You are on page 1of 2

SR ACTIVITY ACTION REQUIRED RESPONSIBILITY

NO.
1. Landscaping Work Work Order and NCA TO CONFIRM THE
negotiation with Pak LANDSCAPING WORKS RATES AND
Shahid NEGOTIATE WITH PAK SHAHID FOR
Missing lights from THE LANDSCAPING WORK
BOQ
(125 lights)
2. Geysers Procurement Engineers estimate NCA TO PROVIDE THE
along with RECOMMENDATION FOR THE
recommendation for PURCHASE ALONG WITH THE ENGR.
the said for the ESTIAMTE AND RATE ANALYSIS
purchase
3. Chandeliers & Decorations New edited BOQ with LETTER FROM PRINCIPAL NCA WITH
the items to be THE LATEST BOQ
purchased from Ahmed
Traders
Replacement
recommendation for
the items excluded
from the initial BOQ
Inspection report of
Chandeliers
International
Inspection at Italy
4. Watch Tower Variation Order for Pak NCA TO GIVE RECOMMENDATION
Shahid or any other alternate FOR THE WATCH TOWER WORK-
ALONG WITH RATE ANALYSIS AND
ENGR. ESTIMATE FOR THE WORKS
5. Transformer Foundation Variation Order/ any other NCA TO GIVE
alternative for the works PROPOSAL/RECOMMENDATION FOR
THE WORKS
6. Exterior wooden Roof Variation order/any other NCA TO GIVE
Projection alternative PROPOSAL/RECOMMENDATION FOR
THE WORKS
7. Fibre Glass Coating Variation Order/ any other NCA TO GIVE
alternative for the works to PROPOSAL/RECOMMENDATION FOR
be added in any existing THE WORKS
vendor/or new contract
8. External Washrooms Variation Order/ any other NCA TO GIVE
alternative for the works to PROPOSAL/RECOMMENDATION FOR
be added in any existing THE WORKS
vendor/or new contract
9. Fire Fighting Pump Analysis and evaluation of NCA TO SEND RECOMMENDATION/
the existing options for the PROPOSAL ALONG WITH ENGR.
procurement, installation, ESTIMATE
testing and commissioning of
the firefighting pump