Professional Documents
Culture Documents
Objective
Traditional and Current EVM methodologies
Introduce the Integral Earned Schedule (IES)
Concept
Develop the Schedule Performance Indicators
and Predictors
Comparison of Different Methods
CPM or EVA?
CPM: The most reliable method to predict the
projects time dimension (Fleming & Koppelman)
CP analysis as a predictor: too time-consuming &
incapable of providing early warning signal due to
its retrospective nature.
C/SCSC & ANSI/EIA 748:
These standards do not define the analysis to be
performed on EVM other than to state cost and
schedule variances need to be computed.
4
Activity Duration
In project baseline (PMB)
BAC
Performance % Complete
EV
AC
CV
CPI
Schedule % Complete
PV
SV
Data Date
(DD)
SPI
DERIVED
DATA
SV = EV - PV
SPI = EV / PV
6
SPI() = EV / PV
SPI(t) = ES / AT
SV() = EV PV = ?
At completion (For late finish project):
SPI() ends up at 1!
SV() ends up at 0!
Schedule Variance in units of budget make
no sense!
They behave erratically for projects behind
schedule.
EV(ATn-1)%
EV(ATn) %
ATn-1
ATn
Time
(Periods)
ATn% - ATn-1%
Indicators:
SV(IES) = IES AT
SPI(IES) = IES / AT
where: AT: Actual Time
11
Prediction Terminology
Prediction
Method
Anbari
Jacob
Earned Duration
Lipke
Earned
Schedule
Zarei
Integral Earned Schedule
IEAC(t)ED1 =
PD + AT (1 -SPI)
IEAC(t)PV1 =
PD - (SV/(BAC/PD)) After PCD:
IEAC(t)ED1 =
AT (2 - SPI)
P.F. = 1
IEAC(t)ES1 = IEAC(t)IES1 =
AT + (PD - ES) AT + (PD - IES)
IEAC(t)ED2 = PD / SPI
IEAC(t)PV2 =
PD / SPI
P.F. = SPI
12
After PCD:
IEAC(t)ED2 = AT / SPI
IEAC(t)ES2 =
PD / SPI(t)
IEAC(t)IES2 =
PD / SPI(IES)
14
SV(t)cum
Target SV
SV()cum
Zarei
2.0
500
0
Periods
0.0
-2.0
-500
-4.0
-1000
-6.0
-1500
-8.0
-2000
-10.0
-2500
0
10
15
20
25
30
35
40
45
50
55
Time (Periods)
The SV(t) starts to show the
real final delay from 97%
completion point!
Incapability in providing the
real final delay in early /
middle stage of project.
15
SPI(t)cum
SPI()cum
Target SPI
1.20
1.10
Index Value
1.00
0.90
0.80
0.70
0.60
0.50
0
10
15
20
25
30
35
40
45
50
55
Time (Periods)
SPI(IES): always overall normal & consistent trend
SPI(t): always overall abnormal & inconsistent trend: Look at the upward and
downward trends! Ooops! So confusing for PM!
16
Schedule Variance
SV():
Expressed in pounds units;
in the vertical direction
SV(t):
Expressed in time units
in the horizontal direction
SV(IES):
Expressed in time units
Consider both vertical and horizontal direction
(integration of time and cost together), then looks at
horizontal direction
17
IEAC(t)PV1
Anbari
IEAC(t)ED1
Jacob
IEAC(t)ES1
Lipke
IEAC(t)
IES1
IEAC(t)EAS1
Planned Duration
Final Duration
Duration (Periods)
Zarei
62
60
58
56
54
52
50
48
0%
20%
40%
60%
80%
100%
Duration (Periods)
P.F. = SPI,
SPI(t),
SPI(IES)
IEAC(t)PV2
Anbari
IEAC(t) IES2
IEAC(t)EAS2
Zarei
90
85
80
75
70
65
60
55
50
45
IEAC(t)ED2
Jacob
IEAC(t)ES2
Lipke
Planned Duration
Final Duration
Seeing is believing!
0%
20%
40%
60%
80%
100%
IES Summary
Time & Cost Integration for assessing and measuring schedule
performance and predicting final duration;
IES: Integration of both time and cost together;
Unique characteristics of the area Under Planned Value curve
(AUPV) and area under EV curve (AUEV) in Real Projects (not
applicable for artificial and unrealistic projects);
SV(IES):
normal & consistent trend from early stage of project;
capability to predict real final delay of project (Early
Warning Signal); CONSISTENCY AND ACCURACY
IES method:
consistent, stabilized and correct predictive behaviour from
the early stage of project (Early Warning Signal).
20
IES Summary
Project Managers do not need the predictive results at the late
stage of project
At the late stage, PM cannot take corrective action; everybody is
aware of delay
IES method claims to predict correct final duration from early
stage. Useful info for PMs! That is called: Early Warning Signal!
IES method:
provide consistent results (real final delay, final duration) from
early stage; CONSISTENCY AND ACCURACY
advance programme control;
give opportune time to project planners and PMs to take
corrective action.
The other methods do not have this capability!
21
22
References
Anbari F. (2003) Earned value method and extension. Project Management
Journal
Fleming, Q. et al. (2005) Earned value project management, 3rd ed, PMI
Jacob, D. (2003) Forecasting project schedule completion with earned value
metrics. The Measurable News (March)
Jacob, D. et al. (2004) Forecasting project schedule completion with earned
value metrics revisited. The Measurable News (Summer)
Lipke, W. (2003) Schedule is different. The Measurable News (March)
Lipke, W. (2009) Project duration forecasting a comparison of earned value
management methods to earned schedule. The Measurable News (Issue 2)
PMI-EVM Practice Standard, (2005), PMI
Vanhoucke, M. et al. (2006) A simulation and evaluation of earned value
metrics to forecast project duration. J Oper Res Soc
Vanhoucke,
M. et al. (2006) comparison of different project duration
forecasting methods using earned value metrics. International Journal of Project
Management 24
24
http://www.mgmt-technologies.com/newsletters.html
25