Max / Min Grout Pad depths

Bridge
Longitudinal Slope of Girder 1% 1% 1% 1% 1%

Transverse slope of girder 6% 6% 6% 6% 6%


Bearing Length parallel to cross
beam 450 450 450 450 450
Bearing length parallel to girder
longitudinal axis 350 350 350 350 350
Top Grout layer at bearing
centreline 40 40 40 40 40

Min thickness of top grout layer 24.8 24.8 24.8 24.8 24.8

Max thickness of top grout layer 55.3 55.3 55.3 55.3 55.3
assumed grout max /min levels
is<15mm or >70mm OK OK OK OK OK
Longitudinal slope of pier
crosshead 0% 0% 0% 0% 0%
Transverse slope of pier
crosshead 6% 6% 6% 6% 6%
Bearing Length parallel to cross
beam 450 450 450 450 450
Bearing length parallel to girder
longitudinal axis 350 350 350 350 350
Bottom grout layer at bearing
centreline 35 35 35 35 35
Min thickness of bottom grout
layer 21.5 21.5 21.5 21.5 21.5
Max thickness of bottom grout
layer 48.5 48.5 48.5 48.5 48.5
assumed grout max /min levels
is<15mm or >70mm OK OK OK OK OK

Depth of Bearing 250 250 250 250 250


Depth from Crossbeam to
girder at bearing centroid 325 325 325 325 325

Surfacing
Deck thickness
Girder Depth 1200
Total depth from surfacing to
crossbeam 1525 325 325 325 325
1% 1%

6% 6%

450 450

350 350

40 40

24.8 24.8

55.3 55.3

OK OK

0% 0%

6% 6%

450 450

350 350

35 35

21.5 21.5

48.5 48.5

OK OK

250 250

325 325

325 325
Girder Geometry
SPAN 1
GIRDER LENGTHS
Dimensions on Control Line
S 21.5 m (perimeter length of section)
R 105 m
0.2048 rad
Lr 21.462 m measured to centre of piers along Radius intersection

G1 G2 G3 G4 G5 G6 G7
Girder offset (m) from
Control Line at Pier A 7.69 5.54 3.39 1.24 -0.91 -3.06 -5.21
Girder offset (m) from
Control Line at Pier B 7.66 5.51 3.36 1.21 -0.94 -3.09 -5.24
Length between Piers
based on Pier A 23.034 22.595 22.155 21.716 21.276 20.837 20.398
r' -0.030 -0.030 -0.030 -0.030 -0.030 -0.030 -0.030
x -0.003 -0.003 -0.003 -0.003 -0.003 -0.003 -0.003
y -0.030 -0.030 -0.030 -0.030 -0.030 -0.030 -0.030
Length between centres of
(Lg) piers at girder offsets 23.031 22.592 22.152 21.713 21.273 20.834 20.394
Distance from pier A
centreline to edge of girder -0.28 -0.28 -0.28 -0.28 -0.28 -0.28 -0.28
Distance from pier B
centreline to edge of girder 0.22 0.22 0.22 0.22 0.22 0.22 0.22
Girder Length 23.091 22.652 22.212 21.773 21.333 20.894 20.454

GIRDER SLOPES
RL at control line at Pier A 4.997
Slope of Pier A 3%
RL at surfacing level above
girders at Pier A 5.228 5.163 5.099 5.034 4.970 4.905 4.841
Depth to Top of Girder at
Pier A -0.235 -0.235 -0.235 -0.235 -0.235 -0.235 -0.235
(A) Top of Girder at Pier A 4.993 4.928 4.864 4.799 4.735 4.670 4.606

RL at control line at Pier B 4.681


Slope of Pier B 3%
RL at surfacing level above
girders at Pier B 4.911 4.846 4.782 4.717 4.653 4.588 4.524
Depth to Top of Girder at
Pier B -0.220 -0.220 -0.220 -0.220 -0.220 -0.220 -0.220
(B) Top of Girder at Pier B 4.691 4.626 4.562 4.497 4.433 4.368 4.304

Girder Slope = (A-B)/L 1.31% 1.34% 1.36% 1.39% 1.42% 1.45% 1.48%

GIRDER RL
RL at Edge of girder at
Pier A 4.996 4.932 4.868 4.803 4.739 4.674 4.610
RL at Edge of girder at
Pier B 4.688 4.623 4.559 4.494 4.430 4.365 4.301

Lg = {(L1+(R2-R1)sin(/2))2+(R2-R1)cos(/2)2}0.5

Lg

L1

R1
R2

P/8112274/S Bridge/345289522.xls Span 1 08:10:44 02/13/2017


Girder Geometry
SPAN 2
GIRDER LENGTHS
Dimensions on Control Line
S 21.5 m (perimeter length of section)
R 105 m
0.2048 rad
Lr 21.462 m measured to centre of piers along Radius intersection

