Electrification of railway tracks plays an important role for reliable and pollution free operation of trains. Various instructions, circulars, letters
etc. are being issued time to time by Board/ RDSO/ Railways to keep Over Head Equipment (OHE) in good condition. During erection of OHE and its
operation and maintenance, various schedule of dimensions (SODs), manuals, reports, letters etc. are required to be referred.
For the convenience of OHE construction/maintenance staff CAMTECH has prepared this "databank on important guidelines, letters,
instructions, circulars etc. for OHE" which provides details and reference at the same place and may be used as and when required.
I am sure this databank will be useful for OHE construction as well as OHE maintenance and operation staff.
Participants during various seminar held at Gwalior requested to prepare a data bank for OHE. This "data bank of important guidelines,
letters, instructions, circulars etc. for OHE" prepared by CAMTECH gives the details on various items with their references at a glance in a
tabular format. The databank covers instructions regarding construction, maintenance and operation of Over Head Equipment (OHE) over
Indian Railways. Some items have been added on basis of field experience of field staff. It is expected that this databank will serve as a
"KNOWLEDGE BANK" for field staff maintaining OHE.
It is clarified that this databank does not supersede any existing provisions laid down by Railway Board/RDSO/ Zonal Railways. This
databank is for guidance only and it is not a statutory document.
I am thankful to Zonal Railways and specially to Shri Shiv Ranjan Gupta, SSE/EL of this organization who put all his efforts and
lifelong service experience in making this databank useful. I am also thankful to all field personnel who have helped us in preparing this
databank
Technological up-gradation & learning is a continuous process. Hence feel free to write to us for any addition or modification in this
report. We shall highly appreciate your contribution in this direction.
Foreword iii
Preface iv
Contents v
Correction Slip viii
1. Foundation 01
2. ELECTRICAL CLEARANCES 08
3. CADMIUM COPPER CATENARY W IRE 15
4. HARD DRAWN GROOVED COPPER (HDGC) CONTACT W IRE 17
5. TURN OUT & CROSS OVER 21
6. CURRENT COLLECTION TEST 25
7. BONDING & EARTHING 26
8. AUTO TENSIONING DEVICE (ATD) 31
9. INSULATED CADMIUM COPPER CATENARY 32
10. IMPLANTATION (SETTING DISTANCE) 33
11. TRACK CENTRE 38
12. HEIGHT OF FOB-ROB 40
13. POWER LINE CROSSING 42
14. STAINLESS STEEL W IRE ROPE 51
15. DROPPER AND ENCUMBRANCE 53
16. HEIGHT GAUGE 56
17. OVER DIMENSION CONSIGNMENT (ODC) 57
18. MAXIMUM MOVING DIMENSION (MMD) 59
Sr.No. Description Page No.
REFERENCE 120
ISSUE OF CORRECTION SLIP
The correction slips to be issued in future for this handbook will be numbered as follows:
Where XX is the serial number of the concerned correction slip (starting from 01 onwards).
Sr. No. Date of issue Page no. and Item no. modified Remarks
CAMTECH/E/16-17/Databank-OHE/1.0 1
1. FOUNDATION
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
2 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 3
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
4 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 5
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
6 CAMTECH/E/16-17/Databank-OHE/1.0
"Volume batching may be allowed only where weigh-batching is not practical and
provided accurate bulk densities of materials to be actually used in concrete have earlier
been established. Allowance for bulking shall be made in accordance with IS: 2386
(Part-3) (latest version). The mass volume relationship should be checked as frequently
as necessary. The frequency for the given job is being determined by Engineer-in-charge
to ensure that the specified grading is maintained."
4. Quality The job of quality control and quality assurance would involve quality audit of both the
Assurance inputs as well the outputs. Inputs are in the form of materials for concrete, workmanship
measures in all stages of batching mixing, transportation, placing, compaction and curing in order
to ensure proper performance, it Is necessary to inspect each step in concreting.
5. Compaction Concrete should be thoroughly compacted and fully worked around the reinforcement,
and curing around embedded fixture.
Curing is the process of preventing the loss of moisture from the concrete while
maintaining a satisfactory temperature regime. Exposed surface of concrete shall be kept
continuously wet condition by covering with a layer of sacking and kept continuously
wet for at least 10 days from the date of placing concrete.
