You are on page 1of 18

Bill of Quantity

#1&#2 Boiler FOR STEPC - 2X 600 MW AT CUDDALORE


BOQ MT
NO. Item Working Description Unit Quant weight Remark

ity ( MT)
ONE Heat Flow Diagram
1 Boiler Steel Structure

Scope of Works: Installation of column, beam horizontal


& vertical brace and connector etc.. Contents of Works:
Main Structuresteel Foundation cleaning, lining; fabrication of pad block ;
1.1 set 2 8890 3200.4 6400.8
framing manufacturing, installation and removal of temporary
facilities; check, calibration, assembly, reinforcement,
hoisting, aligning and fixing of steel structure.

Scope of Works: Installation of platform, ladder, railing and


toe plate belong to the steam generator .
Stairs, platform, walkway,
Contents of Works: Check, assembly and installation of
1.2 handrails and the supports set 2 2010 785.7 1571.4
platform, support, ladder as well as fabrication and
for these
installation of railing and toe plate; process calibration of
platform, ladder and railing in the whole steam generator.

Scope of Works:Roof structure & inclosure , drum house


Over Roof of boiler &drum and storm sewer.etc. content of work: Calibration,
1.3 set 2 668 190.8 381.6
house assembly, installation of skin casing and its framework
,storm sewer erection etc..
Scope of Works:Installation of Boiler ceiling girde.
Contents of Works: lining; installation and removal of
1.4 Ceiling girde temporary facilities; check, calibration, assembly, set 2 760 370.6 741.2
reinforcement, hoisting, aligning and fixing of steel
structure.
Steel structure for gas &
scope of works:steel structure for maintaining gas &
duct,rail beam for electric
1.5 duct,rail beam for electric hoist.content of works: set 2 1600 2007.2 4014.4
hoist,furnace inspection
assemblage and erection, lifting, accessories device, etc
system
2 Boiler Proper

1/18
Scope of works: Installation of drum and its internal
devices, the underbed and u-type hanger rod etc.
Contents of Works: Inspection on internal and external
Drum (including inner
walls of drum; reassembly, hoisting, aligning and fixing of
2.1 Equipment and set 2 536 259.2 518.4
the center line; disassembly and assembly of internal
accessories)
devices; amendment of the underbed and hanger; cleaning
up, sealing of access door; installation of expansion
indicator and fabrication of the support.

Scope of Works: panel welding and erection,sealing


welding etc.
Contents of Works: 1. Line and regulate the panel arrays
Water-cool Wall System (
on the platform. 2. balls passing of per pipe of totall
2.2 piping, fitting, sealing part set 2 1762 799.2 1598.4
panel; the internal clean-up, inspection, lining of headers.
etc) and Header
3. Assembly and butt welding of pipes and panel; lifting,
aligning and fixing of components or panel; the inspection
and adjustment of overall dimensions of heaters.

Scope of Works: 1.Installation & welding of coil tube


arrays, roof tube, exclosure wall tube, header etc. 2.
sealing welding of superheat system etc..
Contents of Works: 1. Line and regulate the pipe or tube
Superheat System (piping,
arrays on the pipe calibration platform. 2.balls passing of
2.3 fitting, sealing part etc) set 2 3730 1615.45 3230.9
all tubes, the internal clean-up,inspection, lining of
and Header
headers. 3. Assembly and butt welding of pipes and tube
arrays; hoisting, aligning and fixing of components or
tubes; the inspection and adjustment of overall dimensions
of panel.

Scope of Works:1. Installation & welding of coil tube arrays


and components, header etc..2. sealing welding of reheat
system etc.
Reheat System ( piping, Contents of Works: 1. Line and regulate the pipe or tube
2.4 fitting,sealing part etc.) arrays on the pipe calibration platform. 2.balls passing of set 2 918 416.3 832.6
and Header panel , the internal clean-up, inspection, lining of headers.
3. Assembly and butt welding of pipes and tube arrays;
hoisting, aligning and fixing of components or tubes; the
inspection and adjustment of overall dimensions of panel.

2/18
Scope of Works: Installation & welding of coil tube arrays
and components, hanged pipe, header, wear-preventing
device etc. Contents of Works: 1. Line and regulate the
pipe or tube arrays on the pipe calibration platform. 2.
Economizers ( piping, balls passing of coil tube arrays ; the internal clean-up,
2.5 set 2 1600 848.6 1697.2
fitting, etc.) inspection, lining of headers. 3. Assembly and butt
welding of pipes and tube arrays; hoisting, aligning and
fixing of components or tubes; the inspection and
adjustment of overall dimensions 4.installation of wear-
preventing devices for economizer.

connection piping between


scope of work: welding, erection ,ball passing etc.
pressure parts(including
2.6 Content of work:transportation,welding,erection and set 2 960 277.2 554.4
support and
support etc.
hanger,accessories )
scope of work: welding, erection,sand blasting etc.
2.7 downcomer Content of work:transportation,welding,erection and set 2 256 128.8 257.6
support etc.

