Professional Documents
Culture Documents
th th th
Paper published in 16 SEAGC, 8 11 May 2007, Kuala Lumpur.
Abstract: Conventional instrumentation method of incorporating high temperature-resistant strain gauges into the heat-cured
production process of spun piles is extremely unpopular due to high cost of these gauges and the uncertainty over their ability to
survive the pile production and driving processes. Due to these difficulties, the engineering community has been using an approximate
instrumentation method for the past few decades, by installing an instrumented steel pipe into the hollow core of spun piles followed
by cement grout infilling. The shortcoming of this method is the infilling of cement grout substantially alters the structural properties of
the piles, thus rendering their load-response behaviour significantly different from that of the actual working piles. This paper
highlights the application of Global Strain Extensometer technology, a state-of-the-art deformation monitoring system for monitoring
loads and displacements at various levels along the pile shaft and toe of instrumented piles. Recent case histories are presented to
demonstrate the advantages of this novel instrumentation technology for spun piles. Results show high quality, reliable and consistent
data, clearly far exceeding the capability of both conventional and approximate methods.
1
TM
th th th
Paper published in 16 SEAGC, 8 11 May 2007, Kuala Lumpur.
where:
N (blows/30cm) (Pile head)
Qu is the ultimate bearing capacity of the pile, kN; 0 50 100 150
Existing Ground Level
0
Ks is the empirical design factor relating ultimate shaft load to
SPT values, kN/ m2 per SPT blow; Strain Gauges Lev. A
Ns is the SPT value for the pile shaft, blows/300mm;
As is the perimeter area of the shaft, m2;
5
Clay
Kb is the empirical design factor relating ultimate endbearing Hollow annular space
load to SPT values, kN/ m2 per SPT blow; Spun Pile
10
Nb is the SPT value for the pile base, blows/300mm;
Ab is the cross-sectional area of the pile base, m2. Strain Gauges Lev. B
15
For bored piles, instrumentation using sacrificial cast-in
Depth (m)
vibrating wire strain gauges and mechanical tell-tales which Sandy
Clay Strain Gauges Lev. C
permit for monitoring of axial loads and movements at various 20
levels down the pile shaft including the pile toe level had been
practiced successfully within limits of accuracy posed by
constraints inherent of the installation method, in this region for Strain Gauges Lev. D
25
many decades, allowing insight evaluation of Ks and Kb factors, Sandy
Silt
including well documented history of The Design of Strain Gauges Lev. E
Foundations for Suntec City, Singapore (S.F.Chan & Peter 30 Strain Gauges Lev. F
C.S.Lee, 1990, S.F.Chan, 2004). Recent use of Global Strain Pile toe at 30.0 m depth
Extensometers (Glostrext) Method for bored piles in this region Legends:
denotes high temperature - resistant
(H.M. A.Aziz & S.K. Lee, 2005, 2006) also provides an excellent SI borehole log
Strain Gauges
alternative means for similar purpose, but with the capability of denotes Pile Joint
producing a more reliable performance and accurate results.
For precast driven piles, the application of instrumented full- Fig. 1: Diagrammatic illustration of conventional spun pile
scale static load tests is far more challenging than their bored pile instrumentation scheme
counterparts due to significant difference in method of pile
installation. Due to practical shortcoming of conventional 3.2 Approximate Instrumentation Method
instrumentation method and the lack of innovation in this area,
instrumented full-scale static load tests are in fact rarely used in Due to the difficulties of using the conventional method, the
driven pile application in this region. Therefore, the far lacking engineering community for spun pile industry has been using an
driven pile industry is long due for a better technology to approximate instrumentation method for the past few decades, by
revolutionize the methodology in the acquisition of design data in installing either an instrumented reinforcement cage or an
a more accurate and reliable way, to catch up with the evolution instrumented pipe, into the hollow core of spun piles followed by
in the design methods. cement grout infilling (Fig. 2(a)).
N (blows/30cm) (Pile head)
0 50 100 150
Existing Ground Level
3 CONVENTIONAL AND APPROXIMATE METHODS 0
2
TM
th th th
Paper published in 16 SEAGC, 8 11 May 2007, Kuala Lumpur.
