ID Task Name Duration Total Slack Late Start Late Finish Predecessors 2015 2016 2017

M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
1 Project Milestone Summary 461 days 0 days Mon 8/22/16 Mon 8/22/16
2 Project Start (Zero Date) 0 days 461 days Mon 8/22/16 Mon 8/22/16 Nov 17 '14
3 Project Engg. Completion 0 days 246 days Mon 8/22/16 Mon 8/22/16 21,30 Sep 11 '15
4 Project Procurement Completion 0 days 71 days Mon 8/22/16 Mon 8/22/16 44,58,70,79 May 13 '16
5 Project Mechanical Completion 0 days 17.75 days Mon 8/22/16 Mon 8/22/16 94 Jul 28 '16
6 Project Completion 0 days 0 days Mon 8/22/16 Mon 8/22/16 96 Aug 22 '16
7 Engineering 215 days -0.13 days Fri 11/14/14 Tue 4/26/16
8 Process Engineering 65 days -0.13 days Fri 11/14/14 Fri 2/13/15
9 Review Basic Engineering Package 20 days -0.13 days Fri 11/14/14 Fri 12/12/14
10 Prepare & Issue PFDs 10 days -0.13 days Fri 12/12/14 Fri 12/26/14 9
11 Prepare & Issue P&IDs 25 days -0.13 days Fri 12/26/14 Fri 1/30/15 10
12 Prepare & Issue Equipment Data 10 days -0.13 days Fri 1/30/15 Fri 2/13/15 11
Sheets
13 Mechanical Engineering 160 days 9.88 days Fri 2/13/15 Fri 12/25/15
14 Prepare & Issue Equipment Layouts 20 days 29.25 days Fri 3/13/15 Fri 4/10/15 11
15 Prepare & Issue GAD 40 days 29.25 days Fri 5/22/15 Fri 7/17/15 23
16 Prepare & Issue ISO 60 days 74.88 days Fri 9/18/15 Fri 12/11/15 15
17 Prepare & Issue MR - Compressor 10 days 49.88 days Fri 4/24/15 Fri 5/8/15 12
18 Prepare & Issue MR - Heat 10 days -0.13 days Fri 2/13/15 Fri 2/27/15 12
Exchangers
19 Prepare & Issue Preliminary MTO 15 days 38.75 days Thu 7/30/15 Thu 8/20/15 15
20 Prepare & Issue MRs for Bulk 10 days 38.75 days Thu 8/20/15 Thu 9/3/15 19
Piping Items
21 Prepare Final MTO 10 days 74.88 days Fri 12/11/15 Fri 12/25/15 16
22 Civil Engineering 45 days 29.25 days Fri 4/10/15 Tue 4/26/16
23 Prepare & Issue Plot Plan 30 days 29.25 days Fri 4/10/15 Fri 5/22/15 14
24 Prepare & Issue Equipment Fdn. 15 days 256.5 days Tue 4/5/16 Tue 4/26/16 23
Drgs.
25 Electrical & Instrumentation 215 days 29.25 days Fri 5/22/15 Fri 10/23/15
Engineering
26 Prepare & Issue SLD 40 days 134.25 days Fri 5/22/15 Fri 7/17/15
27 Prepare & Issue Area Classification 20 days 29.25 days Fri 7/17/15 Fri 8/14/15 26,15
Drgs.
28 Prepare & Issue E&I Cable Layouts 20 days 29.25 days Fri 8/14/15 Fri 9/11/15 27
29 Prepare & Issue MTO for E&I 10 days 29.25 days Fri 9/11/15 Fri 9/25/15 28
30 Prepare & Issue MRs for E&I Bulk 20 days 29.25 days Fri 9/25/15 Fri 10/23/15 29
items
31 Procurement 315 days -0.13 days Fri 2/27/15 Fri 5/13/16
32 Procurement of Equipment 315 days -0.13 days Fri 2/27/15 Fri 5/13/16
33 Procurement-Compressor 265 days 49.88 days Fri 5/8/15 Fri 5/13/16
34 Prepare & Issue Inquiry 10 days 49.88 days Fri 5/8/15 Fri 5/22/15 17
35 Receive Bids 30 days 49.88 days Fri 5/22/15 Fri 7/3/15 34
36 Prepare TBA 15 days 49.88 days Fri 7/3/15 Fri 7/24/15 35
37 Prepare CBA 5 days 49.88 days Fri 7/24/15 Fri 7/31/15 36

