You are on page 1of 5

Financial Solutions:

Partial Risk Guarantee


Finance, Economics & Urban Department December 2007
Sustainable Development Network Vice - Presidency

IDA Partial Risk Guarantee (PRG) to promote


Ugandas first Independent Power Producer
Ugandas first large scale Independent Power Producer (IPP) project, the Bujagali
The Bujagali Hydropower, will double power generation sources in Uganda, thus reducing
significantly the severe power shortage prevailing in the country, and fostering
project is a model
economic growth and wellbeing of its citizens. Supported by the World Bank Group
of the kind of (WBG) and other multilaterals, the project reached financial close in December 2007.
innovative funding _______________________________________________________________
solutions and
IDA provided a Partial Risk Guarantee sponsors are Industrial Promotion Services
partnerships that (PRG) for Uganda, in support of the (Kenya) Limited and SG Bujagali Holdings
will help resolve Bujagali 250MW hydropower plant project. Ltd, an affiliate of Sithe Global Power, LLC
Africas energy The project is being developed on an (USA). The project came at the time when
Independent Power Producer (IPP) basis, Uganda was facing major power shortage,
crises, making it one of the largest private sector which was having a significant constraining
Obiageli Ezekwesili, WB financed projects in the Sub-Saharan Africa impact on its industrial growth. The total
Africa Region VP so far and the first of its kind in Uganda. It is financing requirements for the project
developed, built, owned, and operated by equaled to US$ 798 million1.
Bujagali Electricity Limited (BEL), whose
Awarded the The
Africa Power Deal
of the Year 2007
by Euromoney
Project Finance
Magazine
Guarantors The Project Government has procured a 150MW of
short-term thermal power plants.
The Bujagali hydro project consists of
250MW run of the river power plant After unsuccessful attempts to develop
with a reservoir for daily storage, an the project in the late 90s, the
intake powerhouse complex, and a rock Government of Uganda initiated a new
filled dam with a maximum height of bidding process, with the support of the
about 30 meters, together with spillway World Bank, seeking a new project
and other associated works. It is being sponsor to develop the Bujagali project.
constructed on the Nile river, The tender process benefited from a
approximately 8 kilometers north of the significantly improved sector
Multilaterals and existing Nalubaale and Kiira power environment compared to the previous
Bilaterals plants. The project will sell electricity attempt. This included: (a) a reformed
to Uganda Electricity Transmission power sector structure, in which an
Company Limited (UETCL) under a independent electricity regulator has
30-year PPA, which was signed on been established, and generation and
December 13, 2005. The powerhouse distribution have been unbundled and
will be constructed to house 5x50MW concessioned to the private sector; (b)
Kaplan turbines. The small reservoir increased demand for electricity in the
will have an estimated surface area of face of declining generation output; (c)
388 hectares, extending back to the an improved sector financial structure,
tailrace areas of the Nalubaale and which is now under stress because of the
Kiira dam complex. The proposed current power sector crisis that has
project will require 238 hectares of required expensive thermal power
land take for the project facilities, of generation and has led to significant
which only 80 hectares would be for tariff increases; and (d) improved
new inundated areas adjacent to the governance standards.
Nile river. The land take includes 113
The current sponsors have been selected
hectares required for temporary and
following a transparent, international
ancillary facilities including temporary
competitive bidding process. In turn, the
haul roads, coffer dams, storage and
sponsors selected the Equipment,
quarries. Evacuation of electricity from
the proposed project will require the Procurement, Construction (EPC)
construction of about 100 kilometers of contractor on a competitive bidding basis
and required the contractors to sign up to
transmission line, as well as the
a Code of Conduct.
construction of a substation at
Kawanda, and the extension of the
Commercial Debt Mutundwe substation. Uganda Power Sector
Providers With the new Electricity Act passed by
Project Background the Parliament in 1999, the electricity
sector in Uganda went through
Ugandas main source of power is from
unbundling of the generation,
the Nalubaale and Kiira 380 MW dam
transmission, and distribution. A separate
complex, located at the mouth of Lake
company was established for each of
Victoria. However, electricity output
from this dam complex has declined them. Generation and distribution were
offered for a 20 year concession, and
gradually from around 270MW in 2002
awarded to Eskom Uganda Ltd, and
to 120MW on September 2006 in order
Umeme Ltd respectively. In addition an
to comply with the agreed curve i.e. the
independent Electricity Regulatory
water discharge regime agreed by all
Nile tributary counties. In comparison, in Authority (ERA) was established..
Equity Providers 2006 2007 estimated peak demand was The Bujagali project will support Uganda
about 350 - 380MW and about 290 MW s efforts to meet its electricity demand
at base load, thus resulting in persistent with least-cost power generation as
and acute power shortages which were compared to other energy options. Once
impacting economic growth. To commissioned in 2011, the project will
alleviate the shortage of power, the also relieve residual power shortages and
substantially reduce the need for more investment guarantee of up to US$115m
expensive emergency thermal power. for a 20 year period.
This will help contain potential rises in
electricity tariffs and allow industrial and Contractual Framework
Benefits of the Guarantee commercial users to reduce costs and
Key project agreements with Uganda
increase productivity, boosting economic
The IDA guarantee reduced the growth.
counter-parties are as follows:
perceived risk in the project to such
an extent as to allow commercial Implementation Agreement (IA)
debt to be mobilized. Project Cost and Financing between BEL and Government of
Structure Uganda/UETCL. The IA sets out the
The IDA guarantee improved the The total financing requirement for the terms on which the Government grants to
terms of the commercial bank loan project is US$798 1 million, of which BEL the concession to design, finance,
to the project company BEL, by US$ 627 million is financed with debt, construct, own, operate, and maintain the
enabling access to long term project.
and US$ 171 million financed by equity.
financing at lower cost, thus
allowing such reduction to be The debt equity ratio is around 78:22. Power Purchase Agreement (PPA)
factored in the PPA tariff, therefore The debt facility consists of a between BEL and Government of
reducing the cost to end users via commercial loan of US$115 million, Uganda/UETCL. The PPA sets the terms
lower tariff. for the production related to and sale of
from the Standard Chartered and Absa
banks, covered by the World Bank PRG. the electricity for the project contracted
It created new benchmark for capacity. Under the PPA, BEL agrees to
private sector investment in Sub- The rest of the financing came from
other multilaterals, such as IFC who sell all of its production exclusively to
Saharan Africa power generation.
committed US$130m in loans, the UETCL and UETCL agrees to purchase
It catalyzed co-financing of over European Investment Bank lend US$140 the projects contracted capacity.
US$750 million, by combining million, and the AfDB US$110m. Government Guarantee between
commercial debt over and above European DFIs financing consists of BEL and Government of
DFIs financing. IDA support was French development agency Proparco,
only US$115 million, or about 18% Uganda/[UETCL]. Whereas, the
with a US$73m loan, DEG/KfW of Government agrees to: (a) guarantee
of the total debt financing.
Germany with US$45m, and Dutch UETCLs payment obligations under the
financier FMO with US$73m. All senior PPA to BEL; and (b) indemnify BEL for
loans have a 16 year door-to-door any loss incurred as a result of UETCLs
maturity. obligations under the PPA becoming
The Multilateral Investment Guarantee void, unenforceable or ineffective.
Agency (MIGA) provided an equity