Fig. 2(b) shows typical sequence of spun pile installation by (c) Structural shortening measurement of the test piles are not
jack-in method, commonly used vibrating wire strain gauges representative of the actual working piles;
mounted to steel pipe, lowering of instrumented pipe into the (d) Structural integrity of the original pile cannot be reliably
annular space of the test pile followed by cement grout infilling. ascertained, particularly performance of pile joints, during
As this approximate method is comparatively more the static load test; and
convenient to be implemented than the conventional method, it (e) Significant time loss due to grout infilling and curing
was widely practiced in this region for the past few decades. process, beside the environmental unfriendly nature of this
Some contract specifications also ask for the inclusion of method.
conventional sleeved rod extensometers (depending on the space
available) to monitor the pile shortening reading during the static 4 THE STATE-OF-THE-ART GLOBAL STRAIN
load tests. Either using an instrumented reinforcement cage or an EXTENSOMETER TECHNOLOGY
instrumented pipe, with or without the added-in sleeved rod
extensometers, the end product after the cement grout infilling is To address the challenges and difficulties posed by the
more towards a solid pile, as shown in Fig. 2(c). conventional and approximate methods, Global Strain
Extensometer technology for spun piles had been developed,
improved and field tested over the past 3 years.
3
TM
th th th
Paper published in 16 SEAGC, 8 11 May 2007, Kuala Lumpur.
With the instrumentation set-up as described in Fig. 3, the (iv) Significant cost and time saving, as the additional cage and
state-of-the-art Global Strain Extensometers system is able to cement grout infilling are not required;
measure shortening and strains over an entire section of the test (v) The technology is extremely environmental friendly, as the
pile during each loading steps of a typical static pile load test, sensors are retrievable, and no messing around with cement
thus it integrates the strain over a larger and more representative grouts; and
sample. (vi) Mass implementation of spun piles instrumentation is now
made viable with this technology, to capture representative
and reliable data in large quantities to assist engineers to
N (blows/30cm) (Pile head) build up a reliable databank for better design and safety.
0 50 100 150
0
Anchored Lev. 0 Existing Ground Level
Global Strain Gauge Lev. A
Anchored Lev. 1 Extensometer Lev. 1 5 CASE HISTORIES
5
Clay
5.1 Application of Global Strain Extensometer technology for
Global Strain Gauge Lev. B driven prestressed spun concrete piles
10
Hollow annular space
Spun Pile S.Krishnan & S.K. Lee, (2006) reported an interesting case of
Anchored Lev. 2 Extensometer Lev. 2
pile instrumentation and monitoring works using this technology
in the pre-production pile testing programme for the US$ 800
15
Global Strain Gauge Lev. C million 1400MW Coal Fired Jimah Power Plant Project in Negeri
Depth (m)
Sandy
Sembilan, Malaysia. The pile instrumentation schemes adopted
Clay Anchored Lev. 3 Extensometer Lev. 3 for the pre-production spun pile testing programme are
20
graphically represented in Fig. 4(a) and Fig. 4(b). The pre-
Global Strain Gauge Lev. D
production prestressed spun concrete piles TP3C was installed
Anchored Lev. 4 Extensometer Lev. 4 with an 11-ton BSP hydraulic impact hammer while piles TP5,
25
Sandy Global Strain Gauge Lev. E TP6, TP7 and TP9 were installed with a 9-ton Junttan hydraulic
Silt
Anchored Lev. 5 Extensometer Lev. 5 impact hammer. Preboring was carried out over the upper 12m
Global Strain Gauge Lev. F for piles TP3C and TP5. The structural properties of these driven
30 Anchored Lev. 6 Extensometer Lev. 6
Pile toe at 30.0 m depth prestressed spun concrete piles are summarized in Table 1.
Legends:
denotes Glostrext anchored level Table 1: Prestressed Spun Concrete Pile Properties
SI borehole log denotes Glostrext Sensor
denotes Pile Joint Test Nominal Wall Pile Prestressing
Pile Diameter Thickness Length Bar
Fig. 3: Schematic diagram of typical instrumented spun No. (mm) (mm) (m) (9mm )
pile using Global Strain Extensometer technology TP3C 600 100 38.9 14 no.
TP5 500 90 38.1 10 no.
4.2 Advantages of using the State-of-the-Art Global Strain TP6 500 90 17.5 10 no.
Extensometer technology TP7 500 90 17.5 15 no.
TP9 400 80 41.7 8 no.