Task External Tasks Manual Task Finish-only Progress

Project Name : Gulam- MSP Split External Milestone Duration-only Deadline


Sch Start Date : Mon 11/17/14 Milestone Inactive Task Manual Summary Rollup Critical
Sch Finish Date : Mon 8/22/16
Summary Inactive Milestone Manual Summary Critical Split
Project Summary Inactive Summary Start-only Baseline

Gulam- MSP Page 1 of 3


ID Task Name Duration Total Slack Late Start Late Finish Predecessors 2015 2016 2017
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
38 Prepare & Issue LOI 10 days 49.88 days Fri 7/31/15 Fri 8/14/15 37
39 Prepare & Submit Vendor 30 days 49.88 days Fri 8/14/15 Fri 9/25/15 38
Drawings
40 Procure - Raw Material 40 days 49.88 days Fri 9/25/15 Fri 11/20/15 39
41 Manufacturing 100 days 49.88 days Fri 11/20/15 Fri 4/8/16 40
42 Factory Acceptance Test (FAT) 10 days 49.88 days Fri 4/8/16 Fri 4/22/16 41
43 Packaging & Despatch 5 days 49.88 days Fri 4/22/16 Fri 4/29/16 42
44 Delivery at Site 10 days 49.88 days Fri 4/29/16 Fri 5/13/16 43
45 Procurement-Heat Exchanger 315 days -0.13 days Fri 2/27/15 Fri 5/13/16
46 Prepare & Issue Inquiry 10 days -0.13 days Fri 2/27/15 Fri 3/13/15 18
47 Receive Bids 30 days -0.13 days Fri 3/13/15 Fri 4/24/15 46
48 Prepare TBA 15 days -0.13 days Fri 4/24/15 Fri 5/15/15 47
49 Prepare CBA 5 days -0.13 days Fri 5/15/15 Fri 5/22/15 48
50 Prepare & Issue LOI 10 days -0.13 days Fri 5/22/15 Fri 6/5/15 49
51 Open L/C 10 days -0.13 days Fri 6/5/15 Fri 6/19/15 50
52 Prepare & Submit Vendor 30 days -0.13 days Fri 6/19/15 Fri 7/31/15 51
Drawings
53 Procure - Raw Material 40 days -0.13 days Fri 7/31/15 Fri 9/25/15 52
54 Manufacturing 100 days -0.13 days Fri 9/25/15 Fri 2/12/16 53
55 Factory Acceptance Test (FAT) 10 days -0.13 days Fri 2/12/16 Fri 2/26/16 54
56 Packaging & FOB 15 days -0.13 days Fri 2/26/16 Fri 3/18/16 55
57 Shipping & Custom Clearance 30 days -0.13 days Fri 3/18/16 Fri 4/29/16 56
58 Delivery at Site 10 days -0.13 days Fri 4/29/16 Fri 5/13/16 57
59 Procurement of Bulk Items 155 days 38.75 days Thu 9/3/15 Fri 5/13/16
60 Procurement - Piping Bulk 145 days 38.75 days Thu 9/3/15 Fri 5/13/16
Items
61 Prepare & Issue Inquiry 10 days 38.75 days Thu 9/3/15 Thu 9/17/15 20
62 Receive Bids 20 days 38.75 days Thu 9/17/15 Thu 10/15/15 61
63 Prepare TBA 15 days 38.75 days Thu 10/15/15 Thu 11/5/15 62
64 Prepare CBA 5 days 38.75 days Thu 11/5/15 Thu 11/12/15 63
65 Prepare & Issue LOI 5 days 38.75 days Thu 11/12/15 Thu 11/19/15 64
66 Manufacturing 40 days 38.75 days Thu 11/19/15 Thu 1/14/16 65
67 Packaging & Despatch 5 days 38.75 days Thu 1/14/16 Thu 1/21/16 66
68 Delivery at Site 10 days 38.75 days Thu 1/21/16 Thu 2/4/16 67
69 Repeat Order Final MTO Piping 40 days 74.88 days Fri 12/25/15 Fri 2/19/16 21
items
70 Manufacturing & Delivery at Site 60 days 74.88 days Fri 2/19/16 Fri 5/13/16 69