6. Supervision Supervision is of extreme importance to check the concrete. Hence constant and strict
supervision of all the items of the construction is necessary during the mixing of the
concrete.
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 7
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
8 CAMTECH/E/16-17/Databank-OHE/1.0
2. ELECTRICAL CLEARENCES
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 9
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
10 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 11
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
12 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 13
ii. Less
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
14 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 15
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
16 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 17
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
18 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 19
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
20 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 21
5. TURNOUTS/CROSSOVERS
3. Obligatory structure
i. Turnout span & Turnout span Measure turnout span 54 m or less RDSO Maintenance
Crossed type
ii. Crossed type Measure turnout span Turnout spans as per Instruction
arrangement
arrangement Drg, ETI/OHE/G/02141 No.TI/MI/0028 Rev.-2
Rev.C dated 28.09.2001
ii. Track For best result, Track separation at obligatory Between 500 mm to 700
separation track separation structure mm
iv. Track As per site condition Track separation at obligatory Between 150 mm to 700
separation track separation structure mm
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
22 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 23
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
24 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 25
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
26 CAMTECH/E/16-17/Databank-OHE/1.0
ii. Bond Rail Bond/ Connects rail joints across two consecutive CAMTECH/E/2008/BE/1.0. April 2009.
Longitudinal lengths of rails. It is made of M.S. flat strip Chapter-2, para 2.1.2 on page-5
Bond of size 40 mm x 6 mm
iii. Bond Impedance Bond installed by S & T department, which CAMTECH/E/2008/BE/1.0. April 2009.
Bond provides a low impedance path for the Chapter-2, para 2.1.4 on page-6
traction return current and a relatively high Treatise Vol.-II, Part-III, 3.11.7 (Page-149)
impedance path for track circuit current
iv. Bonds Cross Bonds/ Between two rails of a track or two rails of CAMTECH/E/2008/BE/1.0. April 2009.
transverse bond an adjacent track. It is also called Chapter-2, para 2.1.3 on page-6
transverse bond. It is made of M.S. flat ACTM Vol.-II, Part-II, Appendix II 2.0
strip of size 40 mm x 6 mm (Page-51)
2. Bonds Signal Bond Across the rail joint provided by S&T * Treatise Vol.-II, Part-III, 3.11.7 (Page-
department to facilitate flow of track circuit 149)
current.
3. Bonds Track Bonding In station yards elsewhere, where a track is ACTM Vol.-II, Part-II, Appendix II 3.5
not wired for its entire length, it shall be (Page-53)
wired for a distance of up to 50 m beyond
the traction mast at which the over head
equipment has been terminated. Rail
bond/cross bond shall be provided for a
distance of up to 50 m beyond the last
traction mast.
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 27
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
28 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 29
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
30 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 31
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
32 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 33
Curve track: The minimum setting distance of masts including portals, head span masts etc. on curve is obtained by adding
the curve allowance and 150 mm slewing allowance to the setting distance. For Trunk routes and main lines,
where the speed may be increased in near future. Curve allowance for maximum speed of 200 kmph.
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
34 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 35
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
36 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 37
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
38 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 39
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
40 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 41
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
42 CAMTECH/E/16-17/Databank-OHE/1.0
I- Clause 17.3 (ACTM VoLII, Part.II), Appendix-IV (Regulations for Power Line Crossings of Railway Tracks 1987) to be
replaced as under:
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 43
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
44 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 45
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
46 CAMTECH/E/16-17/Databank-OHE/1.0
II - Clearance for Power Line Crossings Including Telephone Line Crossings of Railway Tracks (Para-11(i), Chapter-I,
Schedule I of SOD 2004 BG)
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 47
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
48 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 49
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
50 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 51
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
52 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 53
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
54 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 55
xx. Dropper Non-standard Droppers at girder bridges. Droppers are spaced as Treatise vol 2 part iii & iv Chapter
spans droppers per dropper calculations. 2 para 4.2.1 page 214
xxi. Encumb Normal Used at single cantilever 1.4 m ACTM, Vol-II, Part-II, Appendix-1
rance Encumbrance structures Item 9.0 (Page-17)
xxii. Encumb Overlaps Encumbrance of 0.4 m, 0.75 To get adequate Handbook on principle of Design
rance Encumbrance m and 0.9 m are used mechanical and electrical of 25 kv AC OHE Chapter -2, para
clearances 2.16, page- 41
xxiii. Encumb Over line Encumbrance of 0.6 m, 0.5 To get adequate electrical
rance structure m and 0.4 and 0.3 m are clearances
Encumbrance used
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
56 CAMTECH/E/16-17/Databank-OHE/1.0
Observation Action
1. Height gauge Height Height of the top member of level Not more ACTM, Vol-II, Part-II, Appendix -
gauge above the road than 4.67 m VII 2 (e) (Page-151)
2. Height gauge Minimum Minimum distance of rail height 8 m Question Bank of OHE (
distance gauge from the nearest track CAMTECH/E/13-14/QB/TRD/OHE/
1.0, Chapter-6- item 6.16
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 57
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
58 CAMTECH/E/16-17/Databank-OHE/1.0
iii. 'C' Class Gross clearance less than 200 mm 15 kmph speed
but more than 100 mm. restriction to be
A representative should imposed with OHE
accompany to supervise safe power must be
movement of the ODC switched off.