Scope of Works: header, support saddle of header etc..


down -comer water header
Contents of Works: 1.the internal clean-up, inspection,
2.8 and recirculating pump set 2 210 3.617 7.234
lining of headers. 2. hoisting, aligning, fixing, inspection
system
and adjustment and hydraulic test etc..

Scope of Works: buckstays and connectors etc..


2.9 Boiler Buckstay Contents of Works: hoisting, welding,placing and fixing of set 2 1040 361.2 722.4
buckstays and connectors.

Scope and contents of works: Inspection,assemble,


Hanger and support for installation, adjustment and fixing of rigid support and
2.10 set 2 960 168.3 336.6
pressure part hanger, spring support and hanger as well as support and
hanger of constant force.
instalation of sootblower, piping, including sandblast of
2.11 sootblower system pipes, valve, fitting and hangers & supports, hydraulic test set 2 520 106.1 212.2
steam blowing,commissioning etc.
2.12 Burners,oil gun,ignitor etc. Inspection and installation of burner and its support etc. set 2 720 161.9 323.8

scope of work: piping,vavle, fitting and hangers &


Fuel oil pipes, valves and
2.13 supports, sandblast of pipes, oil flushing ,hydraulic test, set 2 38 24.3 48.6
supports in boiler area
steam blowing etc. oil circulate with pressure, etc..

3/18
scope of work:installation of silencers,safe valve,drain
steam piping of safe valve,hangers & supports,pressure
2.14 accessories of boiler proper set 2 200 141.97 283.94
gauge,expansion indicator ,fitting, manhole gate, sealing
device,instrument sampling socket for I&C,etc

scope of work:sandblasting and installation of drain water


Pipes of boiler proper
pipe ,dozing pipe ,water level gauge and relative pipe
(including pipings ,valves,
2.15 ,recycle pipe of economizer ,spray pipe of super heater set 2 160 44.95 89.9
fitting ,hangers & supports
and reheater ,sampling pipe ,vent pipe ,blowdown pipe and
etc)
primary isolation valves etc..

Scope of Works:installation of key body, fitting, auxiliary


equipment,sealing device, supports & hangers and sealing
adjustment,assemblage and erection the Steam heated
airheater , the overall cold trial run.
2.16 Air Preheater Contents of Works: Clean-up of foundation; assembly of set 4 2400 1703 3406
rotor and housing; assembly, installation of heat transfer
elements and gearing devices; installation and adjustment
of sealing glands, oil system, firefighting soot-blowing or
cleaning devices;the overall cold trial run.

Scope of Works: 1.contractor shall provide temporary


booster pump,feeder pump, and piping,fitting,valves etc. 2.
Installation and removal of temporary equipment and pipe,
and system recovery
Contents of Works: 1. Installation and removal of
temporary water-feeding, water-draining, pressure-lifting,
Hydrostatic test for
2.17 chemical-dosing and heating pipes, compressed air set 2
pressure part
equipment and piping system. 2. Locking of exit, constant
hanger, inspection and cutting off of temporary fixtures; 3.
air test and defect treatment. 4. Defect treatment after
water feeding, flushing, pressure lifting, pressure
regulation, inspecting, pressure relief and pneumatic test.
5. System recovery.

4/18
1.The contractor supply all the temporary material,
equipment,chemicals, acid trough, water tank, pipes,
pump, valves and accessories ect... (including but not
limited checking, recover after cleaning, waste liquid
treatment and drain), 2. The contractor shall submit to
2.18 Chemical cleaning employer necessary qualified test/report and qualification set 2
of company as per india relevant regulation or requirement
of employer and owner, etc... 3.Chemical cleaning shall
meet the india regulation, such as enviromental
antipollution, discharge of liquid effluent, treatment of
boiler cleaning effluent and monitoring requirements, etc

3 Fans

scope of work:1. Installation and alignment of the impeller


casing, main bearings, rotors, inlet box, diffuser, sealing
glands, dynamic blade regulator, motor etc.. 2. Installation
Primary fan of axial-flow of platform, ladder and railing of the fan. 3. Installation of
3.1 set 4 120 91.7 183.4
type the lubricant system; hydraulic system; internal treatment
of lubricant pipings and servo drive device. 4. Test and
adjustment of lubricant system etc.. 5. Structural
inspection and finishing of fan blades.

scope of work:1. Installation and alignment of the impeller


casing, main bearings, rotors, inlet box, diffuser, sealing
glands, dynamic blade regulator, motor etc.. 2. Installation
Forced draft fan of axial- of platform, ladder and railing of the fan. 3. Installation of
3.2 set 4 140 52.3 104.6
flow type the lubricant system; hydraulic system; internal treatment
of lubricant pipings and servo drive device. 4. Test and
adjustment of lubricant system etc.. 5. Structural
inspection and finishing of fan blades.

scope of work:1. Installation and alignment of the impeller


casing , main bearings, rotors, inlet boxs, diffuser, motor
Induced draft fan of axial- and cooling air fan and assessory etc.. 2. Installation of
3.3 set 4 260 194.9 389.8
flow type platform, ladder and railing of the fan. 3. Installation of the
lubricant system; internal treatment of lubricant pipings. 4.
Test and adjustment of lubricant system.

