You are on page 1of 6

Scheduling/Leveling Report - 2017-02-02 14:45:16 - PM.

exe
=========================================================
Default Project..................................................PHDPL-3
Projects:
PHDPL-3.........................................................
.Paradeep to Haldia Pipeline
Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retaine
d Logic
Calculate start-to-start lag from ...............................Early S
tart
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish
Float
Calculate float based on finish date of .........................Each pr
oject
Calendar for scheduling Relationship Lag ........................Predece
ssor Activity Calendar
Advanced
--------
Calculate multiple float paths...................................No
Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................439
# Not Started....................................................411
# In Progress....................................................28
# Completed......................................................0
# Relationships..................................................531
# Activities with Constraint.....................................0
Errors:
-------
Warnings:
---------
Activities without predecessors..................................6
Project: PHDPL-3 Activity: PEOE110 Prepare & Issue
MR-OFC Joint Kits/Electronic Mar
Project: PHDPL-3 Activity: PGGO000 Notification to
Start
Project: PHDPL-3 Activity: PSSCWB000 Prepare
& Issue Tender
Project: PHDPL-3 Activity: PSSEIB000 Prepare
& Issue Tender
Project: PHDPL-3 Activity: PSSEIO000 Prepare
& Issue Tender
Project: PHDPL-3 Activity: PSSMWB000 Prepare
& Issue Tender
Activities without successors....................................1
Project: PHDPL-3 Activity: PGGO130 Project Completi
on Date
Out-of-sequence activities.......................................24
Project: PHDPL-3 Activity: PCMSP1010 ROW Clea
ring & Grading
Project: PHDPL-3 Activity: PCMSP1040 Hauling
& Stringing
Project: PHDPL-3 Activity: PCMSP1090 Mainline
Welding & Joint Coating
Project: PHDPL-3 Activity: PCMSP1100 Mainline
Lowering - In
Project: PHDPL-3 Activity: PCMSP1140 Back Fil
ling
Project: PHDPL-3 Activity: PCMSP1200 Hydrotes
ting
Project: PHDPL-3 Activity: PCMSP1230 Tie-Ins
Project: PHDPL-3 Activity: PCMSP2010 ROW Clea
ring & Grading
Project: PHDPL-3 Activity: PCMSP2040 Hauling
& Stringing
Project: PHDPL-3 Activity: PCMSP2080 Mainline
Welding & Joint Coating
Project: PHDPL-3 Activity: PCMSP2130 Back Fil
ling
Project: PHDPL-3 Activity: PCMSP2190 Hydrotes
ting
Project: PHDPL-3 Activity: PMOEF050 Delivery
of Electrical Fittings & fixtures
Project: PHDPL-3 Activity: PMOEM50 Deliveryof Earth
ing Materials
Project: PHDPL-3 Activity: PMOFF050 Delivery
of Fire Fighting Equipments
Project: PHDPL-3 Activity: PMOFG050 Delivery
of Fasteners & Gaskets
Project: PHDPL-3 Activity: PMOFV060 Complete
Delivery
Project: PHDPL-3 Activity: PMOHD060 Complete
Delivery
Project: PHDPL-3 Activity: PMOMS060 Complete
Delivery
Project: PHDPL-3 Activity: PMOMVW060 Complete
Delivery
Project: PHDPL-3 Activity: PMOOFC050 Delivery
of OFC Jointing Kits/Electronic Markers
Project: PHDPL-3 Activity: PMOPI050 Delivery
of Pressure Indicators
Project: PHDPL-3 Activity: PMOSP060 Complete
Delivery
Project: PHDPL-3 Activity: PMOW050 Delivery of Warn
ing Signals
Activities with Actual Dates > Data Date.........................28
Project: PHDPL-3 Activity: PCMSP1010 ROW Clea
ring & Grading
Project: PHDPL-3 Activity: PCMSP1020 Trenchin
g
Project: PHDPL-3 Activity: PCMSP1040 Hauling
& Stringing
Project: PHDPL-3 Activity: PCMSP1090 Mainline
Welding & Joint Coating