Due to the significant difference in the methodology evolution,
from conventional sacrificial cast-in method to a new retrievable
post-install approach, the Global Strain Extensometer technology
Platform Level RL +5.5m MLSD
has been proven via a large number of full-scale load tests to be a I I I I
0 I
I
I
I I I I I
reliable and powerful pile load testing and data interpretation Hydraulic
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
5 Sand Fill
tool, capable of leading the spun pile instrumentation industry to I I I I I I
I I I I
I I
I I
-------- - I I I I
- -- -- -- -- -- -- -- -
20 - -- -- -- -- -- -- -- -
(i) The technology enables installation of instrumentation after
Depth (m)
- -- -- -- -- -- -- -- -
- -- -- -- -- -- -- -- -
25
pile-driving and thus virtually eliminates the risk of x x x x x
x x x x x
instrument damage during pile production and installation; 30 Sandy
x x x x x
Silt
(ii) The post-install nature of the method empowers engineers to 35
x xx x
x x x x x
x x x x x
x x
40
foundation piles using pile driving/installation records and x x
Hard
x x x x x
x x
TP 3C TP 5 TP 9
site investigation data as guides; 45 x x x x
Layer
x x x x x
Legends:
4
TM
th th th
Paper published in 16 SEAGC, 8 11 May 2007, Kuala Lumpur.
1500
10
------- - I I
600
------ I I
------- -
Depth (m)
------ I I
------- - I I
------ I I
------- - I I
15 ------ I I
300
- - Clay
----- - I I
------ I I
------- -
------ TP 6 TP 7
------- -
20 ------
------- - Legends: 0
------
------- -
------ 0 5 10 15 20 25
------- - GloStrExt Anchored Level
------ Pile Toe Upward Displacement (mm)
25 ------- -
------
Global Strain Gauge
Soil Profile Pile Joint Fig. 4(d): Pile Head Tension Load versus Pile Toe Upward
I
Bitumen Slip Coating
I Displacement for TP6 and TP7 at Jimah site
To Pull Out Frame
N.T.S
1500
TP6 TP6
Pile Head Stress (N/mm )
TP7
2
10 50 TP7
8 40
1500
6 30
TP7 4 20
Pile Head Tension Load (kN )
1200
2 10
0 0
0 300 600 900 1200 1500 1800 2100 0 300 600 900 1200 1500 1800 2100
900 -6 -6
Axial Tensile Strain (x 10 ) Axial Tensile Strain (x 10 )
TP6
Loads ( kN) Loads ( kN)
0 200 400 600 800 0 400 800 1200 1600
600 0 0
Depth below platform level (m)
Depth below platform level (m)
5 5
300
10 10
0
0 1 2 3 4 5 6 15 15
5
TM
th th th
Paper published in 16 SEAGC, 8 11 May 2007, Kuala Lumpur.
90
TP6(coated): 0.0m to 8.5m depth (Sandfill)
TP7(plain): 0.0m to 8.5m depth (Sandfill)
Mobilised Unit Shaft Friction ( kN/m )
2
60
45
30
15
0
0 5 10 15 20 25
Average Upward Movement (mm) of Pile between soil stratum
4 s pun pile
10 hollow core
12
16
18
Fig. 5(c): Instrumentation and monitoring test set-up for PTP1
18.5 m Extensometer Lev. 3 (RL -16.0m) at Melaka site
20
Sandy
Clay
22 21.5 m Global Strain Gauge Lev. D (RL -19.0m) Pile head settlement and pile settlement at various depths
24
including pile toe (derived by subtracting the structural
24.5 m Extensometer Lev. 4 (RL -22.0m) shortening at corresponding depth from the pile head settlement)
26 25.5 m Global Strain Gauge Lev. E (RL -23.0m)
SandySilt
26.5 m Extensometer Lev. 5 (RL -24.0m)
are presented in Fig. 5(d).
28 27.5 m Global Strain Gauge Lev. F (RL -25.0m) In the pile test analysis, it is highly recommended in practical
28.5 m Extensometer Lev. 6 (RL -26.0m)
29.0 m Global Strain Gauge Lev. G (RL -26.5m) terms to obtain the pile concrete modulus, Ec value directly from
30 29.5 m Extensometer Lev. 7 (RL -27.0m)
6
TM
th th th
Paper published in 16 SEAGC, 8 11 May 2007, Kuala Lumpur.
