You are on page 1of 2

O F F S H O R E E U R O P E

Seawater membrane filtration used


to control scale in Syd Arne reservoir
Alistair M. Munro
Option to chemical injection Tony McMonagle
Alan Skinner
Weir Westgarth Ltd
he control of scale in offshore oil fields

T where filtered seawater is used to maintain


reservoir pressure has generally been
achieved by using squeeze chemicals and
inhibitors injected into the flowline of each
water producing well. The control of calcium
carbonate scales can be controlled using this
method. However, the presence of high levels of
Jim Hardy
Eon Stratton
Amerada Hess

manifolds and in downstream equipment or in the


barium and strontium in the formation water leads wellbore. The highest operational risk is that scal-
to a second form of scale production: namely ing downhole will impact on production. Syd Arne sulfate removal plant: the chemical
barium and strontium sulfate. This will occur In the long horizontal S. Arne wells, the poten- and cleaning package are on the right. The
when seawater containing sulfate comes into tial for scaling was greater than in a conventional SRP 1 module is on the bottom left, with the
contact with the formation water bearing the homogenous reservoir. Since effective inhibition membrane package on top.
strontium and barium ions. is costly and technically difficult, every possible
The plan to install a sea waterflood in the Syd alternative was considered in the design and oper- Plant designs should be modular for ease of
Arne reservoir created a potentially severe scal- ation of the waterflood system. It was considered installation on to an operating production
ing problem from barium sulfase. Analysis by financially and environmentally more prudent to platform.
Amerada Hess reservoir engineers determined remove the problem at source by the reduction of Abstracted seawater is best fed to the sulfate
there would be severe downhole scale forma- the sulfate content in the injection water. reduction package before de-aeration.
tion problems. The magnitude of the scale prob- Pipework from the seawater abstraction to
lem had the potential to seriously impact the module should be in non-ferrous materials
economics of the development. to minimize contamination of the membrane
The production wells were judged at highest system and reduce the module weights.
risk and in the absence of any preventative mea- Pre-heating of the feed water by the plat-
sures, downhole scaling due to seawater break- form cooling systems enhances the effi-
through could cause loss of oil production, ciency of the plant, but the variations in
make sliding sleeves inoperable, and ultimately possible flows. Thus, temperature ranges
require wells to be worked over. should be carefully considered during the
detailed design phase of the project.
Scale prediction The membrane system should not be sub-
Further analysis showed that the highest jected to a reversing of the differential pres-
potential mass amount of barite scaling would sure. System surges are difficult to avoid
occur at a mixing ratio of 20:80 FW:SW, 880 mg/l completely and devices to ensure that the
The lower section of SRP 2 is being lowered
at 115 C and 920 mg/l at 60 C, although signifi- onto the platform. This major lift, one of five,
product outlet is protected must be incorpo-
cant amounts were predicted over much of the was completed in 18 hours. rated into the design.
mixing range. The higher mass amount precipi- The cleaning system should clean each of the
tated at the lower temperature, representative of The use of membrane based sulfate removal streams with the minimum number of sub-
process conditions, was due to the lower solubility. technology was identified as the preferred tech- cleaning circuits to minimize off-line time.
The high scaling tendency meant that the scale nical option to manage the problem. Weir Shock dosing of chlorine to the feed seawa-
would form and deposit rapidly at the point of mix- Westgarth Ltd, the manufacturer for the applica- ter is preferable to continuous dosing.
ing of the incompatible water types. The scaling tion of the technology, which was patented by
reaction would have been difficult to inhibit using Marathon Oil, was selected as the contractor. The Marathon process
chemicals alone. A moderate potential for deposi- The use of membrane technology was pio-
tion of strontium sulfate was also identified. Operational lessons neered by Marathon Oil on the Brae A Field and
However, solutions adapted to control the more Weir Westgarth has the benefit of over 40 was designed to utilize a membrane capable of
serious barium sulfate problem also mitigated years experience in desalination processes with removing specific ions. Unlike reverse osmosis,
against the minor strontium sulfate scale risk. over 20 years related to membrane installations. which rejects all ions, the FILMTEC nanofiltra-
When untreated seawater meets formation Experience transferred from Marathon Brae and tion membrane specifically removes sulfate ions.
water containing barium, scaling is inevitable. The Weir Westgarths own installations, such as Agip The process technology requires seawater to
scale forms immediately downstream of the point Tiffany, provided considerations during retrofit be passed through the membrane at 20-30 bar,
of mixing, typically topsides, in the production designs: depending on the temperature of the feed
Reprinted with revisions to format, from the August 2001 edition of OFFSHORE
Copyright 2001 by PennWell Corporation
O F F S H O R E E U R O P E

