You are on page 1of 136

l

R
;
e
so
t
;
r
s

UPCOMING & BUILT ASSETS


OF CPWD

Volume - I

DIRECTORATE GENERAL, CENTRAL PUBLIC WORKS DEPARTMENT


Year - 2014

Upcoming & Built Assets of CPWD - A Handbook


July, 2014

Published By:
Directorate General
Central Public Works Department
101 A, Nirman Bhawan
New Delhi 110011
Email: cpwd_dgw@nic.in

Prepared by:
Addl. Director General (Arch.)
CPWD, Nirman Bhawan
New Delhi 110011
Email: adg-arch.cpwd@nic.in

Technical Advisory Team:


CPWD Smt. Sipra Mitra (ADG, Arch.)
Sh. Anil Grover (Arch.)

Support Team:
Smt. Manjula Khan (Arch.), Smt. Suman Bhatia (T.O.)
Smt. Seema Bindlish (T.O.), Smt. Sarla Kaul (T.O.)

Printed by:
Falcon Graphics,
M-2, A 42-44, Manushree Building
Commercial Complex
Dr. Mukherji Nagar, Delhi - 110009
Email: falcon_graph@yahoo.co.in

Any part of the publication may be transmitted or reprinted only with due acknowledgment.

Content
1.

Projects of Delhi Region

3.

Projects of Southern Region

2.

4.

5.

Projects of Northern Region

Projects of Eastern/North-East Region

Projects of Western Region

1-35

37-59

61-87

89-101

103-124

Upcoming & Built Assests of CPWD

INDIRA PARYAVARAN BHAWAN, NEW DELHI

Indira Paryavaran Bhawan

Plot area

FACT FILE

9565 Sq Mts

Basement area

11826 sqm

Total P.A.

30914 sqm

Super structure

19088 sqm

Project sanc2oned Cost

Rs. 146.14 Crores

Building Structure

RCC framed structure, Ground + Seven storey

Revised Cost
Parking

Central Public Works Department

Rs 198.00 Crores

Mechanized Car parking for 344 ECS in 3 Basement

Upcoming & Built Assests of CPWD

Natural ven5la5on

SALIENT FEATURES

Solar power genera5on

Solar passive envelope


design including walls
& roof insula5on &
fenestra5on

Ecient
electrical
equipment
as per
ECBC
2007
requirements

Waste water recycling


for Cooling Tower

Rain water harves5ng

Geo
thermal
technology for heat
rejec5on of AC system

Building Configura0ons for Natural Ven0la0on

Design temperature : 26 C (S) / 20 C (W)

55% Area will be developed as Landscape area.

79 exis5ng trees on the project site

Retained 45 nos. trees and 11 trees transplanted

Grass Pavers for Pedestrian circula5on to increase the so& area

Site Planning for Op0mum Connec0on with Nature


4

Central Public Works Department

Upcoming & Built Assests of CPWD

FIRST EVER Building in


GOVERNMENT SECTOR
targeted on comple5on,
to be both a 5 STAR
GRIHA and a LEED
Pla5num Rated GREEN
BUILDING.

UNIQUE FEATURES

FIRST EVER Building of


this magnitude (30,914
m plinth area) to be
targeted as NET - ZERO
Energy Demand Building
with
ON-SITE
GENERATION

Front (North) View


FIRST EVER Building in
which en5re RENEWABLE ENERGY GENERATION of this magnitude (900 KWp of Solar PV
Cell system) is being done Wholly ON-SITE (Roo&op and can5levers at terrace and 4th
oor level) with highest eciency Solar Pv Panels.

Highest ever energy savings by a building of its size (55%) Being targeted by any building
in India, against the baseline bench march E.P.I. (Energy Performance Index) as per GRIHA
criterion 14, of 110 KWh/m/year, to a targeted E.P.I. of 50 KWh/m/year.

This is a building having many rare features like - Chilled Beam systemof HVAC, Geo
Thermal Heat Exchange system, Regenera5ve Li&s, Fully Automated Car Parking in
basements with Zero surface parking and features like Bio Diversity Park,etc.

Central Public Works Department

Upcoming & Built Assests of CPWD

NOTABLE FEATURES OF THE BUILDING

Energy Eciency

AC load designed as 450S&/Tr as against 150s&/Tr in conven5onal building

Light Power Density achieved is 5 wa6/sqm as against 11.8 wa6/sqm of ECBC 2007 for
normal building thus saving in energy > 50% over conven5onal building

Electrical load designed as 4.3 W/S& as against 10W/s& in conven5onal building

Low discharge xture are planned thus reducing water demand by approximately 70%
over conven5onal xtures.

Water eciency

Waste water from building is recycled a&er treatment to the extent of 100% use in
irriga5on and HVAC plant.

Emerging Technology used in IPB Project

Automated Car Parking System

Geothermal Heat Exchange System

All the three (3) basements will be used for Automa5c Car Parking system.

1.

Automated Car Parking System

Chilled Beam System

Solar Power Genera5on

Total Capacity is 330 nos. of cars. The following type of system is adopted in this project:

Puzzle Parking System (1st Basement).

Shu6le Dolly System (2nd & 3rd Basement).

Puzzle Parking system (Similar System will be Installed at 1st Basement)


6

Central Public Works Department

Upcoming & Built Assests of CPWD

2.

Chilled Beam System

Chilled Beam Water in Temperature is 16 C and water out temperature is 20 C.

In the IPB project Chilled Beams are being installed in second oor to sixth oor.
Room temperature maintained is 26 1 C.

Chilled Beams with Drain pan are used to drain out water droplets due to condensa5on
during monsoon.
160 TR of air condi5oning load of the Building is met through Chilled Beam system.

Chillded Beams Induc0on Units Overview

A Chillded Beams Installed at Site

3.

Geothermal Heat Exchange System & Solar Power Genera2on

Complete energy genera5on is onsite using 6000sqm area comprising of roo&op and
can5lever por5on provided at fourth oor.

Solar Power plant of 930 kWp being installed with 20% ecient Modules genera5ng 14
lakh units annually, mee5ng annual energy demand of the Building.
This Power Plant is Grid Interac5ve System, Power so generated would be fed to NDMC
Grid at 11kV.
Annual solar energy generated is mee5ng the annual energy demand(14 lakh Unit) of the
Building, hence our target of NET ZERO ENERGY building is achievable.

Geothermal Pipe wort at Site


Central Public Works Department

Solar Panel
7

Upcoming & Built Assests of CPWD

LANDSCAPE DEVELOPMENT

55% Area will be developed as Landscape area.

79 exis5ng trees on the project site

Grass Pavers for Pedestrian circula5on to increase the so& area

Retained 45 nos. trees and 11 trees transplanted

Energy Conserva2on Measures

Overall Design Load op5mized at 800 KW

Energy ecient T-5 and LED Fixtures

High Eciency Solar Panels for Net Zero

Innova5ve Chilled Beam system for cooling

Water cooled chillers, double skin air handling units with variable frequency drives (VFD)

Geo thermal heat exchange for heat rejec5on from Air-condi5oning system

Central Public Works Department

Upcoming & Built Assests of CPWD

JAWAHAR LAL NEHRU BHAWAN, NEW DELHI

Jawaharlal Nehru Bhawan, the headquarters oce building of the Ministry of External
Aairs at Janpath, New Delhi, is a contemporary state-of-the-art building in complete harmony
with its environment and surrounding architecture of Edwin lutyens.

Jawaharlal Nehru Bhawan is the rst ECBC compliant Govt. Building which will have Green
Building Cer5ca5on with LEEDS. The plot of land measuring 7.785 Acres (31,504 sqm.) is
situated on the crossing of Maulana Azad road and Janpath. The total built up area of the
building is 59,475 sqm including basement area 28,075 sqm to accommodate parking and
services such as electric sub sta5on, pump room, DG set etc. The total cost of the project is
apprx. Rs. 232 Cr.

Central Public Works Department

Upcoming & Built Assests of CPWD

The building has


three main blocks
one of three storeys
and two of 5 storeys,
four dis5nct zones,
with
separate
entrances but interconnected through
corridors
and
courtyards.

10

Central Public Works Department

Upcoming & Built Assests of CPWD

LANDSCAPE FEATURES

Maximizing pervious & green surfaces to almost 60% of site area

Concrete roads around the building instead of black bituminous road for high reectance

Provision of VERTICAL GREEN WALL in landscaped areas

Extensive landscaping, using na5ve plants, in courtyards, terrace gardens & around the
building reduces the ambient temperature around the building

GREEN BUILDING FEATURES

Insula5ng The Building Envelop

Use Of Regional Construc5on Materials

Water And Waste Management

Salient Landscaping Features For A Green


Building

Controls During Construc5on Stage

Natural Light And Ven5la5on In Building


Design
Op5mum External Faade Ligh5ng

Desirable Indoor Air Quality

Integrated Building Management System

E & M Energy Saving Features

Natural Light And Ven2la2on


-

Ample Natural Light In All Common Areas Like Lobbies, Stairs And Li&s

Light Cut Outs In Courtyard To Ensure Natural Light Penetra5ng Both Levels Of Basement.

Glazings In Corridor Walls To Minimize Dependence on Ar5cial Ligh5ng

Central Public Works Department

11

Upcoming & Built Assests of CPWD

Building Envelope

Insula5ng Building Envelope and thus Reducing the AC Load by about 30%.
-

Use Of Cavity Walls With Insula5on

Insulated Double Glass Units For External Glazings.

Over Deck Pu Insula5on Along With Broken Pieces Of Glazed Tiles

Water Management

WATER AND WASTE MANAGEMENT

Use Of Hydro-Pneuma5c Water Distribu5on System

Dual Flushing Cisterns (To Reduce Water Consump5on)

Sensors In Urinals And Water Taps

Use Of Stp Treated Water For Flushing And Irriga5on.

Segrega5on Of Waste During Construc5on

Waste Management
-

Segrega5on Of Waste / Bio-Degradable Waste Generated By End Users Post Occupancy.

E&M Energy Saving Provisions


-

Vrf Air Condi5oning System Using Non Cfc Refrigerants and Heat Recovery Wheel.

Mirror Op5c Fixtures, Cs & Occupancy Sensors.

12

Solar Photo Voltaic (Spv) Panels For Hot Water

All Li&s Are Machine Room Less And Gearless Resul5ng Into 20% Reduc5on In Energy
Consump5on.
Bms System to achieve the Op5miza5on and Monitoring of Resources.

Central Public Works Department

Upcoming & Built Assests of CPWD

FOUR LEVEL CROSSING AT AZADPUR, DELHI

A View of Foot over Bridge on Mall Road / G.T. Karnal Road


Central Public Works Department

13

Upcoming & Built Assests of CPWD

Loca2on

Azadpur Intersec5on is located on Road No 51, Ring Road, Mall Road / G.T. Karnal Road and Mall
Road Ext.
Beneted area

Azadpur Subzi Mandi, Mall Road, Mall Road Extn., Shalimar Bagh, People coming from Haryana,
Himachal, Punjab and going to Airport.
Trac intensity

Peak Hour trac on intersec5on is more than 13,000 PCU per hour.
Technical Details
(i)

Flyover : Flyover has been constructed along the Ring Road and the Road No 51. Main
yover is 630 m long, Dual carriageway of 9 m in each direc5on) with Pre-stressed Box
Girders for superstructure. Flyover was completed and opened to trac on 13th
November 2009.

