Professional Documents
Culture Documents
Three point estimate for activity P = pessimistic, M = most For triangular distribution or simple average: (P + M + O) / 3
TIME/COST Estimating
duration or cost likely, O = optimistic For beta distribution, PERT or weighted average: (P + 4M + O) / 6
Standard Deviation of activity (or cost) SDactivity (or activity ) For beta distribution: (P O) / 6
Variance of activity (or cost) Varactivity (or 2 activity ) For beta distribution: ((P O) / 6)2
Project Duration critical path activities only: (PERT1 + PERT2 + PERT3 + ) + (# of sigmas SDproject)
Estimating early in Planning Budgetary / Top Down / -10% to +25% from actual
Analogous
Estimating late in Planning Definitive / Bottom-up -5% to +10% or +/-10% from actual
Earned Value EV Value of work performed (to date) (PV of completed work)
Budget At Completion BAC Budget assigned for planned work PROJECT COST BASELINE
Estimate To Complete ETC (for atypical variance) Assumes future work to be ETC = BAC EV
performed as budgeted
COST Forecasting
ETC (for typical variance) Assumes past performance to ETC = (BAC EV) / CPI
continue throughout or ETC = EAC AC
Estimate At Completion EAC Use when original est. is flawed EAC = AC + Bottom-up ETC
EAC (for typical variance) Assumes past performance to EAC = AC + ETC = AC + (BAC EV) / CPI
continue throughout or EAC = BAC / CPI
Variance At Completion VAC Forecast of variance VAC = BAC EAC
To-Complete Performance Index TCPI Cost performance necessary to TCPI = (BAC EV) / (BAC AC)
achieve BAC or new EAC goal BASED ON BAC
Work remaining divided by funds or TCPI = (BAC EV) / (EAC AC)
remaining BASED ON NEW EAC
20092013 Q'vive, LLC Eric van der Meulen, PMP All rights reserved www.qvive.biz info@qvive.biz PFS0713.10 "PMBOK" and "PMP" are registered marks of Project Management Institute, Inc.