iv. No movement of ODC Gross clearance less than 100 mm ODC movement not
permitted
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 59
iii. Maximum height Maximum height above rail level for a 4.265 m Schedule of Dimension
above rail level width of 760 mm on either side of the (SOD) Schedule-I, Chapter-
centre of unloaded vehicle IV (A), 29 (Page-21)
(Destination boards for passenger vehicle
may project 76 mm above the dimensions
upto maximum height above rail level at
sides when empty)
2. Rolling Stock (3660 mm width) (EMU width is also 3660 mm)
i. Maximum Width Maximum width 3.66 m Schedule of Dimension
Moving (SOD) Schedule-I, Chapter-
Dimension IV (B), 1 (iv)(Page-23)
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
60 CAMTECH/E/16-17/Databank-OHE/1.0
iv. Maximum height Maximum height above rail level for a width 4.725 m Schedule of Dimension (SOD)
above rail level of 915 mm on either side of the center of Schedule-I, Chapter-IV (B), 4
unloaded vehicle (Page-23)
3. Rolling Stock (Locomotive
i. Maximum Maximum width Maximum width from 1170 mm above rail 3.25 m Schedule of Dimension (SOD)
Moving from rail level when level when fully loaded to a height of 3735 Schedule-I, Chapter-IV (C), 11
Dimension fully loaded and mm when empty. (iv) (Page-25)
empty
ii. Maximum height on Maximum height (above rail level for a width 4.265 m Schedule of Dimension (SOD)
either side of empty of 760 mm on either side of center of empty Schedule-I, Chapter-IV (C), 12
locomotive locomotive. (Page-25)
iii. Maximum width (X- Maximum width (X- Class locomotives) from 3.20 m Schedule of Dimension (SOD)
Class locomotives) 1145 mm above rail level when fully loaded to Schedule-I, Chapter-IV (C),
a height of 3735 mm when empty. 14(iv) (Page-25)
iv. Maximum height Maximum height (X-Class locomotives) 4.47 m Schedule of Dimension (SOD)
(above rail level for a width of 305 mm on Schedule-I, Chapter-IV (C),
either side of center of empty locomotive. 15,(Page-25)
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 61
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
62 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 63
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
64 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 65
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
66 CAMTECH/E/16-17/Databank-OHE/1.0
23. STAGGER
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 67
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
68 CAMTECH/E/16-17/Databank-OHE/1.0
24. SPAN
iii. Span Maximum difference of Maximum difference between two 18 m ACTM, Vol-II, Part-II, 5.5. (i)
span consecutive spans in main line. (Page -8)
iv. Span Span of cross type Maximum span length of anchor span of 54 m ACTM, Vol-II, Part-II, 5.5. (vi)
OHE, turn outs cross type OHE at turnouts. (Page -9)
v. Span Span length at level Maximum span length at level crossings 58.5 m ACTM, Vol-II, Part-II , 5.5.
crossings where earth wire is provided. (vii) (Page -9)
vi. Span Tramway OHE Maximum span length tramway type 63 m ACTM, Vol-II, Part-II, 24.1.2
Regulated Regulated OHE (Page -38). RDSO drg. no.