(ii) Underpass : An underpass has been constructed along Mall Road and the G. T. Karnal
Road. Underpass along the G. T. Karnal Road - Mall Road is 530 m, long with Dual
carriageway of 9m in each direc5on, 5m wide central verge to accommodate piers of
Metro track and 50m covered por5on at the intersec5on. One carriageway of Underpass
for trac coming from Model Town, Delhi University and going towards Mukarba Chowk,
Karnal was opened to trac on 30/01/2010. Second carriageway of underpass for trac
coming from Karnal, Mukarba Chowk and going towards Model Town, University is opened
on 28/02/2010.
(iii) Foot Over Bridge : FOB have been provided to facilitate pedestrian movement of Mall
Road, GTK Road and Azadpur Metro Sta5on.

FACT FILE

Total Cost of Project

Rs. 153.61 Crore

Date of Comple2on

April, 2010

Date of start

14

May, 2007

Central Public Works Department

Upcoming & Built Assests of CPWD

UNDER PASS ON OUTER RING ROAD AT


JWALA HERI!BHERA ENCLAVE INTERSECTION

Loca2on :

The intersec5on at Jwala Heri Bhera Enclave on Outer Ring Road No. 26.
Beneted area :

This four arm intersec5on consists of Road to Jwala Heri, Bhera Enclave and Outer Ring Road
acts as a major link between residen5al areas like Paschim Vihar, Vikaspuri, Janakpuri and
residen5al cum commercial areas of Rohini, Mukarba Chowk.
Trac intensity :

Peak Hour trac on intersec5on is more than 10,000 PCU per hour.

Technical Details :

6 lane- 500 m long Underpass along the Outer Ring Road.

Central Public Works Department

15

Upcoming & Built Assests of CPWD

Surface Level Rotary with two covered por5ons in Voided slab of size 23.6m x 20.6m

Minimum 9 m wide Slip Roads at surface level for le& and right turning trac and Service
roads.

2 Foot Over Bridges with ramps with Escalators and footpath for safe movement of
pedestrians, elderly and disabled persons.

A View through Underpass at Jwala Heri-Bhera Enclave

FACT FILE

Total cost of Project

Rs 54.66 Cr

Date of comple2on

June 2009

Date of Start

16

August 2007

Central Public Works Department

Upcoming & Built Assests of CPWD

CONSTRUCTION OF ELEVATED ROAD BARAPULLA


PHASE ! I

Loca2on : Ring Road Sarai Kala Kha to JLN Stadium

Beneted area : Central Delhi, East Delhi, South Delhi

Trac intensity : Peak Hour trac on intersec5on is more than 50,000 PCU per hour.

View at Lala Lajpat Rai Road


Central Public Works Department

17

Upcoming & Built Assests of CPWD

Technical Details : 9m two carriage way 4.25 km length

Elevated Corridor with segmental construc5on technology with 16 balance can5lever


construc5on with precast segmental technology of 84.5m span and 74 m span crossing Ring
Road at Sarai Kala Kha Railway at Nizamudin, Barapulla at Nizamudin, Mathura Road and Lala
Lajpat Rai Marg, voided integrated slab, loop at Sarai Kala Kha and two connec5vi5es at Lala
Lajpat Rai Road CGO complex, Nizamudin, Ashram

Night view from CGO Complex

FACT FILE

Total cost of Project

Rs 549 Cr

Date of comple2on

November 2010

Date of Start

18

September 2008

Central Public Works Department

Upcoming & Built Assests of CPWD

MULTI FACILITY GRADE SEPARATOR ON


GT KARNAL ROAD NH!1 ! OUTER RING ROAD
INTERSECTION AT MUKARBA CHOWK, DELHI

Loca2on :

Intersec5on on Outer Ring Road and road crossing Mall Road Extn. / GTK Road to NH-1.
Beneted area :

People coming from / going to North Indian States of Haryana, Punjab, Himachal Pardesh and
Jammu & Kashmir and trac coming from Rohini / Pitampura, Narela, Asia,s biggest Subzi
Mandi at Azadpur, Sanjay Gandhi Transport Nagar.
Trac intensity :

Average daily trac was 2,36,000 vehicles per day , equivalent to 3,30,000 PCU per day in year
1999.
Central Public Works Department

19

Upcoming & Built Assests of CPWD

Technical Details :

Signal Free intersec5on with complete segrega5on of Motor Vehicles, Non-Motorized Vehicles,
Cyclist and pedestrians in all direc5ons.

1060 m long Flyover on Road No. 26(Outer Ring Road) and NH-1 Bye Pass with divided
carriageway with 4 lanes (14 m wide) in both direc5ons, 218 m viaduct in composite steel
structure.
Surface level road along GT Karnal Road- NH-1 Grade with divided carriageway with 4
lanes (14 m wide) in both direc5ons.
Four Slip Roads for le& turns with three lane carriageways (9 m each) on Voided Slab/RCC
Box/RE wall/embankment.

Main Flyover from Azadpur End

Length of Slip Road :


-

620 RM

680 RM

ISBT to Azadpur

828 RM

ISBT to Karnal

500 RM

Rohini to Azadpur

540 RM

Karnal to ISBT

680 RM

Four cloverleaves for right turns with three lane carriageways (9 m each) on Voided Slab.
-

Azadpur to ISBT

Karnal to Rohini

20

Rohini to Karnal

Azadpur to Rohini

460 RM

550 RM
Central Public Works Department

Upcoming & Built Assests of CPWD

4m wide cycle track cum footpath for cyclist, NMV and pedestrian movement - Length of
cycle track = 3000 m
Ramps, Staircase, Li&s and Escalators for Pedestrian movement from surface level to
Flyover.

Subway to facilitate crossing of Road at Flyover and surface level for pedestrians and
cyclists.

PHOTOGRAPHS OF COMPLETED WORKS

View of Li" and Ramp for pedestrian from flyover to at Grade Level

FACT FILE

Total cost of Project

Rs 214.48 Cr

Date of comple2on

September 2009

Date of Start

Central Public Works Department

October 2006

21

Upcoming & Built Assests of CPWD

OFFICE BUILDING NATIONAL INSTITUTE OF


SOCIAL DEFENCE AT G!2, SECTOR !10,
DWARKA, NEW DELHI.

Introduc2on :

It is a oce
building for training,
research
and
development ac5vi5es
and conduc5ng long
and short term courses
in the eld of Social
Defence. (Basement
and G + 6 structure)

Site Plan
22

Central Public Works Department

Upcoming & Built Assests of CPWD

Plot Area

: 8096.0 Sqm

Permissible

Proposed ground : 1911.25 Sq mtr

ground coverage
coverage

: 30%

(23.61%)

Permissible FAR

: 16192.00 Sq mtr.

Proposed FAR

: 9790.75 Sq mtr.

Total covd. Area

: 9790.75 Sq. mtr.

Parking required : 176 ECS

on all oors

(FAR 2.0)

(FAR 1.209)

Parking provided : 206 ECS


Es5mate cost

: Rs 23,61,95,000/-

Rain Water Harves5ng Pit Provide.

GROUND FLOOR PLAN

FRONT ELEVATION

Central Public Works Department

23

Upcoming & Built Assests of CPWD

OFFICE BUILDING FOR NCTE AT PLOT NO. G!7,


SECTOR $ 10, DWARKA, NEW DELHI

Introduc2on :

The Oce building of Na5onal Council for Teacher Educa5on coordinate development of
the teacher educa5on system throughout the country, the regula5on and proper maintenance
of Norms and Standards in teacher educa5on system and for ma6ers connected there with. (G
+ 4 storey structure)

Site Plan
24

Central Public Works Department

Upcoming & Built Assests of CPWD

GROUND FLOOR PLAN

Plot Area

Permissible ground coverage


Proposed ground coverage
Permissible FAR

Proposed FAR

Total covd. Area on all oors


including Basement

FACT FILE

4047.75 Sqm

30% (1214.32 Sq mtr.)

1078.38 Sq mtr (26.64%)

8095.50 Sq mtr. (FAR 2.0)

6087.94Sq mtr. (FAR 1.50)

8434.784 Sq. mtr.

Parking required

110 ECS

Es5mate cost

Rs 20,50,98,202/-

Parking provided
Rain Water Harves5ng Pit Provide

Central Public Works Department

111 ECS

25

Upcoming & Built Assests of CPWD

COMPOSITE STRUCTURE FOR 52!SAG,NSG AT


SAMALKHA, NEW DELHI

Introduc2on :

Composite
structure,
consis5ng
of
barracks for 600
jawans, quarter
guard,
store
block
&
Administra5ve
Wing.
The
Quarter guard
and Admin wing
(Which serves as
the
most
important part of
a ba6alion) is at the central part of the composite structure & is separately accessible. barracks
accommoda5ng 600 jawans situated on the both side of the central part (Quarter guard &
admin building).
26

Central Public Works Department

Upcoming & Built Assests of CPWD

Plot Area

: The site is in NSG campus of plot area= 97,181.99 Sqm

Development norms as per MCD approval dated 28-10-2008


APPORTIONMENT OF THE TOTAL AREA
RESIDENTIAL

= 24295.50 SQM (25% OF NET AREA)

SPORTS & CULTURAL

= 14577.30 SQM (15% OF NET AREA)

ACADEMIC & ADMINISTRATION

= 43731.90 SQM (45% OF NET AREA)

PARKS AND LANDSCAPE

= 14577.30SQM (15% OF NET AREA)

Covd. Area on ground oor

: 3,950 Sqm

Parking required @ 1.33 ECS

= 213 ECS

The proposed building is G +4 storey structure in the plot area for Academic & Administra5ve
use.
Total covd. Area on all oors
per 100 SQM

: 16,035 Sqm

Parking provided = 215 ECS in open 7,85,700

Le& Side of the plot is for residen5al use and right side is for acadmic use, Central Part is for
Sports and Cultural Ac5vi5es

GROUND FLOOR PLAN

Central Public Works Department

27

Upcoming & Built Assests of CPWD

PROPOSED OFFICE BUILDING FOR DOEACC


SOCIETY NOW AS NATIONAL INSTITUTE OF
ELECTRONICS AND INFORMATION TECHNOLOGY
%NIELIT& AT SECTOR!8, DWARKA, NEW DELHI

Introduc2on :

A Headquarter Building of
NIELIT (An Autonomous Body
under the administra5ve
control of Department of
Electronics and Informa5on
Technology) having ve main
wings : Administra5ve wing,
Finance wing, Educa5on wing,
Training (Technical wing), Policy
Planning and Implementa5on.
(G+4 storey structure with
double basement)

28

Site Plan

Central Public Works Department

Upcoming & Built Assests of CPWD

Plot Area

: 4277.88 Sqm

Permissible Ground Coverage

= 30% = 1283.36 SQM

Permissible FAR

= 120= 5133.456 SQM

Development Norms :

Proposed Ground Coverage


Proposed FAR

Parking required @2 ECAS


per 100 SQM

= 1173.114 SQM= 27.42%


= 5127.06 SQM= 119.85
= 103 ECS

Parking provided

= 107 ECS (98 IN Basements and 9 in open surface)

Total covd. Area on all oors

: 9,860 Sqm

P.E. Cost

: Rs 54,18,00,500.

