BOLL OF QUANTITY (BOQ)

Single Storied (Tin Shed) Residential Building at Kochua, Chandpur

CONSIDERING RCC STRUCTURE


Sl

Item of Works

Unit

1 EARTH CUTTING: Earth work in excavation of all kinds of soil Cft.


of foundation trenches in/c. leveling, ramming and preparing
the base, bailing out water and shoring if necy. Prdg.
Centerline and bench mark pillars, removing the spoils etc. to
a lead beyond 60m. Beyond 1.5m depth. All complete as per
specification.
2 EARTH FILLING: Earth filling in foundation trenches and plinth Cft.
in 6" thick layer with earth available within 90m of the
building site, watering, leveling and consolidating each layer
up to finished level etc., all complete as per specification.

Quantity
2925.00

Rate(TK)

Amount(TK)

6.00

17,550.00

1,440.00

5.00

7,200.00

3 Supplying and laying of single layer Polythene sheet weighing Sft.


one kilograme per 6.5 square metre in floor below cement
concrete,reinforced concrete slab etc. all complete
charge.direction of the Engineer in in all respects as per

450.00

3.00

1,350.00

4 BRICK FLAT SOLING: One layer of brick flat soling under Sft.
ground floor slab with 1st class bricks in/c. preparation of bed
and filling the interstices with local sand. All complete as per
specification.
5 C.C CASTING: 3" thick casting (1:3:6) in cement concrete with Sft
cement, sand (F.M. 1.2) picked jhama chips in/c. breaking
chips, screening, centering, shuttering, casting curing and
finished. All complete as per specification.

450.00

30.00

13,500.00

1,825.00

35.00

63,875.00

6 R.C.C CASTING : Reinforced cement concrete works with a Cft.


mix proportion of (1:1.5:3) in foundation, column, beam, slab,
wall and floor of vault and stairs, drop wall, lintel with best
coarse screened sand (FM-2.5) and " down graded stone
chips and screening centering placing of rod in position,
mixing the aggregates in mixture machine casting in forms
compacting by mechanical vibrators and curing as per
drawing and specification. (Excluding MS Rod)

1,506.00

325.00

489,450.00

7 SHUTTER: Fitting & fixing of Wooden shutter including supply Sft.


of plank/timber, GI wire, nail pin, rupban sheet, applying form
oil, cost of form oil, shutter making, cleaning, stacking at
suitable place providing necessary tools & plants etc. all
complete as per direction of Engineer-in-Charge.

3,359.32

30.00

100,779.72

8 MS ROD FABRICATION (60-grade): Supplying, fabrication and Ton.


fixing to details as per design deformed bar reinforcement in
concrete in accordance with BSTI standard in/c. straightening
and cleaning rust, if any, bending and binding in position in/c.
supply of G. I. wires etc., complete in all respect in all floors
(60- grade deformed bar. All complete as per specification.

4.44

62,000.00

275,004.78

9 5" BRICK WORKS: 5" thick Brick work with 1st class bricks in sft.
cement mortar (1:4) and making bond with connected walls
including curing all complete etc. as specified.

4,176.00

50.00

208,800.00

10 Roof Sheeting: Supply and application roof sheet and finish all Sft.
complete as per direction of Engineer-in-Charge.

2,450.00

90.00

220,500.00

11 PLASTER WORK: Min. 12mm thick (1:4) to Ceiling & wall both sft
inner and outer surface finishing the corners and edges in/c.
washing of sand cleaning the surface, scaffolding and curing
at least for 7 days etc., all complete as per direction of the
E/ch. Ground floor. Min. 6mm thick C. P(1:4) to ceiling, R.C.C.
columns, beams, surface of Stair Case & Slab, sunshade,
cornices, railings, drop walls, louver fins and finishing the
corners and edges in/c. washing of sand cleaning the surface,
scaffolding and curing at least for 7 days etc., all complete as
per direction of the E/ch. Ground floor

6,960.00

20.00

139,200.00

12 PAINT WORKS: Approved best quality and colour Distemper Sft.


delivered from authorized local agent of the manufacturer in
a sealed container, applying to wall and ceiling in 2 coats over
a coat of brand specified primer or sealer elapsing specified
time for drying/ recoating matt finish including cleaning and
sand papering making the surface free from loose and flaky
materials, dirt grease, wax, polish, scraping all chalked and
scaled materials, applying the paint by brass/ roller and
necessary scaffolding etc. all complete in all floors accepted
by the Engineer.

6,960.00

15.00

104,400.00

Grand Total (BDT)

1,641,609.50

N.B. The cost are arbitrary on the basis of available information. These may be changed due to rate, plan & information changes.