SURFACE FACILITY
PHASE THREE
Material:
1st Layer:
Bonding material due the smooth face of the Brick Wall
contains PACTOMix BRC FF ready mixed mineral
bonding coat. Data sheet attached.
2nd layer:
White Cement
Fine Sand
Cementous dye
Work Procedure:
The 1st layer will be applied to the smooth face of the wall and left
to get dry.
2nd layer will be applied later.
QAQC Requirement:
In order to achieve the exacting quality required in the project and
this activity specially, GTH QAQC team shall follow PCH Standards,
Specifications and Design Basis.
QA team shall maintain implementing of PCH procedures and issuing
RFI to PMC for their comments.
QC shall assure the implementation of GTH, PMC and PMT comments
and implementation of standards without fail.
HALFAYA PROJECT
SURFACE FACILITY
PHASE THREE
HSE Requirement:
All works shall comply with safety procedure or instruction set out in
project safety plan and municipality rules and regulations. Basic PPE
to be worn by all staf and laborers.