Sewage Treatment Plant is provided in basement and Rain Water Harves5ng near the main
entry to the plot.

including basements

GROUND FLOOR PLAN


Central Public Works Department

29

Upcoming & Built Assests of CPWD

OFFICE BUILDING FOR STPI AT EPI PARK,


GREATER NOIDA, %UP&

Introduc2on :

Small size of the plot


necessitated
u5liza5on
of
maximum permissible FAR with
permissible ht. up to 18.0m only.
Thus, the building has been
designed as S5lt + 3 oors, with
Basement for parking and building
services. The Main Entrance to the
building is the focal point and has
been located centrally. The four
wings of oce spaces have been
planned on four ends with central
axis as service core to avoid long
corridors.
Oce Building (basement, s5lt + 3
orey structure)

30

Site Plan
Central Public Works Department

Upcoming & Built Assests of CPWD

Plot Area

: 3780.52 Sqm

Permissible Ground Coverage

= 40% = 1512.20 SQM

Permissible FAR

= 125= 4725.65 SQM

Development Norms :

Proposed Ground Coverage


Proposed FAR

Parking required @ 1 ECAS


per 66 SQM

= 1491.5 SQM= 39.45%

= 4724.50 SQM= 124.96


= 72 ECS

Parking provided

= 81 ECS (36 in Basements and 46 on s5lt oor.

Total covd. Area on all oors

: 6,703 Sqm

P.E. Cost

: Rs 35,83,25,400.

Sewage Treatment Plant is provided in basement and Rain Water Harves5ng near the main
entry to the plot.

including basements

Typical Floor Plan


Central Public Works Department

31

Upcoming & Built Assests of CPWD

PROPOSED MULTISTORIED FLATS FOR


MPs OF RAJYA SABHA AT 2, TALKATORA ROAD,
NEW DELHI

A Perspec0ve View
Introduc2on :

A Bungalow plot at 2 Talkatora road


has been allo6ed to Rajya Sabha by MOUD
for the construc5on of type VII ats for the
MPS of Rajya Sabha. The plot is located
between the Nurses Hostel and SWAJAS
(Swarn Jayan5 Sadan) Mul5 storied Flats
having an area of 2646.68 sqm. with
frontage on Talkatora Road.

The area did not fulll the essen5al


minimum requirement of Group Housing
plot of 3000 Sqm as per the Master plan
2021. Therefore it was decided in consulta5on with NDMC, DDA and L&DO to amalgamate the
plot of 2, Talkatora road with SWAJAS (24854.65sqm) and the exis5ng Service Road
(1105 sqm.).
32

Central Public Works Department

Upcoming & Built Assests of CPWD

Requirements :

Chairman, Rajya Sabha House Commi6ee, projected the requirement for the ats for Rajya
sabha. Each at should should provide for:
i)

ii)

4 spacious Bed rooms with a6ached Toilets


Drawing room, Study (Oce space)

iii) Modular Kitchen, Dining, Family Lounge

iv) Mul5purpose space for holding func5ons & other ac5vi5es on the ground oor.
V)

Each at shall have two servant quarters.

Proposal

The plot at 2 Talkatora Road has been amalgamated with the exis5ng Housing complex
SWAJAS which has three blocks (G+7) having 84 ats and three four storied servant blocks
housing 168 servant quarters, to accommodate an addi5onal (G+7) block having 14 ats and
28 servant quarters.
Design Concept

The required ats are proposed in a Ground + seven storied Y shaped block, to match
with the congura5on & height of the exis5ng building blocks of the SWAJAS housing
complex.
It has been located in harmony with other building blocks without upse7ng the internal
road network, services and exis5ng landscape.

Central Public Works Department

33

Upcoming & Built Assests of CPWD

Typical Unit Detail

34

The exis5ng entrance to the


SWAJAS shall be used for the en5re
complex keeping in mind the
security of the MPs.

The service core has been placed in


such a manner that it not only
segregates the MPS ats and
servants quarters but also provide
an easy access to both the at
owners and the servants in a
cohesive manner.
An eort has been made to design
an apartment sui5ng the func5onal
requirements of the Rajya Sabha
MPs in terms of privacy,
representa5on needs etc.

Typical Floor Plan

All the internal spaces in the at


have been arranged strategically to achieve the maximum eciency and to reduce the
circula5on area to the minimum extent possible.

Central Public Works Department

Upcoming & Built Assests of CPWD

Con5nuous balconies, apart


from being the sit out place,
provide easy access to the
pipe sha&s for servicing.
These balconies also cut the
direct sunrays falling on the
windows and the external
walls thus reducing the load
on Air condi5oners.

The proposed construc5on an


extension of the construc5on,
Drawing Cum Dining -An Interior View
exis5ng housing complex
(SWAJAS), enjoys the exis5ng infrastructure like open landscaped spaces parking etc An
addi5onal parking of 42 spaces, parking, etc. ECS has been provided @ 3ECS per at.

Plot Area

Permissible Ground Coverage


Exis2ng Ground coverage

Proposed Ground Coverage

FACT FILE

27895.58 Sqm

9297.59 Sqm.33.33%
4338.29 Sqm
913.05 Sqm

Total Ground Coverage

5251.35 Sqm-18.82%

Exis2ng area on all oors

29743.96 Sqm

Permissible FAR @200

55791.16 Sqm

Proposed area on all oors

6430.53 Sqm

Exis2ng Parking @1.33 ECS/100sqm

354 ECS

Total FAR

Proposed Parking @ 3 ECS/at

36174.49 Sqm 129.67


42 ECS

Master Bed RoomAn Interior View


Central Public Works Department

35

Upcoming & of
Built
AssestsBuildings
of CPWD
Handbook of Conservation
Heritage

AMBEDKAR BHAWAN AT BABA SAHEB BHIMRAO


AMBEDKAR UNIVERSITY, LUCKNOW

DESIGN CRITERIA : Circular form with minimum surface area and maximum volume to increase
eciency of building reducing the heat gain. Use of smart shading device with sandwiched
solar cell lamina5on. Rainwater harves5ng and recycling treated water. Use of reec5ve
external paint for energy eciency.
SPACE ECONOMICS : Radial grid to
obtain circular sectoral spaces
developed base on the space
requirement module (srm) i.e.
Requirement frac5on works out to be
common mul5ple of various space
requirements in sqm.

METHODOLOGY AND GEOMETRY


ADOPTED : Radius r is a self
determined/ xed distance. Here taken
as 19.0 m for easement of light and
ven5la5on to the inner core.
(Maximum depth permi6ed w.r.t. Bye
laws for ven5la5on is 7.0 m plus 3.0 m
corridor leaves 9.0 m inner radius open
to sky for ven5la5on and light to the
inner core)
Central Public Works Department

39

Upcoming of
Handbook
& Conservation
Built Assests of
of CPWD
Heritage Buildings

MODULATION FOR EASEMENT OF DESIGN


AND CONSTRUCTION : 3 nos similar sector
modules rotated on circle with services
consolidated for each sector. Services
include staircase, li& lobby, electrical sha&,
wet riser, AHU, toilets etc. AC plant room
and ltra5on plant room has been
accommodated in a separate structure away
from the main building to segregate
dierent ac5vi5es.

USE OF EDGE OF THE TECHNOLOGY


MATERIAL : Mul5cell polycarbonate sheet
Floor Plan
with photovoltaic cell layer sandwiched has
been proposed as shading device as well as
for energy produc5on. (Electricity produc5on of solar panel = 1kw / sqm / hour
Area covered with solar panel = 6000 sqm

At 50% eciency electricity produc5on is es5mated to be 3000kw / hour )

Front Eleva0on

Category

EDUCATIONAL

Cost

Rs. 3800 Lac

Name of Work

Area of the plot


Plinth Area

Number of oors
40

FACT FILE

AMBEDKAR BHAWAN (ACADEMIC BUILDING) FOR BABASAHEB


BHIMRAO AMBEDKAR UNIVERSITY, LUCKNOW
24552.00 SQM (AREA OF CAMPUS = 1021960.00 SQM)

7255.00 SQM
G+4

Central Public Works Department

Upcoming & of
Built
AssestsBuildings
of CPWD
Handbook of Conservation
Heritage

PROPOSED VIEWING GALLERY AT THE BSF JCP


AT ATTARI, AMRITSAR
Indias famous A6ari-Wagah Interna5onal border joint check post is located about 26 K.M.
from Amritsar. Half an hour joint retreat ceremony is held by India and Pakistan at this joint
check post every day. In addi5on number of Interna5onal mee5ngs between BSF and Pakistan
Rangers are held in the exis5ng conference hall at this check post. The JCP A6ari also func5ons
as COY headquarter and BOP of the Border Security Force. The area witnesses thousands of
daily visitors. BSF proposes to demolish the exi5ng viewing gallery and other opera5onal
buildings and construct a much larger viewing gallery for the visitors with the related
opera5onal requirements and other facili5es.

The proposed Viewing Gallery has been planned in U-shape within the available limits of
land with focus of ac5vity being the Na5onal Flags of two countries at the entry gates at the
Interna5onal border and the central road leading to the zero line. The Gallery has two levels
i.e. main level and a balcony (total capacity about 13000 visitors) on both sides of the road
with the balcony forming a U-shape above the road.

The related opera5onal requirements and other facili5es are accommodated by u5lizing
the space below
the sea5ng 5ers.
The architectural
character of the
gallery
draws
inspira5on from
the architecture of
Punjab, which is
reected through
elements such as
piers,
domes,
chajjas,
arches,
cornices and jallies
etc. The external
colour scheme is
proposed in shade
of dholpur stone with accentua5ons in shade of red sandstone.

The conceptual proposal has been approved by the Ministry of Home Aairs and the
expenditure sanc5on for Rs. 23.987 crore (23,98,32,274/-) has been issued. Tenders have
already been called and the project is scheduled to be completed within 20 months a&er start
of construc5on.
Central Public Works Department

41

Upcoming & Built Assests of CPWD

PROPOSED HOSTEL FOR TRAINEES AT


LBSNAA, MUSSOORIE

The site is located on the top of the hill in the recently aquired
(Monastry Estate) overlooking the Academy. This hostel will cater to the ever increasing
trainees at the LBSNAA.

Keeping in view the prominant loca5on and the built form in Mussoorie and the Academy
the sloping roof and some features have been adopted from the surrounding buildings
and Koteshwar Castle.

The interiors shall be modern keeping in view the status and rank of the IAS and other trainees.
To reduce heat loss during the cold season a brick cavity wall g y 230+50+115 along with
herma5cally sealed double glazed window panes has been proposed.

Another feature of this building is that no vehicular approach shall be provided only a
jeep-able road has been proposed. This building will be accessed by a pedestrian footpath
or a li& from the parking area.

Front Eleva2on

Front Eleva0on
42

Central Public Works Department

Upcoming & Built Assests of CPWD

Side View

FLOOR PLAN

Upper Ground Floor at Lvl 129


Rooms / Entrance Lobby.

Status

Cost

Specs

First/ Floor at Lvl 132/135


Rooms / Common Room.

FACT FILE

NIT stage. Environmental Clearance received from MoEF.

22 (Crores approx)
Hostel Twin Sharing for 200 Trainees.

Cavity Wall.(230-50-115). Herma5calLy sealed double glazed window


panes.
Central Hea5ng.

Central Public Works Department

43

Upcoming & Built Assests of CPWD

600 SEATED GIRLS HOSTEL


N.I.T KURUKSHETRA

The Proposed design is made for 600 bedded (single room) Girls Hostel in the campus of
NIT Kurukshetra. It has been designed for G+5 storied having plinth area 21480 Sq. Meter.