5/18
Scanner cooling air scope of work:Sizing block & shims erection, equipment
3.4 set 4 8 2 4
fan(centrifugal type) alignment and accessory.
flow 11.52m3/s
scope of work:1. Hydraulic test of bearing box. 2. sizing
Seal air fan(centrifugal ,pressure :9000Pa
3.5 block & shims erection, equipment alignment and set 4 28 14 28
type) ,including motor
accessory.
185kw, 415v
4 electrostatic precipitator 0

Scope of Works: the ESP proper(include steel


structureShell and top capfrom inlet duct to outlet
duct, and flange of ash hopper upward, the whole
machinery, shaking devices and junction piece)Stairs,
4.1 electrostatic precipitator set 4 5800 4750 9500
platform, walkway, anode system, cathode system, small
ash bucket of the ESPaccessories, etc... Contents of
Works: Assembly, alignment and installation of
equipment, kerosene test and air leakage test etc.

5 Milling system
Scope of works: type:HP1163/Dyn motor:850KW
11kV(including oil system, motor, dynamic classifier, gear
box, sealing device, valvesfix/mobile mill rejects hopper,
5.1 Medium speed mills, steel structure, platform , support and hangeretc). set 14 3500 1815.6 3631.2
Contents of works: installation and alignment of
equipment and accessory, internal treatment of lubricant
pipings
Scope of works:max.conveying capacity:101t/h feeding
distance:2.25m inlet/outlet raw coal piping, inlet/outlet
5.2 Belt coal feeder, set 14 182 42 84
gate valves, coal chutesealing device , accessories
etc
Installation of flues & air
6
duct
Scope of Works: wind box, expansion joint and supports &
hangers etc..
Assembly and erection of
6.1 Contents of Works: Assembly, welding and installation of set 4 192 35.8 71.6
wind box
wind box, expansion joint, supports & hangers and
kerosene test etc.
Scope of Works: Installation of steam coil air pre Heater
including drain piping, pump, valve hydraulic test etc.
6.2 Steam coil air preheater set 4 72 9 18
Contents of Works: alignment, installation, welding, hydro-
test etc..

6/18
Scope of Works: inlet & outlet duct of air preheater, inlet
and outlet duct of ESP, inlet and outlet duct of IDF
Assembly and erection of ,manhole gate and baffle and support&hanger etc.
6.3 set 2 1600 1372.8 2745.6
flue duct Contents of Works: Assembly, welding and installation of
flue duct, supports and hangers; inspection and installation
of various doors;kerosene test etc..

Scope of Works: inlet & outlet of PA fan,inlet & outlet of FD


fan,silenser, explosion door,manhole gate and baffle
Assembly and erection of ,support & hangers etc.
6.4 Primer cold duct and Contents of Works: Assembly, welding and installation of set 2 560 303.1 606.2
Secondary cold duct primer cold duct and secondary cold duct, supports and
hangers; inspection and installation of various
doors;kerosene test etc..
Scope of Works: outlet hot duct of APH, explosion
doorexpansion joint ,manhole gate and baffle ,support &
Assembly and erection the hangers etc.
6.5 ducts of Primary hot duct Contents of Works: Assembly, welding and installation of set 2 700 354 708
and Secondary hot air duc primary hot duct and secondary hot duct, supports and
hangers; inspection and installation of various
doors;kerosene test etc..
Scope of Works: pipe ,valve, supports & hangers etc..
Contents of Works: Assembly,weldind and installation of
6.6 Sealing air duct set 2 48 22.4 44.8
seal Air duct, welding of pipe, support & hanger erection
etc..
Scope of Works: the coal pipe is from outlet of coal mill to
burner,include valves, elbows, expansion joint ,
Piping of pulverized coal
6.7 accessories, supports & hangers etc. set 2 900 889.3 1778.6
system
Content of Works: installation, welding of pipe,
support&hanger erection etc..

Scope of Works: fabricaiton and erection of square circle


node,elbow
Content of Works: 1. Blanking, fabrication, inspection and
Fabrication and erection of
6.8 painting of binding, reinforcer, sealing plate at the corners, set 2 120 0
flue&air duct
rectangle flanges and connecting pipe . 2. Rolling of steel
plate; inspection on welding and seam of groove; painting
of one coat of anticorrosion paint etc..3.kerosene test.