ETI/OHE/G/04203
vii. Span Tramway OHE Un- Maximum span length tramway type Un- 30 m ACTM, Vol-II, Part-II, 24.2.1
regulated regulated OHE (Page -38)
viii. Span Tramway OHE Un- Conventional OHE with contact catenary 31.5 m
regulated in station area wire, the maximum span may be increased
ix. Span Mast both side of track Mast located on both side of a track. It 4.5 m ACTM, Vol-II, Part-II, 18.4 (Page
shall be staggered -26)
x. Span Difficult locations Spans in rocky cuttings, girder bridges, No ACTM, Vol-II, Part-II , 5.5.(v)
location of mast on bridge piles and within standard (Page -9)
station area span
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 69
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
70 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 71
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
72 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 73
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
74 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 75
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
76 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 77
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
78 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 79
i. Short neutral speed Bi- directional 200 Km/hr As per Arthur Flury AG
section Neutral section manual
ii. Short neutral Diameter Diameter of new rod in good 24 mm
section
condition.
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
80 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 81
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
82 CAMTECH/E/16-17/Databank-OHE/1.0
30. INSULATOR
S.No Item Parameters Details Authority
Observation Action
1. Composite Insulator
i. Composite Use of 25 kV i. Use of only composite ESDD 0.3 i. Policy circular No. RB/Elect/ TrD
Insulator insulators on insulators of 1050 mm CD dated 04.2012
AC traction for stone pelting menace ii. Railway Board letter No.
system based areas with the approval of 2002/Elect.(G)/161/21 Vol.II
on Equivalent CEE dated 04.07.2012
Salt Deposit ii. Use of porcelain insulators iii. Ref: a. DSO's letter no.
Density of 1050 mm CD for other TI/OHE/INSCOM/SL/11/1 dated
(ESDD) test areas 04.01.2011
ii. Use of composite insulators ESDD > 0.3 b. RDSO's letter No.
of 1600 mm CD in all the TI/OHE/INS/GEN/12 dated
areas with the 07.06.2012.
approval of CEE c. This Office of even
Number dated 13.04.2010
iii. Severity of Method adopted is Brush Equivalent Salt Deposit RDSO Maintenance Instruction no.
pollution Wash of a polluted insulator Density (ESDD) as per TI/MI/040 (Rev.0) dated 05.04.2005
IS: 13134
2. Porcelain Insulator
i. Porcelain Failure of Check failure is due to i. Monkey/ Vulture RDSO Instruction no. TI/IN/0007
Insulator insulator external reasons electrocution (Rev.0) dated 07.09.2001
ii. Pantograph
entanglement
iii. Tree cutting
iv. Short circuit by
snake, stay wire etc.
v. Stone throwing by
miscreant
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 83
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
84 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 85
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
86 CAMTECH/E/16-17/Databank-OHE/1.0
31. TRACK
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 87
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
88 CAMTECH/E/16-17/Databank-OHE/1.0
33. PORTALS
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 89
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
90 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 91
35. INSPECTION
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
92 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 93
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
94 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 95
vi. Paint system Paint system shall be As per para 9 iii. RDSOs letter no. TI/CIV/GCP/08
carefully applied on the of specification dated-22.03.2012
corroded surface as per the
laid down safety norms of iv. RDSO specification no.TI/SPC/CIV/
Original Equipment POR/0080 (08/2008)
Manufacturer (OEM)
Note:
i. The anti corrosion paint shall be used on rusted structures if it is inevitable.
ii. Paint shall be applied over rusted surface of outdoor galvanized steel structures exposed to atmospheric
condition for several years and have started rusting.
iii. Masts, Structures, and other equipments of OHE and traction power supply exposed to atmosphere where
corrosion/rusting is surfacing
iv. Anti corrosion paint shall be applied over the rusted cantilever assembly judiciously over the rusted parts.
v. Paint system shall be carefully applied on the corroded surface as per the laid down safety norms of Original
Equipment Manufacturer.
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
96 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 97
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
98 CAMTECH/E/16-17/Databank-OHE/1.0
S.no. Section Running Nos. of Total Nos. % of Target date Action i. Railway Bd letter No.
date bad location location for plan 2008/Elect(G)/161/8/Punct
location attended attended remaining dated 07.10.2011
location ii. AM/L's DO letter No.