The passive Green Building Measures have been taken into account. The longer side of the
building is oriented N and S and shorter side E & W. Central court yard has been u5lized for
dining and recrea5on, so as to save the ground coverage as well as the oor area to
accommodate the required size of dining and recrea5on.

Similarly the roof of the dining


and recrea5ons are connected from
four wings which can be used for
social ac5vi5es, get together and
other open recrea5onal ac5vi5es
Number of dome covered with
polycarbonate sheet are suitably
located over dining and recrea5on
to get the day light from the top.
The dining and recrea5on have
been divided in three separate
spaces but in case of big gatherings
it can be made a single hall by
44

Central Public Works Department

Upcoming & Built Assests of CPWD

Ground Floor Plan

Typical Floor Plan

sliding all the doors and par55ons. Sha& has been put in the toilet in such a way that all the
WC and bath rooms are directly against its walls, so as to reduce the length of connec5ng pipes.
No sunken oor has been provided, all the pipes beneath the oors will be covered with
aluminum grills. with main holes so as to a6end the faults as and when required.

External balconies are given SS railing above the parapet to provide privacy and safety to
the girls. The ver5cal walls of li& walls facing inside the courtyard will be provided with mo5fs
with murals.

FACT FILE

Catagory

Residen5al

Cost

Rs. 35,82,63,000/-

Plinth area

21480 Sq. Meter.

Name of the Work 600 Seater Girls Hostel at NIT, Kurukshetra


Area of the plot

Number of Floors

14303 Sq. Meter (part of campus).

G+5

Central Public Works Department

45

Upcoming & Built Assests of CPWD

PROPOSED OFFICE BUILDING FOR


STPI, AMRITSAR

PLANNING ANALYSIS AND CONCEPT

So&ware Technology Parks of India under department of Electronics and Informa5on


technology, Ministry of communica5ons and IT was set up for IT/ITES units across the India. To
establish STPI Amritsar building is one of the ini5a5ves by STPI to cater to entrepreneurs in
Punjab area for which the
local Punjab Government
allo6ed 2.72 acre plot at
focal point Amritsar. As
per policy of STPI for TIERIII ci5es the maximum
built up area is 38250 sq&.
comprising of Data center,
Incuba5on facili5es are to
be created. This building
envelope was conceived
on fast track basis as a
state of art four storyed,
green ra5ng and energy.
ecient
building
46

Central Public Works Department

Upcoming & Built Assests of CPWD

comprising of single small basement meant for services along with ground and three oors
the maximum built up area is 38250 sq&. comprising of Data center, Incuba5on facili5es are
to be created. This building envelope was conceived on fast track basis as a state of art four
storyed, green ra5ng and energy ecient building comprising of single small basement meant
for services along with ground and three oors.

maximum built up area is 38250 sq&. comprising of Data center, Incuba5on facili5es are to be
created. This building envelope was conceived on fast track basis as a state of art four storyed,
green ra5ng and energy ecient building comprising of single small basement meant for
services along with ground and three oors.
PLANNING & ARCHITECTURAL CONCEPT

The ecient longer oor plates have been judiciously planned on the north side having
stepped landscape terraces to get shaded natural glare free day light in the core working areas.
To induce natural light the solar tubes will be introduced wherever direct day light is not
possible to have energy eciency. The service core has been kept on the south side with
architectural element as ver5cal wall ns ac5ng as a shading device to reduce the heat intake.
At front a double height lobby with insulated double glass glazing has been provided. The
building is envisaged with less fenestra5on considering the clima5c condi5ons and insulated
data center is planned for minimum heat gain and security.
SPACE ANALYSIS
1.

Service Core to South Side to Reduce Heat Intake.

3.

Core Segregated by Acces Control.

2.

4.

Dened Entry and Access in Planning.


Double Height Lobby

Ground Floor Plan


Central Public Works Department

47

Upcoming & Built Assests of CPWD

SPACE ANALYSIS
1.

Placement of Core as on One Side Gives Clean Floor Plate for Use.

3.

Guest Rooms Placed to the Front of the Buiding to Enhance Living Experience and
Segrega5on Done from Future Expansion.

2.

Ver5cal Movement Easily Accessible and Visible through the Length of the Floor Plate.

Third Floor Plan

FACT FILE

Catagory

Oce Building

Area of the plot

2.72 ACRES (11036 Sq.m )

Number of Floors

G+3

Name of the Work


Plinth area

48

Oce Building for STPI, Amritsar.


3538 Sq. Meter

Central Public Works Department

Upcoming & Built Assests of CPWD

PROPOSED B TYPE KENDRIYA VIDYALAYA


%TO BE UPGRADED TO C TYPE&
AT VILLAGE GAJJAN, BHUNGA, HOSHIARPUR

Kendriya Vidyalaya Sangathan is one of the esteemed Client of CPWD. Kendriya Vidyalaya
Sangathan proposes to construct Kendriya Vidyalaya at village Gajjan, Bhunga in District
Hoshiarpur. The proposal includes B type Kendriya Vidyalaya (to be upgraded to C type in
the future) and 11 residences and sports facili5es. The complete design proposal including the
future expansion provision was approvedby the Honble Minister of State, Health and the KVS.

The expenditure sanc5on for Rs. 22.31 crore (22,31,76,000/-) has been issued for the B
type School building and a separate sanc5on has been issued for boundary wall in the rst
phase.The construc5on for the Boundary wall has started. The school building work is at tender
stage and is scheduled to be completed within 18 months a&er start of construc5on.

The proposed Kendriya Vidyalaya has been planned as a conglomera5on of an


administra5ve block,two self contained blocks of classrooms with central courtyard keeping in
mind the students of dierent age groups and a central block having common facili5es and
laboratories etc. The provision for cycle parking for students, bus parking, visitors parking,
sports facili5es, canteen, play areas, jogging track, sports facili5es, open air performance area,
Central Public Works Department

49

Upcoming & Built Assests of CPWD

ESS and STP etc. has been made in the proposal. The architectural character of the school
draws inspira5on from the architecture of Punjab, which is reected through elements such as
piers, domes, chajjas, arches and jallies etc. The external colour scheme is proposed in exterior
texture paint in shade of dholpur stone with accentua5ons in shade of red sandstone. The red
sandstone has been proposed up to window cill level and in the porch / area.

50

Central Public Works Department

Upcoming & Built Assests of CPWD

GOS MESS, CISF, BEHROR %RAJASTHAN&


%COMPLETED&

CONCEPT :

The proposed building is ocers Mess for CISF at Anantpur, Behror. Salient features of the
building are as under:
The Building incorporates Most of the basic features of a Green Building.

Use of Local material i.e. stone on the external cladding. Dry cladding is proposed.

Cavity wall on the South Side.

Living areas facing North & East Direc5ons.


Ver5cal Louvers on the West Side.
Terrace garden.

Provisions of internal Landscaped courtyards to keep the building cool. It is also proposed
to provide low fountains in the courtyard.

Central Public Works Department

51

Upcoming & Built Assests of CPWD

Solar water hea5ng, photovoltaic cells for common ligh5ng occupancy sensors for the
rooms.
Tinted glass with low U values to be used.

Grass pavers shall be provided in the outside for parking


Local architectural features.

GROUND FLOOR PLANGOS MESS, CISF, BEHROR.

Cost of Building

Covered Area on Ground Floor

Total Covered Area


No. of Floor

52

FACT FILE

654.81 Lacs

1424.60 Sq. Mt.


2842.60 Sq. Mt.
3 Storey

Central Public Works Department

Upcoming & Built Assests of CPWD

HOLIDAY HOME, AJMER, %RAJASTHAN&


%PROPOSED&

PERSPECTIVE VIEW
Introduc2on :

Ajmer being a very popular tourist des5na5on for religious places like dargah, pushkar,
etc., it was always dicult for government ocials to get suitable accomoda5on. The site is
situated in junc5on and near to way to agra gate and jaipur road, and also near to railway
sta5on and dargah.
Proposal :

The proposal is for construc5on of a three storied building.

The main entry has been taken with a lobby and a oce.

The building has a central open landscaped courtyard concept with a corridor moving all
around. a separate lobby has been provided at right side which has barrier free li& along

Central Public Works Department

53

Upcoming & Built Assests of CPWD

PERSPECTIVE VIEW

54

with staircase. the entry to vip suites


is through this lobby. the various
guest rooms and dormitories are
surrounding the central courtyard
through corridor. the lounge
&dining hall with kitchen is at
ground oor. a recrea5on room is
created in rst and second oor. a
central courtyard with double height
arches and over hang balconies add
to the character of rajasthan.

The building has been designed as a


green building to achieve high green
building ra5ng. the external walls
have double walls with cavity. the
windows to have high performance
glass. the windows of rooms are on
recessed covered balconies.

The building which has tradi5onal


stone jalis and jharokhas remind of
the old royal character of rajasthan.

LAYOUT PLANHOLIDAY HOME, AJMER

Eorts have been made to use local building materials and follow tradi5onal architectural
prac5ces.
Central Public Works Department

Upcoming & Built Assests of CPWD

Plot Area

Covered Area on G.F.


Covered Area on F.F.

Covered Area on Second Floor

Total Covered Area on All Floors


Es2mated Cost

FACT FILE

3323.72 Sq.M
990.10 Sq.M

929.80 Sq.M.
929.80 Sq.M.

2849.70 Sq.M.

Rs. 11,59,90,800/-

SECOND FLOOR PLANHOLIDAY HOME, AJMER

Central Public Works Department

55

Upcoming & Built Assests of CPWD

HOLIDAY HOME, UDAIPUR %RAJASTHAN&


%COMPLETED&

Plot Area

FACT FILE

Permissible Ground Coverage

Covered Area On G. F.

Co O . 606. 8 . 6 Covered Area On F.F.

Covered Area On Second Floor 275 54 Sq M


Total Covered Area On All Floors

2973.97 Sq.M
35%

606.18 Sq. M ( 22.26 %)


550.94 Sq.M.

275.54 Sq.M.

1432.66sq.M.

Permissisble Far

1.5

Es2mated Cost

Rs. 4,67,21,600/-

Far Consumed

56

0. 48

Central Public Works Department

Upcoming & Built Assests of CPWD

Proposal

The construc5on of a three storied building following the land prole and the contours of
site site. The main entry has been taken at 93.50 level following the road level and the site
contours. As exis5ng ground rises, the building follows the shape of the ground and extends
onto the exis5ng open spaces in the central landscaped court which is at a level of 100 00 with
100.00 dining and lounge opening on the exis5ng mound.
The building has been designed as a green building to achieve high green building ra5ng
ra5ng. Eorts have been made to use local building materials and follow tradi5onal
architectural prac5ces.

Proposed Accommoda2on
Accommoda2on

Ground Floor

First Floor

Oce/Recep5on

Entrance Hall
Guest Rooms
Vip Suites

Dormitories (4 Beds)
Dining Hall

1
5

Second Floor

Total

--

--

--

--

--

--

--

--

--

--

A6endent

--

--

Linen Store/Store

-1

Kithchen/Pantry
Lobby/Lounge

--

Layout Plan
Central Public Works Department

57

Upcoming & Built Assests of CPWD

GROUND FLOOR PLANHOLIDAY HOME, UDAIPUR

FIRST FLOOR PLANHOLIDAY HOME, UDAIPUR

58

Central Public Works Department

Upcoming & Built Assests of CPWD

Front Eleva0on

Rear Eleva0on

Central Public Works Department

59

Upcoming & Built Assests of CPWD

CHEMICAL ENGINEERING, DEPARTMENT


FOR NIT WARANGAL

SALIENT FEATURES

The Building is designed as Basement+G+6 storied structure with court yard planning for
visual connec5vity and enclosed space planning with following provisions :

Basement oor is provided with


parking as per local body norms and E &
M services. Ground oor consists a
double height entrance hall with 2
passenger li& and one goods li& besides a
wide stair case for easy access to students.
Various laboratories are provided in
ground & rst oors.