6000 6000
6 CONCLUSIONS AND RECCOMMENDATIONS
5000 5000
Pile Head Load (kN )
4000 4000
methods.
3000
`
3000
`
The advanced features and novel nature of the Global Strain
2000 2000 Extensometer technology also made it an improved alternative of
1000 1000 instrumentation approach to the following research areas, where
0 0 it could be too cumbersome and sometimes economically not
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 viable if using conventional and approximate methods:
Pile Settlement (mm) at 18.5m depth Pile Settlement (mm) at 24.5m depth
(a) Fully instrumented piles for long term load transfer
6000 6000 characteristic study, including both positive and negative
5000 5000 skin friction development with time;
Pile Head Load (kN )
4000 4000 (b) Study of locked-in stresses in piles due to handling and
3000 3000 installation process, particular suitable for jacked-in piles;
`
2000
`
2000
(c) Fully instrumented piles for study of influence due to
1000 1000
installation process of adjacent piles;
0
(d) Study of pile joints performance under loadings;
0
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50 (e) Mass implementation of spun piles instrumentation in fast-
Pile Toe Settlement (mm)
Pile Settlement (mm) at 26.5m depth track projects.
Fig. 5(d): Pile head settlement and pile settlement at various
depths including pile toe for PTP1 at Melaka site The authors sincerely hope that the information presented
serves to initiate a mechanism (via further R&D) for continuous
development of an improved empirical method of designing piles
Applied pile head load, Pt ,
measured by VW Load Cell
60 based on results of full-scale instrumented load test using a better
Secant Modulus, E c ( kN/mm2 )
0.0 m
55
technology to revolutionize the methodology in the acquisition of
50
1.0 m
2.0 m
Level A Global Strain
Extensometer to verify and back- 45
pile test and design data in a more accurate and reliable way for
calculate concrete modulus, Ec,
s pun pile using PA = Pt 40 the betterment of our foundation industry and engineering
35
profession.
30
25
20
0 200 400 600 800 1000 1200
Measured Axial Strain ( x 10 ) at Lev A
-6
ACKNOWLEDGEMENT
Loads ( kN) 600
0 1000 2000 3000 4000 5000 6000
Mobilised Unit Shaft Friction ( kN/m 2 )
0
500 Lev A to Lev C
Lev C to Lev D
The authors acknowledge various clients and friends for the
Depth below platform level (m)
5
400 Lev D to Lev E opportunities to be involved in the projects cited in the paper.
Lev E to lev F
10
300 Lev F to Lev G Our sincere and special thanks to Dr. H.M. Abdul Aziz, Ir.
15
200
Sridhar Krishnan and Er. Christopher Pang.
20
100
25
0
30
0 5 10 15 20 25 30 35 40 45 50 REFERENCES
Movement of Pile between soil stratum ( mm )
Fig. 5(e): Level A sensor arrangement for verifying and back- Aziz, H.M.A. & Lee, S.K. 2005. Innovation in Instrumented Test
calculate Ec values, modulus-strain curve, load Piles in Malaysia : Application of Global Strain
distribution curve and mobilized unit shaft friction Extensometer (GLOSTREXT) Method for Instrumented
versus average movement of pile between soil Bored Piles in Malaysia, Bulletin of the Institution of
stratum measured using Global Strain Extensometer Engineers, Malaysia, October 2005 issue. pp 10-19
technology for PTP1 at Melaka site Aziz H.M.A. & Lee, S.K. 2006. Application of Global Strain
Extensometer (GLOSTREXT) Method for Instrumented
Bored Piles in Malaysia. Proceedings of 10th International
A conspicuous benefit which can be derived from the plotting Conference on Piling and Deep Foundations, Amsterdam, pp
shown in Fig. 5(d) and Fig. 5(e) is that they enable engineers and 669-767
researchers nowadays to have an opportunity to have an insight Chan, S.F. & Lee C.S. 1990. The Design of Foundations for
understanding on the relationship between the pile settlement Suntec City, Singapore, Proceedings of Conference on Deep
along the pile depth and the corresponding load transfer Foundation Practice, Singapore.
characteristics.
7
TM
th th th
Paper published in 16 SEAGC, 8 11 May 2007, Kuala Lumpur.