Professional Documents
Culture Documents
INTRODUCTION
1.1
Introduction
An Embedded System employs a combination of hardware and software to
perform a specific function. Software is used for providing features and flexibility
hardware (Processors, Memory) is used for performance and sometimes security. An
embedded system is a special purpose system in which the computer is completely
encapsulated by the device it controls. Unlike a general purpose computer, such as a
PC, an embedded system performs predefined tasks usually with very specific tasks
design engineers can optimize it reducing the size and cost of the product. Embedded
systems are often mass produced, so the cost savings may be multiplied by millions of
items. The core of any embedded system is formed by one or several microprocessor
or microcontroller programmed to perform a small number of tasks. In contrast to a
general purpose computer, which can run any software application, the user chooses,
the software on an embedded system is semi-permanent so it is often called firmware.
1.2
Objectives
The objective of this project is to determine the distance of underground cable
fault from base station in kilometres. The underground cable system is a common
practice followed in many urban areas. While a fault occurs for some reason, at that
time the repairing process related to that particular cable is difficult due to not
knowing the exact location of the cable fault. The proposed system is to find the
exact location of the fault.
The project uses the standard concept of the Ohms law i.e., when a low DC
voltage is applied at the feeder end through a series resistor (Cable lines), then current
would vary depending upon the location of the fault in the cable.
1.3
Problem Specification
All the transmission lines are laid underground as the underground cables are
not affected by the adverse weather conditions. Neither the hot sunny day nor the rain
is to influence it. But when the cable breaks due to some reasons its very difficult to
locate that. Currently what is done is they find the approximate location and dig the
cables out from the location and check it manually to find the exact point of
discontinuity. This method is very tedious and most of the labour is involved.
1.4
Methodologies
1
1.5
Layout of thesis
Chapter 2
LITERATURE SURVEY
In electrical utilities, transmission lines form the backbone of power systems.
With regard to reliability and maintenance costs of power delivery, accurate fault
location for transmission lines is of vital importance in restoring power services and
reducing outage time as much as possible. Accurately locating faults on high voltage
transmission networks is very important for utilities to allow a quick maintenance
action of the repair crew.
Till the last decade the cables where made to lay overhead and currently the
scenario is to lay underground cable, which is superior to the earlier method. This is
because the underground cables are not affected by the adverse weather conditions.
Neither the hot sunny day nor the rain is to influence it. But when the cable breaks
due to some reasons its very difficult to locate that. Currently what is done is they
find the approximate location and dig the cables out from the location and check it
manually to find the exact point of discontinuity.
Fault location detection is finding exact fault position of cable when there
were any unwanted accidents like short circuit, open circuit, insulation breakdown etc.
Because of large damage and inference of power cable accident, power authorities
want to have exact fault detection method to recover power lines as soon as possible.
Various methods have been developed to reduce damage and inference. Bust most of
fault detection methods have shortcomings. Some have low accuracy, some are
difficult to apply because of surrounding environment, and some give unwanted
damage to healthy neighbouring cable and facilities.
Among these methods, pulse echoing method[1] is regarded as most useful
ones.
This method use time difference between incident and reflected pulse to
calculate fault location detection and it has relatively high accuracy because it use
short period pulse. Although it has high accuracy, pulse echoing method has some
drawbacks. When we apply this method to low impedance accident, the error will be
increased. If cable is not open circuit and there is no impedance change, there are no
reflected pulse waves, and it is difficult to find fault location. Also high voltage pulse
generator is needed for pulse echoing method and it is one of its drawbacks. To make
high voltage pulse generator one should pay another money, and inserting high
voltage to cable can cause another damage to cable and facilities. It is usually applied
to detect fault location after accident arises and this way need more time to repair.
Now the world has become digitalized so the project is intended to detect the
location of fault in digital way. The underground cable system is more common
practice followed in many urban areas. While fault occurs for some reason, at that
time the repairing process related to that Fault in cable is represented as :
Any defect,
Inconsistency,
Weakness or non-homogeneity that affect performance of cable,
Current is diverted from the intended path,
Caused by breaking of conductor or failure of insulation.
Chapter 3
HARDWARE IMPLEMENTATION
The Hardware consists of
1.
2.
3.
4.
5.
6.
7.
8.
9.
Transformer
Voltage Regulator
Rectifier
Microcontroller
Analog to Digital Converter
Relay Driver
Relay
LCD Display
GSM Module
3.1. TRANSFORMER
Transformers convert AC electricity from one voltage to another with a little
loss of power. Step-up transformers increase voltage, step-down transformers reduce
voltage. Most power supplies use a step-down transformer to reduce the dangerously
high voltage to a safer low voltage.
little power so the power out is (almost) equal to the power in. Note that as voltage is
stepped down and current is stepped up.
The ratio of the number of turns on each coil, called the turns ratio,
determines the ratio of the voltages. A step-down transformer has a large number of
turns on its primary (input) coil which is connected to the high voltage mains supply,
and a small number of turns on its secondary (output) coil to give a low output
voltage.
TURNS RATIO = (Vp / Vs) = ( Np / Ns )
Where,
Vp = primary (input) voltage.
Vs = secondary (output) voltage
Np = number of turns on primary coil
Ns = number of turns on secondary coil
Ip = primary (input) current
Is = secondary (output) current.