The building consists of HOD ,


Commi6ee room,
double heighted
Conference hall, 30 faculty rooms, 4 P.G
Class rooms, 8 U.G Class rooms , P.G
scholars research labs and common
rooms for students from 2nd to 6th oors.
Central Public Works Department

63

Upcoming & Built Assests of CPWD

Basement Floor

Ground Floor

The building is designed with north south orienta5on for maximum light ven5la5on and
thermal comfort. GRIHA parameters are incorporated in the design and specica5ons

Care has been taken to incorporate provisions for dierently abled people at design stage
by providing ramps, railings, exclusive toilets with all provisions.
E & M services , Fire gh5ng requirements like sprinklers in basement, adequate no of
wet risers in all oors , re escape li&, re water tank are provided as per NBC norms.
Brief Descrip2on
1.

2.

64

RCC framed with y ash bricks.

Flooring consis5ng of Granite, vitried 5les. At certain loca5on acid/alkali resistant 5les.
Wooden ooring high pressure laminated plank in conference hall.
Central Public Works Department

Upcoming & Built Assests of CPWD

3.
4.

5.
6.
7.

8.
9.

Doors frames are with second class teakwood and door shu6ers are ush door with
veneering and polishing. Powder coated aluminum windows for the en5re building.
Stainless steel railing for staircase, corridor and ramp for Dierently abled users.

Structural glazing at certain por5on of the building as per the approved architectural
drawing.
Toilets with 1st quality non-skid ceramic 5les and dado with ceramic 5les.
Wall lining with polished granite in the li& lobby.

Internal nishing with plas5c emulsion paint over a surface prepared with applying cement
based pu6y and primer. Outside nishing with textured paint over a coat of cement primer.
Underground water sump water supply & re gh5ng.

10. Sewer lines, external/ internal water supply lines.

11. Electrical 7ngs with re Figh5ng system, pump & accessories.

12. Li&s.

13. Water proong treatment in basement, toilets and on roof slab.


Category

FACT FILE

Educa5onal

Name of the Work for NIT

Chemical Engineering dept. Warangal

Area of the plot

Campus layout

Cost

Plinth Area & No. of oors

Central Public Works Department

6600 lakhs

26000 Sqm- B+G+6 r.

65

Upcoming & Built Assests of CPWD

IIITD&M AT MELAKOTTAIYUR,
KANCHEEPURAM

66

Central Public Works Department

Upcoming & Built Assests of CPWD

Central Public Works Department

67

Upcoming & Built Assests of CPWD

FACT FILE

Category

Non Residen5al Building

Cost

Rs. 14.90 Crores

Name of work

Area of plot

Construc5on of Administra5ve Building and Senate hall for IIITD&M at


Melako6aiyur, Kancheepuram District, Tamil Nadu. SH: Building
por5on including internal water supply sanitary installa5on and
drainage i/c Electrical Installa5ons.

Campus area = 52 acres

Plinth area

4350 sq. metre

No. and type of


quarters

Not applicable

Number of oors

Date of start

Ground plus three ( four oors )

05.10.2011

Date of comple2on 10.03.2014

Salient features

(A) Civil Por2on : The building is (G+3) Storied RCC framed structure with ver5cal extension
of 2 addi5onal oors in future. The building is with RCC framed structure beams covered
with yash brick ller walls. Doors are with second class teak wood frames with ush
shu6ers. Windows are with aluminium frames covered with double glazing. Floors are
with polished / An5que nished granite with pa6ern. Internal walls are nished with
emulsion paint and exterior walls are nished with exterior emulsion paint and wire cut
brick cladding. En5re building is provided with False ceiling in dierent shapes since this
building is provided with centralised A/C. Ground oor entrance is provided with spider
glazing with automa5c sensor type sliding glass shu6ers. All water supply lines are
provided with CPVC and sanitary lines are provided with UPVC pipes. Senate hall is nished
with acous5c treatment with sea5ng arrangement. Water closets, Urinals and wash basins
are provided with sensors for automa5c ushing.

(B) Electrical Por2on : Wiring with modular switches (Make Legrand) with distribu5on
through MCBDBs, rising mains and auto transfer switches Luminaire with electronic
ballasts. Luminaire switching on and o controlled by sensor system comprising mo5on
sensors wall and ceiling mounted for all rooms corridors and toilets. Sensors have facility
for daylight harves5ng also.
The sensors are networkable with cat 6 cables connected to a server with PC clock and
ba6ery back up including sunrise/sunset tracking and automa5c daylight saving
adjustmentsMake (PHILIPS)

68

Central Public Works Department

Upcoming & Built Assests of CPWD

INDIAN MARITIME UNIVERSITY, CHENNAI

Administra0ve Building A Block and B Block


Category

Name of the work


Cost

Area of the plot

FACT FILE

NonResiden5al Building, Administra5ve Building

Construc5on of Administra5ve Building for Indian Mari5me


University, Uthandi, Chennai.
Rs.12.5 Crores

300 Acres

Plinth Area

A Block 1972 Sqm., B Block 2535 Sqm.

Date of Start

16.10.2010

Number of oors
Actual Dt. of
comple2on

A Block Ground + 1 oor, B Block Ground + 2 oors


03.01.2014

Central Public Works Department

69

Upcoming & Built Assests of CPWD

INDIAN MARITIME UNIVERSITY

SALIENT FEATURES

Indian Mari5me University Chennai is being developed in an extent of about 300 acres of
land located along the East Coast Road (ECR) across the Buckingham Canal.

Master plan was prepared by CPWD consis5ng of Administra5ve Building, Academic


Building, Boys Hostel, Girls Hostel with Dining hall and further drawings are under prepara5on
for Vice Chancellors Bungalow and other Residen5al buildings.
Brief History :

The Administra5ve Building consists of Block A and B. Both the blocks are of Special
Dravidian Architecture involving highly skilled sthapathy works especially one big dome in Block
A having dia of 6.00 metre and 5 domes in block B out of which 4 domes of 3.1 metres and
one big dome of 7.90 metres dia. roman owers at top around the building, lotus ower nish
in each and every tall column with gigan5c pedestals in all columns. Further electrical works
of specialised items like centralized AC re gh5ng, re alarm and installa5on of li& etc. were
executed. The total cost of the building is Rs.12.50 crores including electrical installa5ons, li&,
re gh5ng and Centralised A.C.
Total Area : A Block

B Block

A block consists of :

: 1972 Sqm.(Ground + 1 oor)

: 2535 Sqm.(Ground + 2 oors)

Mul5purpose Hall : Capacity 432 persons and Library & Master Computer
Centre.

B Block consists of :

Ocers & Oce room, Directors Room, Controller of Examina5on, Registrar Deputy
Registrar, Finance Ocer, Vice Chancellor and Conference hall.

70

Central Public Works Department

Upcoming & Built Assests of CPWD

UNIVERSITY CAMPUS
AT NAGARJUNA NAGAR, GUNTUR

The Main Entrance gate


for the Acharya Nagarjuna
University campus is
designed to suit local
Buddhist Architecture and
it resembles the Amrava5
Sanchi Stupa and Torana.
This is a Structure with
entry and Exit gates on
both sides and at the
Centre Security cabin. This
is a huge structure of
about 15m height, 42m
width and about 520 sqms
of built-up area.

Central Public Works Department

71

Upcoming & Built Assests of CPWD

Proposed Administra0on Building, Acharaya Nagarjuna University, Guntur, A.P.


Interna2onal Students 'Hostel for 243 Students at Acharya Nagarjuna University Campus,
Nagarjuna Nagar, Guntur

This hostel building provides 81 rooms to accommodate 243 rooms. Each hostel room
caters 3 persons with a6ached toilet & a kitchene6e & a sit out balcony. The total built-up area
is 5550 sqm. and the building is G+2 storied structure with one oor future provision

72

Central Public Works Department

Upcoming & Built Assests of CPWD

TRAINING AND DEVELOPMENT COMPLEX,


SERC, CHENNAI

FACT FILE

Category

Non-Residen5al Building

Cost

Rs. 7 Crores

Name of the Work


Area of the plot
Plinth Area

Number of Floors

No & Type of quarters

Construc5on of Training and development complex for SERC,


Taramani, Chennai.
10,857 sqm

4,624 sqm (or) 49,773 sq&.


G+ 2 (3 Storied)

(for residences)

----

Actual Date of comple5on

31.07.2013

Date of start

Central Public Works Department

09.09.2011

73

Upcoming & Built Assests of CPWD

SALIENT FEAUTURES

Name of work : Construc5on of Training and development Complex (TDC) at SERC , SERC
Campus, Taramani , Chennai. SH: Building por5on including internal W/S,S/I and drainage.

This building is three storeyed RCC framed construc5on (G+2 storeys) having Seminar Hall
and Teaching facili5es at Central por5on and Boys and Girls Hostel rooms with a6ached toilet
for accommoda5ng two occupants in each room.

74

Central Public Works Department

Upcoming & Built Assests of CPWD

INTERNATIONAL CONVENSION CENTRE


HYDERABAD

Requirements :

1.

Conven5on Center capacity 300 par5cipants

3.

Conference Halls/Class rooms gallery type with the capacity of 40 par5cipants.

2.
4.
5.
6.

Two mini halls gallery type with the capacity of 50 to 60 par5cipants.

The conference halls need to have access to support rooms/syndicate rooms/Discussion


rooms.

Facili5es like Cafeteria/refreshment are at two feasible loca5ons and washrooms etc. as
per requirements.
Facili5es for centralized reprographic services and stores for the training materials.

Central Public Works Department

75

Upcoming & Built Assests of CPWD

Concept :

The Interna5onal conven5on Centre has been designed to suit with the Interna5onal
standards and accommodated all the requirements men5oned by the client.

The orienta5on and design of the conven5on centre has been designed based on the physical
features as per exis5ng terrain condi5ons which is prevailing in the proposed site hence natural
condi5ons of boulders & rocks have been protected so as to provide good ambience.
The Ground oor accommodates the total parking requirements and other requirements like
Electrical rooms, Generator, Canteen, central stores etc. The central part accommodates the green
lawns in stepped fashion this is the space which will be used by the Ins5tu5on for discussions and
demonstra5ons of new innova5ons with the rural people.

The rst oor accommodates all the requirements the access is provided through the
ramp for disabled & VIPs, stair case and li&s. The secondary entry has been provided from the
backside for the students to access the class rooms and other facili5es

76

Central Public Works Department

Upcoming & Built Assests of CPWD

GPOA KAVADIGUDA HYDERABAD

Concept

Eorts have been made to make op5mum u5liza5on of space and simultaneously to have
sucient open space all-round the building
A 10 storied (G + 9) high rectangular block of 8 x 6 bays has been envisaged with open
courtyard (Atrium) in the center for natural light and ven5la5on Each bay is of size 7m x 7m
The size of building is about

56m x 42m

Services cores comprising of Li&s, Staircases, Toilets, Sha&s etc., have been designed on
East & West sides

Travel distance to an exit from the farthest point has been maintained within the
prescribed limit i.e. 30m

North and south sides have been slightly made curvilinear and treated with structural
glazing and AL composite panels to have natural light as well as to give modern and
pleasant look

Central Public Works Department

77

Upcoming & Built Assests of CPWD

Floor to oor height has been kept 3.75m for providing central air condi5oning in future

Double basement has been proposed to house 203 cars as well as space for pumps, sumps
and other services etc.

