Professional Documents
Culture Documents
NATM
Prediction of geotechnical behaviour is often difficult, therefore it
is sometimes appropriate to adopt the observational method
approach, in which the design is reviewed during construction.
According to Peck observational method has the following
procedural steps:
Exploration sufficient to establish at least the general nature, pattern
and properties of the deposits, but not necessarily in detail
The assessment of the most probable conditions and the most
unfavourable conceivable deviations from these conditions, in this
assessment geology often play a major role
The establishment of the design based on a working hypothesis of
behaviour anticipated under the most probably conditions
The selection of quantities to be observed as construction proceeds
and the calculation of their anticipated values on the basis of the
working hypothesis
The calculation of values of the same quantities under the most
unfavourable conditions compatible with the available data concerning
the subsurface conditions
The selection in advance of a course of action or modification of
design for every foreseeable significant deviation of the observational
findings from those predicted on the basis of the working hypothesis
The measurement of quantities to be observed and the evaluation of
actual conditions
The modification of design to suit actual conditions
The method is inapplicable where there is no
possibility to alter the design during
construction. The ability to modify the design is
appropriate if the method is to be applied only
during construction and the focus is on the
temporary conditions.
However, there are situations where the method
could be applied after construction, e.g long-
term monitoring of dams and buildings.
Peck emphasises the importance of asking the
critical questions. These must ensure that the
observations are appropriate and meaningful.
The key is to combine comprehensiveness
with reliability, repeatability and simplicity.
Observations are often far more elaborate and
costly than necessary.
The Base Design developed in (c) will typically be based on
analysis, such as finite element.
Possible modes of failure particularly those of a sudden or
brittle nature, or those who could lead to progressive
collapse must be assessed carefully.
It is a fundamental element of the Observational Method to
overcome the limitations of analysis by addressing actual
conditions.
The design in (c) may therefore present difficulties
associated with the term most probably, and in practice (c)
has been interpreted as unlikely to be exceeded.
Some margin of conservatism is always necessary; it may
therefore be more appropriate base the design on a
moderately conservative approach. A moderately
conservative design would be less conservative than a
conventional design, but more conservative than one based
on Pecks most probable.
Feedback from Observations
Feedback and assessment from observations must be
timely in order to confirm predictions or to provide adequate
warning of any undue trends in ground movements or loadings.
There must be sufficient time to enable planned contingency
measures to be implemented effectively. This emphasises a
further aspect of the Observational Method.
Measurements of quantities must occur at the required times
during a construction sequence. It may be necessary to interrupt
construction progress and may even influence the way
construction is sequenced.
Other Observational Approaches
As set out by Peck, the procedures (a) (h) for the
Observational Method may be unnecessarily cumbersome and
often impossible to achieve.
Further, the most probable condition in (c) is very difficult to
find in a statistically reliable manner. Simpler versions of an
observational approach have been suggested, as e.g. by Muir
Wood.
Management of observational approaches are often described
in flowcharts, often including risk levels and responses.
System for Observational approach to tunnel design
Eurocode 7 (EC7) includes the following remarks concerning an
observational method.
Four requirements shall all be made before construction is started:
With the excavation of a tunnel the primary stress field in the rock
mass is changed into a more unfavourable secondary stress field.
Under the rock arch we understand those zones around a tunnel
where most of the time dependent stress rearrangement processes
takes place. This includes the plastic as well as the elastic behaving
zone.
1.Deformation of the
excavated tunnel surface/
Convergence tape
Surveying marks
2.Deformation of the ground
surrounding the tunnel/
Extensometer
3.Monitoring of ground
support element anchor/
Total anchor force
4.Monitoring of ground
support element
shotcrete shell/
Pressure cells
Embedments gauge
NATM Process on site
Main Pressure
where;
Pi = skin resistance
C = cohesion
= angle of internal friction
R = radius of the protective zone
r = radius of the cavity
P0 = H; overburden
Following the main principle of NATM, the protective ring around the cavity (R-r), is a load carrying
part of the structure. The carrying capacity of the rock arch is formulated as;
S R Cos S nR Sin
PiR =
b/2 b/2
where;
Pi = resistance of rock arch (t/m2)
S = length of shear plane (m)
R = shear strength of rock (t/m2)
= angle of internal friction (0)
b = height of shear zone (m)
nR = normal stress on shear plane (t/m2)
, R, nR, can be measured in laboratories, where as S
can be measured in meters , on a drawing made to scale.
Generally two separate supports are carried
out. The first is a flexible outer arch or
protective support designed to stabilize the
structure accordingly. It consists of a
systematically anchored rock arch with
surface protection, possibly reinforced by ribs
and closed by an invert.
The behaviour of the protective support and
the surrounding rock during the readjustment
process can be monitored by a measuring
system.