stream. The membranes are capable of reducing Applied pressure varies and the main high
seawater sulfate levels from approximately 3000 pressure pumps are subject to variable back
ppm to less than 40 ppm. pressure to provide the quantity of water at the
The primary consideration in process design required pressure for the changing conditions
was to agree with Amerada Hess on the level of across the membrane system.
sulfate required in the product water and also the A super duplex steel, Zeron 100, was utilized
feed water temperature. The higher the temper- for the pipework system to eliminate ferrous
ature, the lower the pressure needed to maintain contamination and reduce the weight of the
the flux rate and the flow per unit area of mem- module. Zeron 100 duplex (UNS32760)
brane surface. At higher temperatures the sulfate pipework allowed reduced pipe diameters and
passage through the membrane and into the valve sizes because of the high velocity the
product water increases but the energy absorbed internal polished surfaces of this super duplex
decreases. material could utilize without significant pres-
On the Syd Arne project, Weir Westgarth sure losses. Plant processes were controlled Phase 2, the fabrication step.
worked to optimize feed temperature flow by centrally within the platform control room and
mixing warmed seawater from the platform linked into the platform computer systems. nized by all that the filtration required upstream
cooling system outlet with the main injection Since the water is taken before de-aeration, of the membranes required careful considera-
feed flow. The membrane rejection characteris- the ability to chlorinate the feed greatly reduces tion. The feed supply had been identified as being
the potential problems associated with bacterial affected by an annual algae bloom that lasted
contamination. The addition of sodium bisulfite from mid-spring through to late autumn. Pilot tri-
removes any free chlorine before the membrane als were conducted during the first few weeks of
system. Chemical cleaning of the membranes is the fasttrack first phase, to allow definition of the
carried out using in-situ connections to remove optimum cartridge filter arrangement and pro-
any scale formed within the membrane system posed intermediate filtration.
or any bacteria. The sulfate-reduced water is As a result of these trails, dual media filters
then passed to the de-aerator system where de- were provided as a part of the second phase.
oxygenation and chemical additives are made in These were located on the opposite side of the
The Toisa Lion conveying the packages to the the normal manner prior to injection. platform from the SRP plant, on a purpose built-
platform. Due to the high scaling potential of the Syd cantilever deck.
tics being temperature dependant increases the Arne reservoir, Amerada Hess ordered the first Due to the location, the lift limit in this area
sulfate passage by 100% for every 10 C rise in phase of a 120 000 b/d sulfate reduction pack- was reduced to 20 tons. As a result, the filters
temperature. age at the end of May 2000, on a 17-week deliv- were delivered as eight individual filters with a
ery program. This schedule was made possible separate central access/pipe manifold support
Mixture control by internal manufacturing capabilities for criti- structure, to which the filters were linked on site.
The design conditions for the Syd Arne plant cal path items such as pumps, valves, and the The membrane process plant for the reduction
were 10-24 C with three high pressure pumps, Zeron 100 super duplex material. of sulfate in seawater is now a tried and proven
each rated for 354 cu m/hr with a 270 meter devel- The plant was designed to operate in three 33% technology, helping to decrease the environmen-
oped head, along with a 750 kW motor running at capacity streams. The product water specification tal impact of reservoir development. The process
3000 rpm. By controlling the mix ratio of the feed was to reduce the sulfate level of 2,740 ppm, to has overcome scale formation problems in
water, the membranes can be operated in a steady less than 50 ppm, and was designed around injected wells using seawater, which is incompat-
state condition with respect to temperature. FILMTEC SR90 nanofiltration membrane ele- ible with formation water.
This allows a constant feed water pressure to ments. Fasttrack execution of this technology was
be applied to the membrane ensuring a 75% con- Phase 1of the plant was designed to provide possible through client-contractor partnering,
version of seawater feed to low sulfate product an initial stand-alone 40,000 b/d and was deliv- and by securing long lead item supply from inter-
water for injection. The residual 25% is dis- ered mid-October 2000. The program consisted nal manufacturing capabilities.
charged overboard and contains the sulfate ions of three fabricated modules, limited in weight to The use of membranes as a specific ion
removed from the feed stream. The 75% conver- 40 tons by the crane facilities on the platform. removal mechanism is the first of many areas in
sion of feed to product is achieved by a two-stage Phase 2 of the project, comprising an additional which membrane technology shows great
membrane process with 50% recovery over each 80,000 b/d capacity, was ordered by Amerada promise in ensuring that harmful discharges are
stage. Hess in October 2000, with a 26-week delivery. minimized. 
Because of the inter-relationship between This phase consisted of a further two modules.
temperature and output, the system must be To accommodate both phases of the plant,
able to vary the applied pressure to the mem- which had a combined wet weight of 228 tons,
brane in order to maintain a constant output with Amerada Hess undertook the strengthening and
Authors
Alistair M. Munro is Director, Sales and Marketing; Tony
changing temperature. The control of the mem- extension of an existing cantilever platform. McMonagle is the Project Manager; and Alan Skinner is the
brane system therefore incorporates analogue Manager, Sulfate Removal, all for Weir Westgarth Ltd.
loops to ensure that the reject to product ratio Filtration Jim Hardy is a Production Chemist, and Eon Stratton is the
stays constant. Prior to the start of the project, it was recog- Project Manager, both for Amerada Hess

*Trademark of The Dow Chemical Company Form No. 609-00376-202


CH 172-288-E-202

You might also like