Structural arrangement in the design has been made for AC Plant, AHU etc.

Electrical sub-sta5on is at ground oor and provision of AC plant room on the terrace in
future.
All the oors inclusive of both the basements are connected with Li&s

Arrangement of enclosed staircase and mechanical ven5la5on and extractors have been
made in both the basements

Provision of re li&, enclosed staircase, wet risers, sprinklers have been made from re
safety point of view
Building has been designed as barrier free oce

CFL lamps have been proposed from energy eciency point of view

Solar water for canteen, kitchen, pantry etc.,

78

The building when completed shall be able to house 2100 employees (approx)

Rain water harves5ng has been proposed

Suitable landscape to improve the environment and quality of air

Central Public Works Department

Upcoming & Built Assests of CPWD

Central Public Works Department

79

Upcoming & Built Assests of CPWD

N.F.D.B. RAJENDRANAGAR, HYDERABAD

Concept :

80

Administra5ve building block to be designed in the form of FISH to give symbolic shape to
the building.
Administra5ve block should in front facing the main road.

Hierarchy in the Residen5al Quarters to be maintained. Govt. norms to be adopted for


the type quarters.
Phased manner construc5on should be feasible. Can be taken up in phased manner as
when required and on availability of funds.
Part of Ground Floor on East & West side is on s5lts.

Eastern side s5lt is used for parking and western side having water body to give oa5ng
eect.

Central Public Works Department

Upcoming & Built Assests of CPWD

Entrance to building proposed at two levels :


-

Ground oor for Driven Cars & disabled persons.


First oor for Public entry.

A structural grid of 6m 6m has been adopted for op5mum u5liza5on of space.

Conference hall is proposed on 3rd oor in order to have column free space and addi5onal
height.

Outer shell proposed is combina5on of R.C.C., Stainless Steel, Aluminium composite panel
and glass.
Two number li&s and regular staircase are provided for ver5cal movement.

Central Public Works Department

81

Upcoming & Built Assests of CPWD

First Floor Plan

Second Floor Plan


82

Central Public Works Department

Upcoming & Built Assests of CPWD

Name of the project

FACT FILE

Oce Building & Residen5al Complex for


N.F.D.B. at Rajendranagar, Hyderabad.

Climate Zone in which project is built

Hot and Dry

Plot Area

5.13 acres (20, 760 sqm)

Ins2tu2onal / Residen2al/Oce
Built up Area

Central Public Works Department

Oce cum Residen5al

Oce Area 7, 398.0, Residen5al : 8,956.0

83

Upcoming & Built Assests of CPWD

PROPOSED GENERAL POOL OFFICE


ACCOMMODATION AT KAVADIGUDA,
SECUNDERABAD

84

BRIEF HISTORY

AA & ES amoun5ng to Rs. 49.9 crore was


accorded on 31-03-08
Plot admeasuring 2.108 acres (8532 Sqm)
situated at Kavadiguda, was purchased from
M/s Praga Tools Limited on 11.08.04 (Sale deed)

Land use of the plot was changed from


partly Residen5al / Industrial to Commercial
use for the construc5on of Oce Complex
on 05.07.05
Building plans were submi6ed to MCH on
28.09.05

NOC from Airport Authori5es regarding


building height received on 05.12.05

MCH informed on 06.01.06 that due to


widening of roads 3.2m stretch of land
towards west side and 4.7m towards south
side needs to be surrendered and resubmit
revised drawings accordingly

Proposed Site for General Pool oce


Building at Kavadiguda, Secundrabad

Loca2on Plan (Not to Scale)

Surrendering of land eected the surface


parking adversely. Second basement was
therefore proposed to adjust the eected
parking
Revised drawings submi6ed to MCH on
06.03.06 and Fire Department on 10.03.06

Due to stay on construc5on of


mul5storeyed by the High Court from re
safety, writ pe55on was led by CPWD for
early clearance. NOC by the Fire
Department issued on 16-10-06.

NOC regarding structural stability issued by


MCH on Aug 20007.

Proposed Site for General Pool oce


Building at Kavadiguda, Secundrabad

Loca2on Plan (Not to Scale)

Central Public Works Department

Upcoming & Built Assests of CPWD

CONCEPT :

Eorts have been made to make op5mum u5liza5on of space and simultaneously to have
sucient open space alround the building
A 10 storeyed (G+9) high rectangular block of 8 x 6 bays has been envisaged with open
courtyard (Atrium) in the center for natural light and ven5la5on Each bay is of size 7mx7m
The size of building is about 56m x 42m

Services cores comprising of Li&s, Staircases, Toilets, Sha&s etc., have been designed on
East & West sides

Travel distance to an exit from the farthest point has been maintained within the
prescribed limit i.e. 30m

North and south sides have been slightly


made curvilinear and treated with
structural glazing and AL composite panels
to have natural light as well as to give
modern and pleasant look

Floor to oor height has been kept 3.75m


for providing central air condi5oning in
future
Structural arrangement in the design has
been made for AC Plant, AHU etc.

Double basement has been proposed to


house 203 cars as well as space for
pumps,sumps and other services etc.

Electrical sub-sta5on is at ground oor and


provision of AC plant room on the terrace
in future.

Central Public Works Department

85

Upcoming & Built Assests of CPWD

Floor Plan

Typical Floor Plan

All the oors inclusive of both the basements are connected with Li&s

Provision of re li&, enclosed staircase, wet risers, sprinklers have been made from re
safety point of view

Arrangement of enclosed staircase and mechanical ven5la5on and extractors have been
made in both the basements

Building has been designed as barrier free oce

CFL lamps have been proposed from energy eciency point of view

Solar water for canteen, kitchen, pantry etc.,

The building when completed shall be able to house 2100 employees (approx)

Rain water harves5ng has been proposed

Suitable landscape to improve the environment and quality of air

Sec0on through Ramp X-X


86

Central Public Works Department

Upcoming & Built Assests of CPWD

Right Side Eleva0on

Total Plot Area

Area eected in road widening


Net Plot Area

Height of Building (G + 9)
Floor to oor height

Central Public Works Department

FACT FILE

8532.44 Sqm

(-) 746.57 Sqm


7785.87 Sqm

38.95 m
3.75 m

87

Upcoming & Built Assests of CPWD

NIT DURGAPUR

This Academy building consis5ng of 4


Nos. 150 capacity class roos, 6 nos 75
capacity
class
rooms,
library,
Administra5ve oce, canteen, server,
faculty rooms etc.; have been designed
in two blocks, inter connected at upper
level allowing a main through fare in
between & 3 Nos exis5ng Sal trees at
the center crea5ng an open greenery &
u5lizing & saving the exi5ng natural
resources.

Central Public Works Department

91

Upcoming & Built Assests of CPWD

1500 CAPACITY AUDITORIUM

SALIENT FEATURES OF THE AUDITORIUM :

Ground+1, Centrally Air-Condi5oned Auditorium following the Site Prole, Orienta5on &
Surrounding Landscape.

92

Main Entry is through Cable Suspended Glass Canopy & Double Level Foyers Connected
with External & Internal Staircase.

The building has been designed as a carrier free building with entrance ramps to Foyer
with barrier free standard as well as side entry ramp to reach the Front Row Seats Of The
Auditorium, Reserved For The Wheel Chaired Persons. Green Building Norms Like Usage
Of High Uv Resistent Glass Faade, Recessed Window Openings, Usage Of Energy Ecient
Fi7ngs, Water Saving Toilet Fi7ngs Etc Have Been Incorporated As Salient Features Of
The Building.

To Make the External Features Aesthe5cally Expressive & To Conglomerate With the
Surrounding Buildings of Guest House, Academy Blocks, Structural Glazing, Acp External
Cladding, Modular Ss Railing, Impressive Color Scheme has been adopted.

Interior has been designed with proper layout of Seats Maintaining Proper Slope & Angle
to facilitate the audience with perfect viewing of stage performance & projection screen.
Acoustic False Ceiling with Mineral Fiber, Carpet Flooring, Wall Acoustic Panelling &
Sound Proof Door have been Provided to Enable the Audience with Proper Audibility.

The Curved Glass Walls With Its Imposing Canopy, Will Give A Invi5ng Eect To The People.

Central Public Works Department

Upcoming & Built Assests of CPWD

1250 CAPACITY BOYS HOSTEL

An example of the fusion of structure with the organiza5on of space, light , ven5la5on and
so& landscape.

All circula5on around central green.

Modern faade treatment with mul5-wall polycarbonate with high NRC value.

Punches on the faade allows the North-South wind ow across the court-yard.
Centralized dining facility at ground oor with the kitchen protruded out from the building
envelop.
Recrea5on & ac5vity at the top oor.

Central Public Works Department

93

Upcoming & Built Assests of CPWD

500 SEATED GIRLS HOSTEL

500 seated Girls hostel is a four storied building having 167 nos triple bedded rooms. The
building has a future provision of two more oors. Besides three bedded rooms the building
contains a dining hall/ kitchen & recrea5on hall to cater to more than 500 students. It also has
spacious lounges at all oors.

The building has been oriented to avoid the harsh east & west sun. It contains two separate
blocks around internal courtyards. It is equipped with four nos li&s and two staircases.
This building has been
designed with an organic Helical
shape to avoid cu7ng down of
exis5ng Sal trees as per the site
condi5on. This organic shape of
the plan creates dierent
interes5ng nega5ve spaces which
add to the avor in form of
Garden, Greenery, waterbody,
fountain, outdoor si7ng areas,
out-door restaurant etc. The
double height Atrium, Glass
Capsule li&, Curtain Glazing gives
a sophis5cated feeling of modern
star hotel entrance.
94

GUEST HOUSE

Central Public Works Department

Upcoming & Built Assests of CPWD

CHEMISTRY & BIOCHEMISTRY LAB

The chemistry & Biotechnology lab building at NIT Durgapur primarily contains the
chemistry & Biotechnology labs for the UG, PG, Research scholars. It also contains other
support areas like HOD room, Conference room and a number of faculty rooms. It is a G+4
(ve storied) building planned on a severe land constraint. Also special care was taken while
planning, not to fell the exis5ng trees at site. An internal one side open courtyard was created
to save one full grown tree right at the center of the site.The building planning is very
streamlined, completely barrier free and contemporary. Finishes such as ACP, Structural
Glazing, Glass canopy & Spider n glazing have been used to render the modern. The building
is par5ally air-condi5oned.

Central Public Works Department

95

Upcoming & Built Assests of CPWD

EXTENSION CAMPUS OF THE INDIAN INSTITUTE


OF TECHNOLOGY, KHARAGPUR AT NEW TOWN,
RAJARHAT, KOLKATA
An Extension campus of The Indian
Ins5tute of Technology, Kharagpur at New
Town, Rajarhat, Kolkata consis5ng of
Research & Developmental ac5vi5es
Advanced Na5onal Mission Laboratories &
Incuba5on programmes Residen5al
Accommoda5on for Research scholars &
faculty members.

