6 Prove CT polarity (Flick Test ) and carry out ratio checks to confirm CT
tolerance.
7 Confirm all secondary wiring is connected and there are no open
circuits.
Voltage Transformers
8 Confirm primary and secondary fuses are correctly rated.
Protection Relays
12 Confirm all connections are correct, secure and there are no open
circuits.
13 Confirm relay identification is correct and to design schedule.
14 Confirm relay type and settings are correct to latest revision of design
schedule.
15 Confirm that the vendor has completed primary injection tests and
operation of protection & lockout relays and that test sheets are
available.
348479047.doc
MPN PROJECTS Electrical
Static Commissioning Checksheet E-014B
Protection Relay Circuit Sheet 2 of 3
Remarks
348479047.doc
MPN PROJECTS Electrical
Static Commissioning Checksheet E-014B
Protection Relay Circuit Sheet 3 of 3
Signature
Name
Date
348479047.doc