71 Procurement - E&I Bulk Items 110 days 29.25 days Fri 10/23/15 Fri 3/25/16
72 Prepare & Issue Inquiry 10 days 29.25 days Fri 10/23/15 Fri 11/6/15 30
73 Receive Bids 20 days 29.25 days Fri 11/6/15 Fri 12/4/15 72
74 Prepare TBA 15 days 29.25 days Fri 12/4/15 Fri 12/25/15 73
75 Prepare CBA 5 days 29.25 days Fri 12/25/15 Fri 1/1/16 74
76 Prepare & Issue LOI 5 days 29.25 days Fri 1/1/16 Fri 1/8/16 75

Task External Tasks Manual Task Finish-only Progress

Project Name : Gulam- MSP Split External Milestone Duration-only Deadline


Sch Start Date : Mon 11/17/14 Milestone Inactive Task Manual Summary Rollup Critical
Sch Finish Date : Mon 8/22/16
Summary Inactive Milestone Manual Summary Critical Split
Project Summary Inactive Summary Start-only Baseline

Gulam- MSP Page 2 of 3


ID Task Name Duration Total Slack Late Start Late Finish Predecessors 2015 2016 2017
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
77 Manufacturing 40 days 29.25 days Fri 1/8/16 Fri 3/4/16 76
78 Packaging & Despatch 5 days 29.25 days Fri 3/4/16 Fri 3/11/16 77
79 Delivery at Site 10 days 29.25 days Fri 3/11/16 Fri 3/25/16 78
80 Construction 323.75 -0.13 days Thu 2/4/16 Wed 6/8/16
days
81 Construction of Civil Work 15 days 288.63 Tue 4/26/16 Fri 5/13/16
days
82 Construct Fdn for Compressor 10 days 293.63 days Mon 5/2/16 Fri 5/13/16 24
83 Construct Fdn for Heat Exchanger 15 days 288.63 days Tue 4/26/16 Fri 5/13/16 24
84 Mechanical Works 143.75 -0.13 days Thu 2/4/16 Wed 6/8/16
days
85 Install Compressor 20 days 56.13 days Fri 5/13/16 Wed 6/8/16 82,44
86 Install Heat Exchangers 20 days -0.13 days Fri 5/13/16 Wed 6/8/16 58,83
87 Fabrication & Erection of Pipe 90 days 43.63 days Thu 2/4/16 Thu 5/26/16 16,68,70FF+10
Racks & Pipe days
88 Electrical & Instrumentation Works 60 days 33 days Fri 3/25/16 Wed 6/8/16
89 E&I Cabling & Erection of E&I 60 days 33 days Fri 3/25/16 Wed 6/8/16 79,87FF+10
Items days
90 Hookup, Testing & 40 days -0.13 days Wed 6/8/16 Thu 7/28/16
Pre-commissioning
91 Hookup, Testing & 40 days -0.13 days Wed 6/8/16 Thu 7/28/16
Pre-commissioning
92 Hookup & Tie-Ins 10 days -0.13 days Wed 6/8/16 Tue 6/21/16 89,85,86
93 Loop Checking & Testing 15 days -0.13 days Tue 6/21/16 Fri 7/8/16 92
94 Precommissioning 15 days -0.13 days Fri 7/8/16 Thu 7/28/16 93
95 Commissioning & Startup 20 days -0.13 days Thu 7/28/16 Mon 8/22/16
96 Commissioning & Startup 20 days -0.13 days Thu 7/28/16 Mon 8/22/16 94

Task External Tasks Manual Task Finish-only Progress

Project Name : Gulam- MSP Split External Milestone Duration-only Deadline


Sch Start Date : Mon 11/17/14 Milestone Inactive Task Manual Summary Rollup Critical
Sch Finish Date : Mon 8/22/16
Summary Inactive Milestone Manual Summary Critical Split
Project Summary Inactive Summary Start-only Baseline