SCOPE OF WORK/SUPPLY

GENERAL CIVIL
COKE HANDLING SYSTEM
PACKAGE
BPCL-IREP

3.0

SECTION: C-1.7
A307-0ID16-47-SOW-7000
Rev. 3
Page 13 of 13

During excavation for foundations, underground piping, etc., lowering of


ground water table if required and dewatering of surface water is in the scope
of the CONTRACTOR.

For piping being laid from underground to aboveground, tape coating shall be
done minimum of upto 500 mm from the HPP.

Necessary coordination like collecting necessary data, levels, including visits


to site, other contractors design offices etc., required to interface various
facilities with other contractors shall be in the CONTRACTOR scope.

APPROVALS
Approval of the facilities within contract scope limit from Chief Controller of Explosives
(CCOE,), of PETROLEUM AND EXPLOSIVES SAFETY ORGANISATION (PESO)
and Tariff Advisory Committee (TAC) accredited agency shall be obtained by the EPC
package contractor.
EPC Contractor to comply with the requirement of these authorities irrespective if it is
mentioned or not in the bid package & shall form part of contractors scope of work
including preparation of required drawings/ documents. Contractor shall comply with
the requirement of local bodies including preparation of required drawings/ documents.

4.0
4.1

SCOPE OF SUPPLY
OWNERS SCOPE OF SUPPLY
Nil

4.2

CONTRACTORS SCOPE OF SUPPLY


- All items consumables/non consumables required to complete the job.
-

All tools tackles, plant machinery etc to complete the job.