G.L G.L G.L G.

PLINTH BEAM PLINTH BEAM PLINTH BEAM

BOTHWAYS ,TOP &


BOTTOM

BOTHWAYS BOTHWAYS

P.C.C. 1:5:10 P.C.C. 1:5:10


100mm THK 100mm THK

SAND FILLING SAND FILLING


SECTION OF FOOTING F1 SECTION OF COMBINED FOOTING CF1/CF2 SECTION OF FOOTING F2
OF SIZE 7'0" X 7'0" (COLUMN PLACEMENT DIMENSIONS SHALL BE AS PER THE PLAN)
OF SIZE 6'0" X 6'0"

G.L
G.L G.L G.L

PLINTH BEAM
PLINTH BEAM PLINTH BEAM PLINTH BEAM

BOTHWAYS BOTHWAYS TOP AND BOTTOM BOTHWAYS


BOTHWAYS TOP AND BOTTOM

P.C.C. 1:5:10 P.C.C. 1:5:10


100mm THK P.C.C. 1:5:10 100mm THK P.C.C. 1:5:10
100mm THK 100mm THK

SAND FILLING
SAND FILLING SAND FILLING
4" THK
4" THK 4" THK
SAND FILLING

SECTION OF FOOTING F1-N SECTION OF FOOTING F2C OF SIZE 6'0" X 6'0" SECTION OF FOOTING F2-N OF SIZE 6'0" X 6'0" SECTION OF FOOTING F3
OF SIZE 7'0" X 7'0" OF SIZE 5'0" X 5'0"
G.L
G.L
PLINTH BEAM
PLINTH BEAM
IMPORTANT NOTE:
IN NO CASE THE FLOOR SLAB OF THE SEPTIC TANK/SUMP BE LOWER
THAN THE DEPTH OF THE FOORINGS.THE FLOOR SLAB SHALL MATCH
WITH THE DEPTH OF THE FOOTINGS.

NOTES:
BOTHWAYS 1. CHECK ALL DIMENSIONS, ELEVATIONS IMMEDIATELY, REPORT ANY
DISCREPANY, CONFLICTS OR ERROR ,PRIOR TO COMMENCEMENT OF
BOTHWAYS WORK.
P.C.C. 1:5:10 TOP AND BOTTOM
100mm THK 2. EARTH BELOW FOUNDATION SLAB TO BE COMPACTED TO A DRY
DENSITY OF 95 %.

P.C.C. 1:5:10 3.ALL DIMENSIONS ARE IN FOOT & INCHES


100mm THK 4.CLEAR COVER FOR : BEAM - 25mm, COLUMNS 40mm, SLABS 25mm
5. RCC M20 GRADE CONCRETE WITH MINIMUM CEMENT CONTENT OF
320 Kg/cu. m AND MAXIMUM WATER CEMENT RATIO OF 0.5 TO BE
SAND FILLING ADOPTED .
SAND FILLING 4" THK 6. FOUNDATION DESIGNED FOR G+3 FLOORS ONLY

SECTION OF FOOTING F4 SECTION OF FOOTING F3 -EN R.C.C DETAILS OF FOOTINGS 7. SBC OF THE SOIL IS TAKEN AS 12.5 TONNES/SQ.M
OF SIZE 4'0" X 4'0" OF SIZE 5'0" X 5'0"