A composite research Laboratory


building cum Guest house and a 500
capacity auditorium .The building will be a
Griha 4 star rated building.The building has
been integrated with a plaza, which acts
as a central breathing space as well as an
extended gathering place for dierent
ac5vi5es of the laboratory building.

96

Central Public Works Department

Upcoming & Built Assests of CPWD

INTEGRATED COLLABORATIVE CENTER

R&D-Admin-Collabora2ve Center

Collabora5ve R and D Laboratories

10 nos @ 150sq.m. each

Na5onal Mission Laboratories

3 nos @ 200 sq.m. each

Incuba5on Units

E-library & Computer center


Mee5ng/ Conference Room

10 nos @ 150 sq.m. each


1 no @ 500 sq.m.

4 nos @ 150 sq.m. each

Administra5ve Units( General)

Guest house

20 nos@ 20 sq.m. each

Accommoda5on for visi5ng faculty

10 nos @ 80 sq.m. each

Guest House

Accommoda5on for research scholars

Kitchen & Dining hall

1 no @ 600 sq. m each

50 nos @ 20 sq.m. each

1 no @ 200 sq.m. each

Ground floor plan


Central Public Works Department

97

Upcoming & Built Assests of CPWD

ANTHROPOLOGICAL SURVEY OF INDIA,


AT SALT LAKE, KOLKATA

Perspec0ve View
Introduc2on :

A composite building consis5ng of a ground plus eight storied oce building, a conference
hall, an exhibi5on hall and a 400 capacity auditorium interconnected with each other. The
building is centrally air-condi5oned and a perfect blend of structural glazing and A.C.P.
cladding.
Proposal :

The proposal is for construc5on of basement +g+8, centrally air-condi5oned building


following the site prole & orienta5on & surrounding cityscape.

L-shaped corridor leading to all the rooms around triangular hall spaces. high rise main
block is inter-connected to the low rise conference & auditorium around a central landscaped
green & extending to well designed refec5ng pool with fountains at the approach point.

The building has been designed as a barrier free building with entrance ramp, li&s with
barrier free standard. green building norms like usage of low-e glass faade, recessed window,
usage of energy ecient 7ngs, water saver toilet 7ngs etc have been incorporated as salient
features of the building.

To make the external features aesthe5cally expressive & to match the exis5ng
surroundings of i.t. city with the millenium tower at the back-drop, structural glazing, acp
external cladding, modular ss railing, impressive color scheme provided.
98

Central Public Works Department

Upcoming & Built Assests of CPWD

Plot Area

FACT FILE

Permissible Ground Coverage @ 55%


Permissible Far @ 2.75

FLOOR AREA OF PROPOSED STRUCTURE :

20000 Sq.Mts

11000 Sq.M.
55000 Sq.M

Ground Floor Area for Lab Block

= 3341 Sq.M

Second Floor Area for Lab Block

= 1198 Sq.M

First Floor Area for Lab Block

Third Floor Area for Lab Block

Fourth Floor Area for Lab Block


Fi&h Floor Area for Lab Block

Sixth Floor Area for Lab Block

Seventh Floor Area for Lab Block


Eighth Floor Area for Lab Block

Basement Floor Area for Lab Block


Total Exis5ng Floor Area
Total Floor Area

Total Ground Coverage

Central Public Works Department

= 1198 Sq.M

= 1260 Sq.M

= 1260 Sq.M
= 1260 Sq.M

= 1260 Sq.M

= 1067 Sq.M
= 934 Sq.M

= 1000 Sq.M

= 13778 Sq.M

= 17406.35 Sq.M. = 0.87 (F.A.R. Achieved)


= 5388.38 Sq.M.

99

Upcoming & Built Assests of CPWD

PROPOSED ADMINISTRATIVE BLOCK FOR 13TH


BATTALION ITBP GANGTOK, SIKKIM

Green Features

Most rooms are either facing North-East or South-West, thereby receiving maximum
sunlight so that less power is required for room hea5ng. The roong system is at RCC
structure, but the parappet wall has been designed by following local Sikkimese Architecture.
The at roof can be used for instala5on of solar panel. Since the projects in Sikkim, elements
of Buddhist Architecture in shape, form and colour has been incorporated using modern
material.
Design features :
Building Type

: This is a Oce Building for 13th Ba6alion, ITBP, Gangtok.

Climate

: Gangtok is cold and humid with temperature ranging from Average 25*C
during summer to Average 10* C during winter.

Site Loca2on

Design Eciency

100

: The site is located in Lingdum, Gangtok, near famous Rumtek Monastry.


The site is in a highly hilly area with beau5ful natural landsacpes.

: Since the site is in a hilly region, op5mum design input has been given
for less soil cu7ng and lling. The Building consists of two Blocks with
a level dierence of 5 metres. The rear Block can be approached from
the rst oor of Front Block.

Central Public Works Department

Upcoming & Built Assests of CPWD

Since the site is in a hilly region, op5mum design input has been given for less soil cu7ng
and lling. The Building consists of two blocks with a level dierence of 5 metres. The rear
block can be approached from the rst oor of Front Block.

Category

FACT FILE

Oce Building.

Cost

Rs. 800 Lakhs Approx

Number of oors

Ground + 2

Plinth Area

Central Public Works Department

1980 sqm + Parking

101

Upcoming & Built Assests of CPWD

CENTRAL BANK OF INDIA AT SAMTANAGAR,


KANDIVILI %E& MUMBAI
Plot Area

FACT FILE

7736.52 Sq.M.

Permissible F.S.I.

2.00

Proposed F.S.I.

15473.0 Sq.M.
15437.00 Sq.M.

Max. FSI Achievable, If ( G+2 Lvl Pordium +


Refuge Area

Tenament Proposed

Block-A = 129 Nos Flat

23 Upper) Floors
Including
15437sq.M.

Block-B = 129 Nos Flat

258 Nos

Unit Area Flat Type B

53.00 Sq.M.

Unit Area Flat Type A

54.00 Sq.M.

LAYOUT PLAN
Central Public Works Department

105

Upcoming & Built Assests of CPWD

PRATYAKSHA KAR BHAVAN FOR INCOME TAX


DEPT. AT SUBHANPURA,BARODA
DESIGN BRIEF

The building has been designed around a


central landscaped courtyard.

The entrances to the complex are from a


podium around the
building. Three
oor high entrances are proposed on all
the four sides to give a sense of
magnicence.

Separate entrances for public have been


provided.

The building is proposed to be a green


building. Due care with respect to green
building features has been taken while
designing and giving
specica5ons.

All oce areas are ge7ng direct


ven5la5on and external view.

Some features of Baroda architecture have been incorporated in the facades to blend the
building with old architecture.

The proposed building has been approved by the client department and has been highly
appreciated by its Design Commi6ee.
PLOT AREA

PERMISSIBLE F.S.I.
PROPOSED F.S.I.
PERMISSIBLE GROUND COVERAGE
Proposed ground coverage

Max. FSI achievable, if

106

FACT FILE

296.80 SQ.M.

2.00
10593.00 SQ.M.

2.00
10500.00 SQ.M.

30% OF PLOT AREA


1589.04 SQ.M.

1600.00 sq.m.

( g+10 structure)
10600.00 sq.m.

Central Public Works Department

Upcoming & Built Assests of CPWD

Parking

Required as / norms
Provided
1)

2)

surface parking

basement parking

C.O.P. required as / norms


Proposed

Central Public Works Department

30% of max. per. FSI

687.95 sq.m.

3511.75 sq.m.

=
=

( 3177.90 sq.m.)

2823.80 sq.m.
10% =529.6sq.m.

530.65 sq.m.

107

Upcoming & Built Assests of CPWD

Planning Highlights :

G+10 storied structure

Huge large entry for the visitors / sta etc from the podium towards the centrally located
/ oriented landscape courtyard / atrium proposed at the front by considering quantum of
daily users.

Proper segrega5on of users.

Direct access / approach for the ocers to the centrally proposed atrium / landscape
courtyard at the le& side of the building.

Direct drop and pick u for the ocers at the le&.

Three oor height openings to the building are proposed at or in the four main direc5ons
to get the elegant look, kind of baroda architectural character to the structure.

Service core proposed / located in a manner so that it can be easily accessible and
serviceble.
Two level basement oor proposed for ample parking spaces and services.

Oce accomoda5ons and ocers cabins, conference rooms , visitors wai5ng spaces , etc
are planned from 2 nd oor.

Rxterior faade are proposed dholpur stone cladding.

Double height visitors lounge are proposed on every oor for the commissioners are
located to get the maximum view of the centrally located landscape courtyard.
Internal walls are proposed of double skinned pre laminated par5cle board par55ons.
Barrier free.

Rasy for handicapped movements, separate toilet, ramp, li& proposed.

Fully air condi5oned/ centrally air condi5oned building.

Bank , post oce telephone exchange, audit party rooms are planned on second oor and
directly accesible to the users without disturbing the core facili5es.

Ask centre , receipts counters are planned on ground oor and pr unit , associa5on rooms,
stores for sta5onary , canteen are planned on rst oor in such a way so that the tax payers
and users can be easily and directly acess the areas without disturbing the whole complex
/ core facili5es.
Energy ecient , proper circula5on spaces, proper ven5la5on.

Designed as per green building norms grhia

Auto sprinkler system , re gh5ng network system and services.

108

Proper re tender acess.

Rain water harves5ng- all roof top rain water shall be channelised to the rainwater
harves5ng tank and used for hor5culture.

Central Public Works Department

Upcoming & Built Assests of CPWD

GREEN BUILDING NORMS

Solar power pack & water hea5ng system. Doubled Glazed facades for energy eciency
& natural light. Sewage treatment plant to recycle waste water for Air- condi5oning &
gardening. Energy saving devices (VFD) with switching system for lights & AC system. Intelligent
re alarm system with PA system and safety signage's. Facade cleaning system & Ligh5ng
including signage and illuminated Logo. Mechanical ven5la5on system for basement. Non-wet
re gh5ng system for computer sec5on and rare document sec5on. Rain water harves5ng:
All roof top rain water shall be channelized to the rainwater harves5ng tank and used for
hor5culture.
Landscape : Open space shall be landscaped with fountains, suitable trees, plants and ground
covers.

Central Public Works Department

109

Upcoming & Built Assests of CPWD

INTERNATIONAL INSTITUTE FOR


POPULATION SCIENCE AT DEONAR , MUMBAI

SALIENT FEATURES :
Loca5on

Deonar,Mumbai

Plot Area

19008.60 Sqmt.

Land Use

Permissible F.S.I

:
:

Commercial / Ins5tu5onal
0.75(Exis5ng)2.0 Conveyed By Client

Name of the Client for Popula5on

Interna5onal Ins5tute Sciences

Type Of Building

R.C.C Structure With Bk. Wall

Height Of Building

30.00 Mt.

Founda5on

No. Of Storeys
Road

:
:
:

Ra& Founda5on

Ground + 6 Floors

18.3 Mt.Wide On The West Side

Entry To The Building

North West(Gr.Fi.)