2008/Elect(G)/161/8/ Punct.
dtd. 08.09.10
iii. Board's letter No 2008/
Elect(G)/161/8/Punct dtd.
28.09.10
3. Population of predictive maintenance Tools:
Railway Division Oliver-G Thermo vision GPS mapping for i. Railway Bd letter No.
camera Netra Car 2008/Elect(G)/161/8/Punct
dated 07.10.2011
ii. AM/L's DO letter No.
2008/Elect(G)/161/8/ Punct.
dtd. 08.09.10
iii. Board's letter No 2008/
Elect(G)/161/8/Punct dtd.
28.09.10
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 99
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
100 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 101
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
102 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 103
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
104 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 105
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
106 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 107
i. Competency Opening of isolator Station Master/ Assistant Station Master/ ACTM para Railway Board letter no.
certificate to during emergency Pointsmen should be issued with 20970-5 modified 2001/Electrical(G)/138/4 Pt.
pointsmen competency certificate, after giving dated- 10.01.2013
practical training to enable them to operate Advanced correction slip no. 24
specific isolator under instructions of dated-10.01.2013
Traction Power Controller (TPC)
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
108 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 109
iii. Testing Testing of tools Ropes, come-along clamps, tirfor etc should be tested once in six months
at least, in the presence of SSE/JE and record of such tests maintained in
each depot
2. Documents to be kept with OHE Supervisors for Work on OHE
i. Lay out plan Keeping of drawing A Complete set of structure erection drawings, lay out plans, Treatise (OHE) page
sectioning diagram, SWR and general supply diagram etc 159
pertaining to the overhead equipment under his charge ACTM Volume- II, Part
ii. Responsibility Responsibility of i. Ensure that all safety rules prescribed are actually observed by I, para-20333 page - 87
of SSE/JE SSE/JE (OHE) or in the staff when carrying out work on traction installations.
(OHE) his absence the ii. Duty of the supervisor to remind the staff periodically of the
senior most official various safety rules to be observed at work site
in-charge of the
work
3. Permit to work
i. Commencing PTW shall be taken Before commencing work on any part of the dead OHE or within 2 Treatise (OHE) page
of work m of live OHE, a permit to work shall be obtained from TPC or 159
other authorized person ACTM Volume- II, Part
I, para-20334 page - 87
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
110 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 111
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
112 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 113
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
114 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 115
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
116 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 117
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
118 CAMTECH/E/16-17/Databank-OHE/1.0
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
CAMTECH/E/16-17/Databank-OHE/1.0 119
Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE May, 2016
120 CAMTECH/E/16-17/Databank-OHE/1.0
REFRENCES
1. Manual of AC Traction Maintenance and Operation Volume II (PartI) Fixed Installations 1994
2. Manual of AC Traction Maintenance and Operation Volume II (PartII) Fixed Installations 1994
5. Indian Railways Schedule of Dimensions (SOD) 1676 mm Gauge (BG), Revised 2004
7. Details of Thermo Vision Camera 28th MSG TRD at SCR on Feb 2011 item no. 28.19
8. Circulars, Instructions, Correction Slips and letters etc issued by Railway Board New Delhi
9. Suggestion given by participant for various Railways during seminar conducted on 29.04.2016 at IRCAMTECH,
Gwalior.
May, 2016 Databank of Important Guidelines, Letters, Instructions, Circulars etc. for OHE
OUR OBJECTIVE
To upgrade maintenance technologies and methodologies and achieve improvement in productivity and performance
of all Railway assets and manpower which inter-alia would cover reliability, availability, utilisation and efficiency.
CAMTECH is continuing its efforts in the documentation and up-gradation of information on maintenance practices of
electrical assets. Over the years a large number of publications on electrical assets have been prepared in the form of
handbooks, pockets books, pamphlets & video films etc. These publications have been uploaded on the internet as well as
rail net.
For downloading these publications please do following:
1. On internet visit : www.rdso.indianrailways.gov.in
Go to Directorates CAMTECH Publications for download Electrical Engineering
2. On Railnet visit RDSO website at 10.100.2.19
Go to Directorates CAMTECH Publications for download Electrical Engineering