Professional Documents
Culture Documents
Mix
STEPS
IN
DETERMINING
AND
ANALYZING
ENERGY
MIX
ECONOMICS
1. Using
the
load
curve
(or
LDC),
determine
mix
on
the
basis
of
the
components
of
the
load
curve;
namely,
base-load,
mid-to-peak
load,
and
ancillary.
2
Load
Curves
and
LDC
Annual
Monthly
Daily
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
0
10,000
1
88
175
262
349
436
523
610
697
784
871
958
1045
1132
1219
1306
1393
1480
1567
1654
1741
1828
1915
2002
2089
2176
2263
2350
2437
2524
2611
2698
2785
2872
2959
3046
3133
3220
3307
3394
3481
3568
3655
3742
3829
3916
4003
4090
4177
4264
4351
4438
4525
4612
4699
Luzon
Demand
4786
4873
4960
5047
5134
5221
5308
5395
5482
5569
5656
5743
5830
5917
6004
6091
6178
6265
6352
6439
6526
6613
6700
6787
6874
6961
7048
7135
7222
7309
7396
7483
7570
7657
7744
7831
7918
8005
8092
8179
8266
8353
8440
8527
8614
8701
Energy
Mix
%
of
Peak
%
of
Gwh
From
LDC
Demand
Demand
2015 Luzon LF = 0.75 0.750 Per Unit Total Energy 0.750 100%
Per Unit mid- to peak 0.4444 44% Per Unit Mid- Peak Energy 0.194 26%
2. Determine
technologies
for
each
component
of
the
load
curve
using
basic
rule
of
power
system
economics
of
a
veracally
integrated
uality;
namely,
a)
the
base-load
component
are
supplied
by
technologies
with
high
capex
and
low
variable/fuel
costs;
and,
b)
mid-
to
peak
load
are
supplied
by
technologies
with
low
capex
and
high
variable/fuel
costs.
Moreover,
they
lend
themselves
to
cycling
and
on/o
operaaon
and
control
of
capacity
output
8
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
0
10,000
1
88
175
262
349
436
523
610
697
784
871
958
1045
1132
1219
1306
1393
1480
1567
1654
1741
1828
1915
2002
2089
2176
2263
2350
2437
2524
2611
2698
2785
2872
2959
3046
3133
3220
3307
3394
3481
3568
3655
3742
3829
3916
4003
4090
4177
4264
4351
4438
4525
4612
4699
Luzon
Demand
4786
4873
4960
5047
5134
5221
5308
5395
5482
5569
5656
5743
5830
5917
6004
6091
6178
6265
6352
6439
6526
6613
6700
6787
6874
6961
7048
7135
7222
7309
7396
7483
7570
7657
7744
7831
7918
8005
8092
8179
8266
8353
8440
8527
8614
8701
Technology
vs.
Load
Curve
Component
2015 Luzon LF = 0.75 0.750 Per Unit Total Energy 0.750 100%
Per Unit mid- to peak 0.4444 44% Per Unit Mid- Peak Energy 0.194 26%
2. Determine
technologies
for
each
component
of
the
load
curve
using
basic
rule
of
power
system
economics
of
a
veracally
integrated
uality;
namely,
a)
the
base-load
component
are
supplied
by
technologies
with
high
capex
and
low
variable/fuel
costs;
and,
b)
mid-
to
peak
load
are
supplied
by
technologies
with
low
capex
and
high
variable/fuel
costs.
Moreover,
they
lend
themselves
to
cycling
and
on/o
operaaon
and
control
of
capacity
output.
3. Distribute
mix
among
the
technologies
using
(1)
&
(2).
Opamize
mix
on
the
basis
of
the
following
criteria/constraints:
1) Cost-of
electricity
generaaon
2) Environmental
impact
3) Security
of
supply
a) Indigenous
vs.
imported
b) Weather
dependency
c) Geopoliacs
16
Must-dispatched
REs
Largest
Unit,
MW
647
Approx.
MW
(from
Load
Required
Net
%
of
Peak
%
of
Required
%
of
Gwh
%
of
peak
Capacity
Curve
and
LDC)
Capacity
Demand
Installed
Capacity
Demand
Factor
Required
Gross
Capacity
+Maintenance
Capacity
Base
Capacity
5,000
56%
5,000
6,173
1.00
69%
48%
74%
Mid-merit
Capacity
3,000
33%
3,000
3,508
26%
Peaking
Capacity
1,000
11%
1,000
1,169
73%
52%
100%
9,000
Total
Demand
Check
Rate
FIT
Load
Factor
Energy
Mix
Technologies
%
of
Required
%
of
Peak
%
of
Gwh
Installed
Must-
Demand
Demand
Geother- Base
Peaking
Total
Capacity
Coal
dispatched
Gas
Oil
mal
Hydro
Hydro
Check
REs
Base
Capacity
69%
48%
74%
30%
18%
48%
Mid-merit
Capacity
26%
Peaking
Capacity
73%
52%
12%
30%
10%
52%
Ancillary Capacity
27%
Energy
Mix
Peak
Load,
MW
9,000
2015
Year
Largest
Unit,
MW
647
Approx.
MW
(from
Load
Required
Net
%
of
Peak
%
of
Required
%
of
peak
Capacity
Curve
and
LDC)
Capacity
Demand
Installed
Capacity
Factor
Required
Gross
Capacity
+Maintenance
Capacity
Base
Capacity
5,000
56%
1.00
5,000
6,173
69%
48%
Mid-merit
Capacity
3,000
33%
3,000
3,508
Peaking
Capacity
1,000
11%
1,000
1,169
73%
52%
Ancillary
Capacity
18%
1,654
1,935
Mid-merit
Capacity
26%
73%
52%
12%
30%
10%
52%
Peaking
Capacity
Ancillary
Capacity
TOTAL
100%
30%
30%
30%
10%
100%
27%