Project: PHDPL-3 Activity: PCMSP1100 Mainline
Lowering - In
Project: PHDPL-3 Activity: PCMSP1140 Back Fil
ling
Project: PHDPL-3 Activity: PCMSP1200 Hydrotes
ting
Project: PHDPL-3 Activity: PCMSP1230 Tie-Ins
Project: PHDPL-3 Activity: PCMSP1240 Final Cl
ean up & Restoration
Project: PHDPL-3 Activity: PCMSP2010 ROW Clea
ring & Grading
Project: PHDPL-3 Activity: PCMSP2020 Trenchin
g
Project: PHDPL-3 Activity: PCMSP2040 Hauling
& Stringing
Project: PHDPL-3 Activity: PCMSP2080 Mainline
Welding & Joint Coating
Project: PHDPL-3 Activity: PCMSP2090 Mainline
Lowering - In
Project: PHDPL-3 Activity: PCMSP2130 Back Fil
ling
Project: PHDPL-3 Activity: PCMSP2190 Hydrotes
ting
Project: PHDPL-3 Activity: PMOEF050 Delivery
of Electrical Fittings & fixtures
Project: PHDPL-3 Activity: PMOEM50 Deliveryof Earth
ing Materials
Project: PHDPL-3 Activity: PMOFF050 Delivery
of Fire Fighting Equipments
Project: PHDPL-3 Activity: PMOFG050 Delivery
of Fasteners & Gaskets
Project: PHDPL-3 Activity: PMOFV060 Complete
Delivery
Project: PHDPL-3 Activity: PMOHD060 Complete
Delivery
Project: PHDPL-3 Activity: PMOMS060 Complete
Delivery
Project: PHDPL-3 Activity: PMOMVW060 Complete
Delivery
Project: PHDPL-3 Activity: PMOOFC050 Delivery
of OFC Jointing Kits/Electronic Markers
Project: PHDPL-3 Activity: PMOPI050 Delivery
of Pressure Indicators
Project: PHDPL-3 Activity: PMOSP060 Complete
Delivery
Project: PHDPL-3 Activity: PMOW050 Delivery of Warn
ing Signals
Milestone Activities with invalid relationships..................0
Finish milestone and predecessors have different calendars.......0
Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................439
# Relationships with other projects..............................0
Data Date........................................................12-May-
14
Earliest Early Start Date........................................12-May-
14
Latest Early Finish Date.........................................30-Sep-
15
Exceptions:
-----------
Critical Activities..............................................74
Project: PHDPL-3 Activity: PCCS1000 Mobilize
Resources for Cased Xings
Project: PHDPL-3 Activity: PCCS1010 Cased Xi
ng at CH. 0.219KM (24m)
Project: PHDPL-3 Activity: PCCS1020 Mobln. &
Cased Xing at CH. 0.258KM (24m)
Project: PHDPL-3 Activity: PCCS1030 Mobn. &
Cased Xing at CH. 1.923KM (48m)
Project: PHDPL-3 Activity: PCCS1040 Mobln. &
Cased Xing at CH. 17.659KM (24m)
Project: PHDPL-3 Activity: PCCS1050 Mobln. &
Cased Xing at CH. 32.740KM (18m)
Project: PHDPL-3 Activity: PCCS1060 Mobln. &
Cased Xing at CH. 34.106KM (24m)
Project: PHDPL-3 Activity: PCCS1070 Mobln. &
Cased Xing at CH. 37.550KM (36m)
Project: PHDPL-3 Activity: PCCS1080 Mobln. &
Cased Xing at CH. 37.895KM (18m)
Project: PHDPL-3 Activity: PCCS1090 Mobln. &
Cased Xing at CH. 38.100KM (18m)
Project: PHDPL-3 Activity: PCCS1100 Mobln. &
Cased Xing at CH. 42.994KM (36m)
Project: PHDPL-3 Activity: PCCS1110 Mobln. &
Cased Xing at CH. 51.270KM (18m)
Project: PHDPL-3 Activity: PCCS1120 Mobln. &
Cased Xing at CH. 53.506KM (18m)
Project: PHDPL-3 Activity: PCCS1130 Mobln. &
Cased Xing at CH. 70.703KM (18m)
Project: PHDPL-3 Activity: PCCS1140 Mobln. &
Cased Xing at CH. 83.915KM (18m)
Project: PHDPL-3 Activity: PCCS1150 Mobln. &
Cased Xing at CH. 86.104KM (30m)
Project: PHDPL-3 Activity: PCCS1160 Mobln. &
Cased Xing at CH. 87.083KM (18m)
Project: PHDPL-3 Activity: PCCS1330 Cased Xi
ng at CH. 144.55KM (24m)
Project: PHDPL-3 Activity: PCCS1340 Mobln. &
Cased Xing at CH. 152.15KM (60m)
Project: PHDPL-3 Activity: PCCS1350 Mobln. &
Cased Xing at CH. 152.68KM (24m)
Project: PHDPL-3 Activity: PCCS1360 Mobln. &
Cased Xing at CH. 154.10KM (24m)