Car Parking

As Applicable

Li&

110

4 Nos Li& For 13 Passengers

Central Public Works Department

Upcoming & Built Assests of CPWD

ADDITIONAL FEATURES :

Universal Design: Barrier Free access for all

Green Building:

Use of low energy materials

Orienta5on of complex north- south to reduce conven5onal energy demand

Minimum Space U5lised For Services And Circula5on Areas

Full Height Atrium: Provides natural light, ven5la5on and ambience of spaciousness

Form of the complex based on shape / topography features of the site

Central Public Works Department

111

Upcoming & Built Assests of CPWD

NATIONAL FIRE SERVICE COLLEGE,


AT NAGPUR
Under construc2on Buildings

Administra5ve Building

Hostel cum Guest House & Gymnasium

137 Nos. Residen5al Qtrs.

112

Academic Building

Laboratary Building

Library

Fire Sta5on

Store & Workshop

Auditorium

7 Nos. Training Module (Technical Bldgs.)

80 Nos. Covered Car Parking & 120 Nos. Open Parking

Central Public Works Department

Upcoming & Built Assests of CPWD

Administra2ve Building(nishing stage)

Total Plinth Area - 2021.16 Sqmt.

Structure G+2 upper oors (Two future oors)

Barrier free Planning

First Floor Area - 653.41 Sqmt.

Ground Floor Area - 714.34 Sqmt

Second Floor Area - 653.41 Sqmt.

To accommodate Directors, Joint Directors & Other oces.

Academic Building (nishing stage)

Ground + 3 upper oors (Two future oors)

Total Plinth Area 5943.95 Sqmt.

Departments Oces & Faculty Rooms

Landscaped courtyards

Conference & Training Hall

Barrier free Planning

First Floor Area - 1454.91 Sqmt.

Third Floor Area - 1484.56 Sqmt

Central Public Works Department

Lecture Halls, Tutorial Rooms,

Ground Floor Area - 1537.11 Sqmt

Second Floor Area - 1467.37 Sqmt.

113

Upcoming & Built Assests of CPWD

Lab Building (under construc2on)

Ground + 2 upper oors

Total Plinth Area 7826.07 Sqmt.

13 Nos. Labs

Landscaped Courtyard

Ground Floor Area - 3071.34 Sqmt

First Floor Area - 2275.80 Sqmt.

Faculty rooms

Second Floor Area - 2478.93 Sqmt.

Library (under construc2on)

Ground + 2 upper oors

Ground Floor Area - 888.17 Sqmt

Book Store & 2 Nos. Reading Room Provided

114

Second Floor Area - 747.89 Sqmt.

Barrier free Planning

Total Plinth Area - 2312.25 Sqmt.

First Floor Area - 676.19 Sqmt.

Computer Room & Data Centre Provided


Barrier free Planning

Central Public Works Department

Upcoming & Built Assests of CPWD

Hostel Building, Guest House & Gym(under construc2on)

Ground + 8 upper oors (Boys Hostel)

Ground + 3 upper oors (Guest House & Sick Bay)

Ground + 3 upper oors (Girls Hostel)

Ground + 3 upper oors (Gymnasium, Kitchen & Dormitory)

Barrier free Planning with 5 Nos. of Li&s

Single storey Dining Halls (separate for Boys & Girls)

Central Public Works Department

115

Upcoming & Built Assests of CPWD

Fire Sta2on(under construc2on)

Ground + 2 upper oors

Total Plinth Area 3639.75 Sqmt.

Ground Floor Area - 2162.63 Sqmt

First Floor Area - 435.00 Sqmt.

16 Nos. Fire Vehicle Parking Bays

Second Floor Area - 1042.12 Sqmt.

Oce, Control Room & Dormitories

AUDITORIUM BUILDING (under construc2on)

Category

Name of Work

Cost

Ins5tu5onal building

Auditorium for Na5onal re service


College, Nagpur
Approx. 5.00 Crores

Area of the plot

Situated in NFSC premises.

Number of Floors

----

Plinth Area

Date of Requisi5on

13/05/2010

Salient features

Auditorium having sea5ng capacity of 700 persons


with Exhibi5on Hall. It is centrally Aircondi5oned.

116

Date of client approval

1535.00 Sqmt

09/12/2010

Central Public Works Department

Upcoming & Built Assests of CPWD

RESIDENCE FOR FORMER PRESIDENT OF


INDIA, PUNE

A piece of Govt. land of an area 5224 Sq.m with an exis5ng bunglow of area 213 Sq.m is
allo6ed for former President of India, Smt. Pra5bhatai Pa5l at Pune. Since the exis5ng building
area was not as per her en5tlement, addi5onal area was sought, accordingly plan was proposed
to have extension to the exis5ng building.

The overall plan of an area 350 Sq.m has living cum dining hall, kitchen, lounge, library and
3 Bedrooms with a6ached toilet facility. Servants quarter 4 Nos. and 2 Garages was also
provided. Security cabin, PAs oce were also planned. Beau5ful Eleva5ons, Interiors &
landscaping were created to add asthe5cs to the bunglow. Boundary wall has been properly
secured. Sentry posts were proposed on all the corners of the site for security purpose.

The whole project was planned and conceived in a short span of 5me and was completed
in a period of four months
Central Public Works Department

117

Upcoming & Built Assests of CPWD

118

Central Public Works Department

Upcoming & Built Assests of CPWD

FACT FILE

Category

Residen5al Building

Cost

201.00 Lakhs

Name of the Work

Area of the plot

Proposed addi5ons & altera5ons to the residence for


former President

5224.00 Sq.m

Plinth Area

539.00 Sq.m

Date of Start

15-12-2012

Number of Floors
Date of Comple2on

Central Public Works Department

Ground oor
10-05-2013

119

Upcoming & Built Assests of CPWD

MAHATMA GANDHI ANTARRASHTRIYA HINDI


UNIVERSITY, WARDHA

The MGAHU, Wardha is situated on Nagpur-Wardha bypass highway on highlands. This is


the only Hindi university in central India to promote Hindi language in masses.

1.

PROPOSED ACEDEMIC BLOCK UNDER CONST.

Built Up Area : 9120.00 Sq.m

Cost : 1393.25 Lakhs (AA/ES)

2.

DISTANCE EDUCATION BUILDING UNDER CONST.

Built Up Area : 3465.95 Sq.m

3.

Cost : 588.83 Lakhs (AA/ES)

PROPOSED BOYS HOSTEL yet to be started

Cost : 140.00 Lakhs

Built Up Area : 521.017 Sq.m

4.

PROPOSED GIRLS HOSTEL (sanc5on awaited)

Built Up Area : 6073.01 Sq.m

120

Cost : 1150.00 Lakhs

Central Public Works Department

Upcoming & Built Assests of CPWD

89 NOS TYPE QUARTERS


AT GHOUD DAUD ROAD, SURAT

Plot Area

Permissible F.S.I.
Proposed F.S.I.
Permissible Ground Coverage
Proposed Ground Coverage
Parking Required As / Norms

FACT FILE

8290.00 Sq.M.

1.80
14922.00 Sq.M.
1.80
10800.00 Sq.M.

30% of Plot Area


2487.00sq.M.

25.00 %
2102.81 Sq.M.

15% of Max. Per. Fsi


2238.30sq.M.)

Provided 1) Surface Parking

835.42 Sq.M.

C.O.P. Required As / Norms =10%

1658.00 Sq.M.

2) S2lt Parking
Proposed

Central Public Works Department

1524.00 Sq.M.
2360.00 Sq.M.
121

Upcoming & Built Assests of CPWD

LAYOUT PLAN
Consists of

Type Quarters

Parking

Service Core

Entrance Foyer

Exterior Facade

Units ( Type Quarters )

Conopy

122

Landscaping

Total 89 Nos Type Quarters , 1 Block Of ( 3 Nos


Type-Vi ,4 Nos Type-V Quarters ), 3 Blocks Of
Type-Iv (82 Nos Quarters )
S5lt Floor / Ground Floor for Parking and Services

Located In The Manner So That It Can Be Easily


Accessible and Serviceble for the User .
Entrance Is Provided In The Centre at Ground
Floor Considering Quantum of Daily Users .

Composi5on Of The Projected Exterior Surfaces


by Giving The Residen5al Look to the Eleva5ons
By Coa5ng Surface Texture Paint.

All The Units Are Placed Such A Way to Get The


Maximum Openable View of the Loca5on.
Centrly Located To Get the Maximum Landscaped
/ Garden View.

Invi5ng And A6rac5ve

Centrly Placed / Oriented to get the Fresh View


to the Type Quarters.
Central Public Works Department

Upcoming & Built Assests of CPWD

Bank, Post Oce

Handicapped

Fire Figh5ng Systems and


Services

Green Building Norms

On First Floor And Directly Accessible to the Users


as well as Visitors Without Disturbing the Core
Facili5es.

Barrier Free , Easy For Handicapped Movements.


Li& Facili5es.

Proper Fire Tender Access , Auto Sprikler System


And Fire Figh5ng Network. Non-wet re gh5ng
system for computer sec5on and rare document
sec5on.
Sewage treatment plant to recycle waste water
for Air- condi5oning & gardening.

Rain water harves5ng: All roof top rain water shall


be channelized to the rainwater harves5ng tank
and used for hor5culture.
Landscape : Open space shall be landscaped with
fountains, suitable trees, plants and ground
covers.

Central Public Works Department

123

Upcoming & Built Assests of CPWD

OFFICE BUILDING FOR CENTRAL EXCISE


AT VAPI

Plot Area

Permissible F.S.I.
Proposed F.S.I.

Permissible Ground Coverage


Proposed Ground Coverage

FACT FILE

5010.00 Sq.M.

1.70 = 8517.00 Sq.M.

1.70 = 8291.65 Sq.M.

25% Of Plot Area = 1252.50 Sq.M.

1069.23 Sq.M.

Max. Fsi Achievable, If

( G+8 Structure) 8291.65 Sq.M.

Provided

3917.00 Sq.M.

Parking Required As / Norms


C.O.P. Required As / Norms
Proposed

124

46% of Built Up Area ( 3917.00 Sq.M.)


30% of Plot Area (1503.00 Sq.M.)
1608.52 Sq.M.

Central Public Works Department

Central Public Works Department (CPWD)


In the service of the nation since 160 years
Under the Ministry of Urban Development, Government of India, CPWD provides single
window services for all facets of the government built environment in India and abroad.
With its huge resource of skilled and competent engineers, architects and horticulturists,
CPWD's strength is its country wide presence, with proven ability to undertake a whole range
of complex constructions under difficult terrains. The department has the capacity to
undertake construction varying from the smallest works in the remotest of places to mega
projects in metro cities. These works include the construction and maintenance of
government structures such as residential complexes, offices, schools, laboratories,
hospitals, sport facilities, stadia, gymnasia, auditoria, storages, highways, flyovers, tunnels,
bridges, jetties, airports, runways and border fencing. Intra-campus facilities such as water
and electric supply, sewerage and treatment plants are also provided.
CPWD also performs other functions such as the custody of estates, valuation, rent
assessment, technical advice to government, consultancy services, standardisation and
benchmarking, State Ceremonies (Republic Day, Samadhis, etc.), processing of DPRs for
development of urban infrastructure under JNNURM and works of other Ministries for
centrally funded works. CPWD also assists in organising public and ceremonial functions,
and upkeep of historical and important monuments and structures.

Handbook of Upcoming & Built Assets of CPWD


CPWD also publishes various documents to help the construction industry. With this
publication CPWD is coming up with the volume-I of this book which has the inventory of
upcoming projects and the projects built by CPWD in the recent past. In the years to come
CPWD will release other volumes of this book.

Central Public Works Department


Nirman Bhawan, New Delhi 110 011.
URL : http://cpwd.gov.in

July, 2014.

You might also like