You can store copying requirements at every level in copying control. Copying
requirements contain the specific requirements for each business process and
can be stored at every level. The reference document can only be created if
all these requirements have been met.
a. Header level copying requirement 001 checks, for instance, whether the
sold to party in the source and the target document are the same.
b. Item level copying requirement 301 checks, for instance, whether the item
that is to be used as a copy has a reason for rejection or completed status.
c. Schedule line level copying requirements 501 ensures that only schedule
lines with an open quantity greater than zero are copied.
a. Data transfer routines these routines control how fields are copied from
the preceding document.
Possible scenarios:
inquiry - order
quotation - order