G1 G2 G3 G4 G5 G6 G7
Girder offset (m) from
Control Line at Pier A 7.685 5.535 3.385 1.235 -0.915 -3.065 -5.215
Girder offset (m) from
Control Line at Pier B 7.685 5.535 3.385 1.235 -0.915 -3.065 -5.215
Length between Piers
based on Pier A 23.033 22.594 22.154 21.715 21.275 20.836 20.396
r' 0.000 0.000 0.000 0.000 0.000 0.000 0.000
x 0.000 0.000 0.000 0.000 0.000 0.000 0.000
y 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Length between centres of
(Lg) piers at girder offsets 23.033 22.594 22.154 21.715 21.275 20.836 20.396
Distance from pier A
centreline to edge of girder 0.22 0.22 0.22 0.22 0.22 0.22 0.22
Distance from pier B
centreline to edge of girder 0.22 0.22 0.22 0.22 0.22 0.22 0.22
Girder Length 22.593 22.154 21.714 21.275 20.835 20.396 19.956

GIRDER SLOPES
RL at control line at Pier A 4.681
Slope of Pier A 3%
RL at surfacing level above
girders at Pier A 4.912 4.847 4.783 4.718 4.654 4.589 4.525
Depth to Top of Girder at
Pier A -0.235 -0.235 -0.235 -0.235 -0.235 -0.235 -0.235
(A) Top of Girder at Pier A 4.677 4.612 4.548 4.483 4.419 4.354 4.290

RL at control line at Pier B 4.364


Slope of Pier B 3%
RL at surfacing level above
girders at Pier B 4.595 4.530 4.466 4.401 4.337 4.272 4.208
Depth to Top of Girder at
Pier B -0.220 -0.220 -0.220 -0.220 -0.220 -0.220 -0.220
(B) Top of Girder at Pier B 4.375 4.310 4.246 4.181 4.117 4.052 3.988

Girder Slope = (A-B)/L 1.31% 1.34% 1.36% 1.39% 1.42% 1.45% 1.48%

GIRDER RL
RL at Edge of girder at
Pier A 4.674 4.609 4.545 4.480 4.415 4.351 4.286
RL at Edge of girder at
Pier B 4.372 4.307 4.243 4.178 4.113 4.049 3.984

Lg = {(L1+(R2-R1)sin(/2))2+(R2-R1)cos(/2)2}0.5

Lg

L1

R1
R2

P/8112274/S Bridge/345289522.xls Span 2 08:10:44 02/13/2017


Girder Geometry
SPAN 4
GIRDER LENGTHS
Dimensions on Control Line
S 21.5 m (perimeter length of section)
R 80 m
0.2688 rad
Lr 21.435 m measured to centre of piers along Radius intersection

G1 G2 G3 G4 G5 G6 G7
Girder offset (m) from
Control Line at Pier A 7.192 4.97 2.748 0.526 -1.696 -3.918 -6.14
Girder offset (m) from
Control Line at Pier B 7.13 4.665 2.255 -0.165 -2.595 -5.035 -7.485
Length between Piers
based on Pier A 23.362 22.767 22.172 21.576 20.981 20.386 19.790
r' -0.062 -0.305 -0.493 -0.691 -0.899 -1.117 -1.345
x -0.008 -0.041 -0.066 -0.093 -0.120 -0.150 -0.180
y -0.061 -0.302 -0.489 -0.685 -0.891 -1.107 -1.333
Length between centres of
(Lg) piers at girder offsets 23.354 22.728 22.111 21.495 20.880 20.266 19.655
Distance from pier A
centreline to edge of girder 0.22 0.22 0.22 0.22 0.22 0.22 0.22
Distance from pier B
centreline to edge of girder -0.28 -0.28 -0.28 -0.28 -0.28 -0.28 -0.28
Girder Length 23.414 22.788 22.171 21.555 20.940 20.326 19.715

GIRDER SLOPES
RL at control line at Pier A 4.048
Slope of Pier A 3%
RL at surfacing level above
girders at Pier A 4.264 4.197 4.130 4.064 3.997 3.930 3.864
Depth to Top of Girder at
Pier A -0.205 -0.205 -0.205 -0.205 -0.205 -0.205 -0.205
(A) Top of Girder at Pier A 4.059 3.992 3.925 3.859 3.792 3.725 3.659

RL at control line at Pier B 3.731


Slope of Pier B 3%
RL at surfacing level above
girders at Pier B 3.945 3.871 3.799 3.726 3.653 3.580 3.506
Depth to Top of Girder at
Pier B -0.205 -0.205 -0.205 -0.205 -0.205 -0.205 -0.205
(B) Top of Girder at Pier B 3.740 3.666 3.594 3.521 3.448 3.375 3.301

Girder Slope = (A-B)/L 1.37% 1.44% 1.50% 1.57% 1.65% 1.73% 1.82%

GIRDER RL
RL at Edge of girder at
Pier A 4.056 3.989 3.922 3.855 3.788 3.722 3.655
RL at Edge of girder at
Pier B 3.744 3.670 3.598 3.525 3.453 3.380 3.307

Lg = {(L1+(R2-R1)sin(/2))2+(R2-R1)cos(/2)2}0.5

Lg

L1

R1
R2

P/8112274/S Bridge/345289522.xls Span 4 08:10:44 02/13/2017