1
World Bank, Bujagali Project Appraisal
Document (PAD), April 2, 2007
Engineering, Procurement and contractor (and related parties, such as
Construction (EPC) Contract between subcontractors) unlawful;
BEL and Salini SPA. The proposed
Government imposed restrictions on
project will be built pursuant to a fixed
the ability of BEL to be paid or to
price, date certain, turnkey EPC
receive foreign currency or transfer funds
Contract. The EPC contractor, Salini
abroad; and
SPA (Italy) (with Alstom Power
Financing Plan Hydraulique (France) as a key Failure by the Government to fulfill
$ million subcontractor) was selected pursuant to a its payment obligations relating to
Debt_____________________ competitive EPC selection process in UETCLs purchase of power and
___ accordance with the EIB procurement termination payments due by UETCL.
IFC 130 rules.
EIB 130 The provision of the PRG was
Commercial Banks Operation and Maintenance (O&M) instrumental in catalyzing long term
(under PRG) 115 Agreement. The operation and commercial debt in Uganda, and reduced
AfDB 110 maintenance of the power plant will be risk for commercial debt without
European DFIs 142
conducted by a Sithe Global affiliated increasing government liability to an
Total Debt 627
company, incorporated in Uganda. extent that commercial debt could match
Equity____________________ DFIs maturities.
Direct Agreements. As usual in PPP
projects, the lenders entered into direct The PRG Agreements consist of: the
Project Sponsors 151
Government 20 agreements, amongst other, with the Guarantee Agreement, entered into
Total Equity 171 parties signatory to the PPA, IA, and between IDA and the commercial lenders
TOTAL SOURCES 798 Government Guarantee. The to BEL, which defines the scope of
Government Direct Agreement includes IDAs risk coverage and the trigger
customary clauses, including mechanics of the guarantee; the
Governments acknowledgements of the Indemnity Agreement, entered into
security interests created in the project between IDA and the Government of
for the benefit of the lenders and the Uganda, under which the state counter
step-in rights of the lenders in the guarantees IDA for any payments made
project. under the Guarantee Agreement, and the
Project Agreement, entered into between
IDA Partial Risk Guarantee (PRG) IDA and BEL, under which the company
covenants that it complies with World
The IDA PRG guarantees commercial
Bank environmental guidelines and other
lenders against debt service payment
applicable requirements.
defaults resulting from the Governments
failure to meet its payment obligations as Lead Financial Officers for this
stipulated under the IA and the operation:Mr Suman Babbar
Government Guarantee. The proposed (Sbabbar@worldbank.org) and Mr.
IDA PRG is non-accelerable; therefore, Raymond Bourdeaux (Tel: (202) 458-
principal and interest on the IDA 955; Rbourdeaux@worldbank)..
Guaranteed Facility between the
For more information on the World Bank
commercial banks and BEL would be
Guarantee program please visit our web
covered by IDA only as they become
site www.worldbank.org/guarantees or
due.
contact:
The IDA PRG covers the risk of debt
Upali Perera at (202) 458-2801, by
service default for the covered lenders
email at uperera@worldbank.org or
arising from the following categories of
events: Chalida Chararnsuk at (202) 458-8111,
by email cchararnsuk@worldbank.org.
Political force majeure events;
Changes in law and events making
the project contractual agreements
unenforceable or void, or making the
performance of BEL or its EPC
IDA Partial Risk Guarantee for Uganda: Bujagali Hydropower Project

Contractual Structure

You might also like