The second means of support is an inner concrete arch, generally not
carried out before the outer arch has reached equilibrium. In addition to
acting as a final, functional lining (for installation of tunnel equipment
etc.) its aim is to establish or increase the safety factors as necessary.
The resistance of the lining material (shotcrete) is:
d s
Pt =
s
sin s ( b / 2 )
E
The lining resistance is:
PiL = Pis + Pist
The anchors are acting with a radial
pressure:
f p
st st
Pi =
A
et
With the lateral pressure given by:
3 = pis + pist + piA
and with Mohrs envelope, the shear
resistance of the rock mass R and the
shear angle is determined, assuming that
the principal stresses are parallel and at
right angles to the excavation line.
The carrying capacity of the rock arch is
given by:
S cos S n sin
R R
Pi =
R
b/2 b/2
p cos
st st
af
Pi = A
et (b / 2)
The total carrying capacity of the outer arch is then:
Pi = Pi + Pi + Pi Pi min
w L R A
Numerical example for NATM
Tunnel size: 12.10 x 12.00 m
(fig.10)
H = 15.0 m overburden
according to tests on samples
found: = 27, c = 100 t/m
(three axial tests). When we
open a cavity the stress
equilibrium spoiled and for
establishing new equilibrium
condition achieved by
supporting as follows.
Use the supporting ring which
develops around the cavity after
excavation as a self-supporting
device and select a type of
supporting which can bear the
developed rock loads and
deformable when necessary.
Design the inner lining under
final loads
The (1) supporting system is capable of carrying safely the
loads, the (2) lining is for safety and to bear the additional
loads which are probable to develop after the supports are
installed.
Supporting will consists in this example:
a: Shotcrete (15+10) cm in layers by two shots
b: Bolts spaced 2.00 x 2.00 m in rings with diameter 26 mm.
c: Rib steel channel supports (2 x 14)
d: by ground supporting ring
To find the radius of disturbed zone R:
Talobre formula:
2sin
R
Values entered into the formula:
= 27
= 2.5 t/m
H = 15.0 m
P0 = H = 2.5 x 15.0 = 37.5 t/m
C = 100 t/m
R = 6.45 m
[ ]
2 sin 27
6.05 1sin 27
Pi = 100 cot g 27 + 100 cot 27 + 37.5 (1 sin 27 ) (
o o o
)
R 2 x 0.450
[
Pi = 100 1.96 + 100 1.96 + 37.5 (1 sin 27 ) ( o
R
)]
6.05 10.450
1 .66
6 .05
196 .3 + 217 .08 =0
R
1.66
196.3 6.05
=
217.08 R
R = 6.45 m
Shotcrete:
d = 25 cm
c28 = 160 kg/cm compressive strength shear in
concrete (assume 20% of c28)
the capacity carrying load
sh = 0.20 160 = 32 kg/cm = 320 t/m
d = thickness of shotcrete in (cm)
= /4 - /2 angle of shear plane with vertical
b = shear failure height of the cavity (see Fig.10)
sin 31.5 = 0.520;
b/2= r cos = 6.05xcos31.5=5.15
0.25 320
p =
c
= 29.9 t / m 2
0.52 5.15
i
bolts
Bolt 26 mm
St III, sh = 4000 kg/cm
Spacing=2x2 m
f = 5.3cm
5.3 4000
p =
b
= 0.53 kg/ cm2
200 200
i
p = 5.3 t / m
b
i
2
N = normal stress = 142 t/m
steel ribs
t = spacing 2.00 m read on X
Z = minor stress = 37.2 t/m
F = 2 20.4 cm = 40.8 cm =
0.00408 m
R = shear stress = 170 t/m
st = c 15 = 320 15 = 4800 t/m
read on Y
F st 0.00408 4800
Pi st = = = 36.56t / m
b 0.52 5.15 2.00
sin t
2
Connect AB and find the centre (W) draw the
circle. Tangent at the point B (BB) so
OB = Cohesion = 100 t/m
= internal friction angle (27)
R calculated (Talobre formula) as 6.45 m. Width of the
protective ring 6.45-6.05 = 0.4m drawn through A, B
and the intersection bisecting with the middle ring (C);
ABC shear failure line drawn and thus (S) measured.
Bolt length l = 4.00 m is taken and inclination
measured
Pi = pic + pib + pist = 29.9 + 5.3 + 36.56 = 70.26 t/m
bearing capacity of the
supporting ring
Sin = sin 27 = 0.450
Cos = cos 27 = 0.891
thus
S = 4.54 m (from figure 17)
= 27
b/2 = 5.15 m
R = 170 t/m
N = 142 t/m
enter the formula
p CR = 78.22 t / m 2
The resistance of the bolts (anchors) against the movement of the
shear body towards the cavity is:
a f sh cos
p =
b
et b/ 2
i