3.3. RECTIFIER
A rectifier is an electrical device that converts alternating current (AC), which
periodically reverses direction, to direct current (DC), current that flows in only one
direction, a process known as rectification. Rectifiers have many uses including as
components of power supplies and as detectors of radio signals. Rectifiers may be
made of solid state diodes, vacuum tube diodes, mercury arc valves, and other
components. The output from the transformer is fed to the rectifier. It converts A.C.
into pulsating D.C. The rectifier may be a half wave or a full wave rectifier. In this
project, a bridge rectifier is used because of its merits like good stability and full wave
rectification. In positive half cycle only two diodes (1 set of parallel diodes) will
conduct, in negative half cycle remaining two diodes will conduct and they will
conduct only in forward bias only.
varied, D.C. voltage received at this point changes. Therefore a regulator is applied at
the output stage.
The simple capacitor filter is the most basic type of power supply filter. The
use of this filter is very limited. It is sometimes used on extremely high-voltage, lowcurrent power supplies for cathode-ray and similar electron tubes that require very
little load current from the supply. This filter is also used in circuits where the powersupply ripple frequency is not critical and can be relatively high. Below figure can
show how the capacitor changes and discharges.
3.4. MICROCONTROLLER
A Microcontroller is
circuit containing
processor
core,
memory,
on
single integrated
and
programmable
Specifications.
Works with 2.5 V (LM336) Voltage Reference on Chip Clock Generator.
0 V to 5 V Analog Input Voltage Range with Single 5 V Supply.
No Zero Adjust Required.
0.3 Inch Standard width 20 Pin DIP Package.
20 Pin Molded Chip Carrier or Small Outline Package.
Operates Rationmetrically or With 5 VDC , 2.5 VDC or Analog Span Adjusted
Voltage Reference.
Key Specifications
o Resolution : 8 Bits
o Total Error : 1/4 LSB, 1/2 LSB and 1 LSB
o Conversion Time : 100 s
11
3.5.1. DESCRIPTION
The ADC0801, ADC0802, ADC0803, ADC0804 and ADC0805 devices are
CMOS 8-bit successive approximation converters (ADC) that use a differential
potentiometric ladder similar to the 256R products. These converters are designed
to allow operation with the NSC800 and INS8080A derivative control bus with Tristate output latches directly driving the data bus. These ADCs appear like memory
locations or I/O ports to the microprocessor and no interfacing logic is needed.
Differential analog voltage inputs allow increasing the common-mode
rejection and offsetting the analog zero input voltage value. In addition, the voltage
reference input can be adjusted to allow encoding any smaller analog voltage span to
the full 8 bits of resolution.
12
FEATURES
Pin no.16
Temperature, Operating Range:-20C to +85C
Transistor Polarity: NPN
Transistors, No. of:7
Case Style:DIP-16
Temp, Op. Min:-20C
13
DIAGRAM
FEATURES OF
DRIVER
3.7. RELAY
A relay is an electrically operated switch. Many relays use an electromagnet to
operate a switching mechanism mechanically, but other operating principles are also
used. Relays are used where it is necessary to control a circuit by a low-power signal
(with complete electrical isolation between control and controlled circuits), or where
several circuits must be controlled by one signal.
14
available. For further information about switch contacts and the terms used to
describe them please see the page on switches.
Most relays are designed for PCB mounting but you can solder wires directly
to the pins providing you take care to avoid melting the plastic case of the relay.
The supplier's catalogue should show you the relay's connections. The coil
will be obvious and it may be connected either way round. Relay coils produce brief
high voltage 'spikes' when they are switched off and this can destroy transistors and
ICs in the circuit. To prevent damage you must connect a protection diode across the
relay coil.
The figure shows a relay with its coil and switch contacts. You can see a lever
on the left being attracted by magnetism when the coil is switched on. This lever
moves the switch contacts.
COM = Common, always connect to this; it is the moving part of the switch.
NC = Normally Closed, COM is connected to this when the relay coil is off.
NO = Normally Open, COM is connected to this when the relay coil is on.
solenoid of an automobile.
Detect and isolate faults on transmission and distribution lines by opening
16
copper disk between the armature and moving blade assembly. Current flowing in
the disk maintains magnetic field for a short time, lengthening release time. For a
slightly longer (up to a minute) delay, a dashpot is used. A dashpot is a piston
filled with fluid that is allowed to escape slowly. The time period can be varied
by increasing or decreasing the flow rate. For longer time periods, a mechanical
clockwork timer is installed.
commonly used in various devices and circuits. These modules are preferred over
seven segments and other multi segment LEDs. The reasons being: LCDs are
economical; easily programmable; have no limitation of displaying special & even
custom characters (unlike in seven segments), animations and so on.
1. A 16x2 LCD means it can display 16 characters per line and there are 2 such
lines. In this LCD each character is displayed in 5x7 pixel matrix. This LCD has
two registers, namely, Command and Data.
2. The command register stores the command instructions given to the LCD. A
command is an instruction given to LCD to do a predefined task like initializing
it, clearing its screen, setting the cursor position, controlling display etc. The data
register stores the data to be displayed on the LCD. The data is the ASCII value of
the character to be displayed on the LCD.
18
19
Chapter 4
20
Chapter 5
Chapter 6
REFERENCES
[1].
[2].
[3].
M.S. Choi, D.S. Lee and X. Yang, A line to ground fault location algorithm
for underground cable system, KIEE Trans. Power Eng., pp. 267-273, June
[4].
2005.
Md. Fakhrul Islam, Amanullah M T Oo, Salahuddin. A. Azad, Locating
Underground Cable Faults : A Review and Guideline for New Development,
[5].
2013 IEEE.
T.S. Sidhu and Z. Xu, Detection of Incipient Faults in Distribution
Underground Cables, IEEE Transactions on Power Delivery, Vol. 25, No.3,
[6].
July 2010.
K.K. Kuan, Prof. K. Warwick, Real-time expert system for fault location on
high voltage underground distribution cables, IEEE PROCEEDINGS-C, Vol.
[7].
22