided into several
phases. A sub phase denotes one of these
divisions. Examples include: 01D for in house
PE, 06K for construction, 03C for construction
CE, etc.
T-725
Project Authorization Memo
Document that shows the breakdown of costs
on each sub phase of a project along with the
funding source/sources. This document is
submitted to the Deputy Director for signature
prior to the advertisement of the project.
TIF
Transportation Improvement Fund
The TIF was created in the 2005 Special
Session by House Bill 1008 and contains
revenue from legislative appropriations,
sales tax and vehicle registration fees. These
funds are used for maintenance, construction
and reconstruction of state and federal
highways as assigned by the Transportation
Commission. (udot.utah.gov)
TIGS
Transparency in Government Spending
A UDOT website that shows the public how
funds are being spent on projects.
TIP
Transportation Improvement Program
The Transportation Improvement Program is
57
Glossary
58
VMS
Variable Message Sign
Electronic roadway signs that provide
changing but specific information to roadway
users. Messages are controlled by the
TOC and may be used for the purpose of
construction, incident management, traveler
information and maintenance activities.
(cotrip.org)
Various Routes
When a project has multiple routes that are not
defined/mapable in ePM.
W10A
Federal Funding Balance Report
FMIS report that shows exact federal funding
amounts obligated and remaining to be
expended by the state.
W96A
Federal Authorization Form
FMIS report that shows all obligated funding
on a project.
WFRC MPO
Wasatch Front Regional Council
The WFRC is an association of 60 cities
and five counties organized for the purpose
of pursuing goals of common interest. The
WFRC area of service comprises Davis,
Weber, Morgan, Salt Lake and Tooele
Counties and the cities contained therein.
(wfrc.org)
WTO
Work Task Order
A request for specific consultant work using a
preapproved on call contract. (LoDaRy)
Yellow Book Project
Emergency UDOT bridge repair projects.