Professional Documents
Culture Documents
UK numbers
MTBF
MDT
10 years
1 hour
1 month
1 day
30 seconds 1 second
Availability
6+1 hours
99.992%
6h+30s
99.17%
6h+1s
74.99%
Availability
Nines
MDT
20ms failures
99.0%
99.9%
99.99%
99.999%
99.9999%
99.99999%
99.999999%
99.9999999%
2
3
4
5
6
7
8
9
87.6 hrs
8.76 hrs
53 min
5.3 min
31.5 sec
3.15 sec
315 ms
31.5ms
15,768,000
1,576,800
157,680
15,768
1,577
158
15
2
Connectivity
Power
Cooling
EPO
The Uptime Institute [1] has, for more than 10 years, sponsored
research and practical studies into data centre design, operation and
resultant resilience and developed a Tier Classification to describe and
differentiate facilities from an availability standpoint
A White Paper [2] from the Institute (authors of which include the
originator of dual power supplies in IT equipment and the Tier system
itself) is the basis of this review of the facility and operational concepts
www.uptimeinstitute.org
[1] The Uptime Institute, Building 100, 2904 Rodeo Park Drive East, Santa Fe, NM 87505, USA
[2] Title: Industry Standard Tier Classifications Define Site Infrastructure Performance, Turner, Seader &
Brill, 2001-2005 The Uptime Institute, Inc
ANSI/TIA-942-2005
-
Standards and Technology Dept, 2500 Wilson Boulevard, Arlington, VA 22201, USA
www.tiaonline.org/standards/search_n_order.cfm
Follows the same Tier I-IV format and draws heavily on The Uptime
Institute publications but extends the detail, especially in connectivity
Fault Tolerant: A site that that can sustain at least one unplanned
worst-case infrastructure failure with no critical load impact
Note that it is acceptable that the fault tolerance level will be reduced
during maintenance or after the first fault
[1] Title: Fault Tolerant Power Compliance Specifications, v2.0, see www.uptimeinstitute.org
Tier IV power +Tier III all other + Tier II cooling = Tier II Facility
Segregation
To be able to run the load via the bypass and test the UPS
system as a parallel group is a very attractive and useful
operational/maintenance feature
-
Generally that means that between the PDU and the output
bus of the UPS system there are at least two MCCBs or
ACBs in series
-
Maintenance Bypass
Output Switchboard
100% Redundancy
600kVA Load
2x 600kVA modules
R = 10*
Day One only
Highest UPS CapEx
High risk of partial load
High load step
1200kVA of batteries
2+1
3+1
50% Redundancy
25% Redundancy
3x 300kVA modules
R=7
Day One to Two
Scope for load shrink
Medium risk of partial load
Medium load step
900kVA of batteries
25% space saving
Lower battery CapEx
4x 200kVA modules
R=5
Day One to Three
High scope for load shrink
Low risk of partial load
Low load step
800kVA of batteries
33% space saving
etc
To truly achieve a Tier Classification means ticking-the-box in 16 subgroups and one of the most important is timely, skilled and proper
maintenance capabilities on site
-
Human error remains the largest contributor group to mission failure, most
often when responding to alarms in complex systems
For the power system the best (and only cost effective?) solution is to
use 24x7 remote monitoring with trained service personnel
-
Diagnose alarm and set in motion the right engineer with the right parts
Complete physical segregation of the two power supplies from the grid
to the dual-corded load a true Dual-Bus system
-
Needs two grid sub-stations (they will be on the same MV-ring or diverse
MV-radials) and diverse cable routes into the site
Note that many engineers question having N+1 on both A & B buses
No STSs, no common point of failure except the grid and the load
B fed from UPS-B for the second feed of the dual-cord loads
A/B with STS fed from UPS-A & B for single-cord loads
Keep the air moving, server fans are often sufficient, obtain
generator power after 10-15 seconds and, preferably, have high
floor-to-ceiling heights
Keep the fluids moving via UPS driven redundant pumping and,
wherever possible, apply Chilled-Water-Storage
N+1 topology: The higher the N, the higher the module load
Higher capital cost typically 3-8 times that of an equivalent power battery
Low speed flywheels (steel rotor, bearing load relief via magnetics)
-
Standby losses x20 that of battery float power (+10kW higher losses per MVA)
Standby losses x15 that of battery float power (+8kW higher losses per MVA)
Standby losses x2 that of battery float power (+1kW higher losses per MVA)
Are they a replacement for the generator rather than the battery?
Not to rely on the dual-corded loads to operate with one feed dead?
A third UPS (C) system? Space hungry, 0.05% utilisation and a poor
return on investment
-