Project: PHDPL-3 Activity: PCCS1370 Mobln. &
Cased Xing at CH. 154.64KM (60m)
Project: PHDPL-3 Activity: PCCS1380 Mobln. &
Cased Xing at CH. 162.24KM (24m)
Project: PHDPL-3 Activity: PCCS1390 Mobln. &
Cased Xing at CH. 162.478KM (24m)
Project: PHDPL-3 Activity: PCCS1400 Mobln. &
Cased Xing at CH. 163.163KM (24m)
Project: PHDPL-3 Activity: PCCS1410 Mobln. &
Cased Xing at CH. 166.631KM (24m)
Project: PHDPL-3 Activity: PCCS1420 Mobln. &
Cased Xing at CH. 171.372KM (36m)
Project: PHDPL-3 Activity: PCCS1430 Mobln. &
Cased Xing at CH. 173.536KM (18m)
Project: PHDPL-3 Activity: PCCS1440 Mobln. &
Cased Xing at CH. 173.631KM (18m)
Project: PHDPL-3 Activity: PCMSP1170 Cased Cr
ossings (See details in separate head)
Project: PHDPL-3 Activity: PCMSP2080 Mainline
Welding & Joint Coating
Project: PHDPL-3 Activity: PCMSP2090 Mainline
Lowering - In
Project: PHDPL-3 Activity: PCMSP2100 Mobilize
HDPE & OFC Blowing Agency
Project: PHDPL-3 Activity: PCMSP2110 HDPE Duc
t Laying
Project: PHDPL-3 Activity: PCMSP2120 OFC Blow
ing
Project: PHDPL-3 Activity: PCMSP2130 Back Fil
ling
Project: PHDPL-3 Activity: PCMSP2140 Mobilize
TCP Work Agency
Project: PHDPL-3 Activity: PCMSP2150 TCP Work
Project: PHDPL-3 Activity: PCMSP2160 Cased Cr
ossings (See details in separate head)
Project: PHDPL-3 Activity: PCMSP2170 HDD Cros
sings (See details in separate head)
Project: PHDPL-3 Activity: PCMSP2180 Submerge
d Xings (See details in separate head)
Project: PHDPL-3 Activity: PCMSP2190 Hydrotes
ting
Project: PHDPL-3 Activity: PCMSP2200 Mobilize
Swabbing & Calliper Survey Agency
Project: PHDPL-3 Activity: PCMSP2210 Swabbing
& Calliper Survey
Project: PHDPL-3 Activity: PCMSP2220 Tie-Ins
Project: PHDPL-3 Activity: PCMSP2230 Final Cl
ean up & Restoration
Project: PHDPL-3 Activity: PECS1010 Issue Ca
sed Xings AFC Drawings by IOCL
Project: PHDPL-3 Activity: PECS2010 Issue Ca
sed Xings AFC Drawings by IOCL
Project: PHDPL-3 Activity: PEHS1010 Issue Ca
sed Xings AFC Drawings by IOCL
Project: PHDPL-3 Activity: PEOE010 Prepare & Issue
MR - Joint Coating Materials
Project: PHDPL-3 Activity: PEOE020 Prepare & Issue
MR - Welding Consumables
Project: PHDPL-3 Activity: PGGO000 Notification to
Start
Project: PHDPL-3 Activity: PGGO010 Kick-Off Meeting
Project: PHDPL-3 Activity: PGGO130 Project Completi
on Date
Project: PHDPL-3 Activity: PHDDS2110 Mobln. &
HDD Xing at CH. 342.25KM (90m)
Project: PHDPL-3 Activity: PMOJC000 Prepare
& Issue Enquiry
Project: PHDPL-3 Activity: PMOJC010 Receive
Bids
Project: PHDPL-3 Activity: PMOJC020 Techno-C
ommercial Evaluation
Project: PHDPL-3 Activity: PMOJC030 Place Or
der
Project: PHDPL-3 Activity: PMOJC040 Issue PO
/PR
Project: PHDPL-3 Activity: PMOJC050 Part Del
ivery
Project: PHDPL-3 Activity: PMOJC060 Complete
Delivery
Project: PHDPL-3 Activity: PMOWC000 Prepare
& Issue Enquiry
Project: PHDPL-3 Activity: PMOWC010 Receive
Bids
Project: PHDPL-3 Activity: PMOWC020 Techno-C
ommercial Evaluation
Project: PHDPL-3 Activity: PMOWC030 Place Or
der
Project: PHDPL-3 Activity: PMOWC040 Issue PO
/PR
Project: PHDPL-3 Activity: PMOWC050 Part Del
ivery
Project: PHDPL-3 Activity: PMOWC060 Complete
Delivery
Project: PHDPL-3 Activity: PPCMOP000 Pre-comm
issioning
Project: PHDPL-3 Activity: PSOCCW000 Prepare
& Issue Tender
Project: PHDPL-3 Activity: PSOCCW010 Receive
Bids
Project: PHDPL-3 Activity: PSOCCW020 Techno-C
ommercial Evaluation
Project: PHDPL-3 Activity: PSOCCW030 Negotiat
ion & Award Contract
Activities with unsatisfied constraints..........................0
Activities with unsatisfied relationships........................0
Activities with external dates...................................0