Steam generator and


7
other auxiliaries

7/18
Scope of Works: Installation of the tank and its
attachment. Contents of Works: 1. Foundation lining;
intermittent blowdown flash fabrication of pad block; hoisting, placing and fixing of the
7.1 set 2 24 35.518 71.036
tank and accessories tank. 2. Internal cleaning; cushioning and sealing of port
lid; grinding installation of valves and glass water gauge ;
installation and adjustment of other attachments.

Scope of Works: Installation of the tank and its


attachment. Contents of Works: 1. Foundation lining;
continuous blowdown flash fabrication of pad block; hoisting, placing and fixing of the
7.2 set 2 16 25.5 51
tank and accessories tank. 2. Internal cleaning; cushioning and sealing of port
lid; grinding installation of valves and glass water gauge ;
installation and adjustment of other attachments.

Scope of work:1. installation of electric hoist 2. Load test of


7.3 electric hoist set 2 10 0
electric hoist.

7.4 Elevator
Scope of Works:Installation of Elevator structure. Contents
of Works:Foundation lining; installation and removal of
7.4.1 Elevator structure temporary facilities; check, calibration, assembly, welding, set 2 182 74 148
reinforcement, hoisting, aligning and fixing of steel
structure.
Scope of work: 1.Support and guide rail
erection,2.Installation and adjustment of the traction
7.4.2 Equipment motor,3.The erection of Carrier Safety clamps and guide set 2 15 0
shoe,4.Installation of car,5.Buffer erection,6.installation of
door system, 7.the report of usage etc.
TWO Fuel supply system 0
1 mill reject system 0
including double disc valve of mill, discharge valve of
1.1 mill hopper set 14 7 26.5 53
accident etc.
1.2 blow tank including feed valve,expansion joint and accessory set 14 4.2 0
including proper,structure, platform,pressure relief valve
1.3 mill bin set 2 12 0
,indicator etc
Inspection, clearing, wrapping with cloth bags, installation
1.4 exhaust air filter set 2 2 0.9 1.8
of the machine proper etc..
Dismantling inspection, clearing and installation, motor
1.5 manual knife gate set 2 0.8 0.12 0.24
installation

8/18
Dismantling inspection, clearing and installation, motor
1.6 pneumatic knife gate set 2 0.8 0.44 0.88
installation
diameter of the pipe
1.7 including valve, hanger and support, accessories etc. set 2 2 0
57
diameter of the pipe
1.8 including valve, hanger and support, accessories etc. set 2 4 53.1 105.7
133 and219
fittings:ceramic
1.9 set 2 4 0
-lined
THREE Ash disposal system 0
1 bottom ash system 0
1.1 steel band conveyor output: 3~14t/h, including belt ,motor structure etc. set 4 60 0 Drawing no have
hydraulically operated
1.2 isolating gate and oil including related equipment and piping ,accessory ,etc set 2 60 0 Drawing no have
system
1.3 BA hopper including anchor bolt ,steel structure, platform,etc set 2 70 0 Drawing no have
1.4 clinker grinder including motor and accessory set 4 12 0 Drawing no have
including structure, platform, supports, gate,auxiliary
1.5 bottom ash bin set 2 160 0 Drawing no have
equipment, pipe,accessory ,etc.
1.6 double paddle mixer including motor and accessory etc. set 2 16 0 Drawing no have
1.7 motor-driven air-lock feeder include motor and accessory etc. set 8 2 0 Drawing no have
1.8 pneumatic knife gate set 8 2 0 Drawing no have
1.9 manual knife gate set 8 2 0 Drawing no have
1.10 dry ash unloader include motor and accessory etc. set 2 0.6 0 Drawing no have
1.11 scraper conveyor include motor and accessory etc. set 4 8 0 Drawing no have
1.12 slurry pump including motor , accessory , etc. set 4 11.6 0 Drawing no have
1.13 water pump including motor , accessory ,etc. set 4 4 0 Drawing no have
1.14 bottom ash slurry mixer set 2 5 0 Drawing no have
1.15 bottom slurry sump set 2 3 0 Drawing no have
cast stone -lined steel pipe including pipe,valves, supports and hangers, accessory,
1.16 set 2 50 0 Drawing no have
and valves etc
1.17 the other pipe including valve,gate and accessory set 2 6 0 Drawing no have
Four Miscellaneous Piping 0

9/18
including compressed air pipe of boiler house, closed cycle
cooling water pipeopen cycle coling water pipeservice
water pipeauxiliary steam pipeflush pipe of air
diameter of the pipe preheater ,boiler hall washing water piping, and valves,
1.1 set 2 20 0
57 hanger&support , accessory etc. For cooling water,
service water pipe,and compressed air pipe, sandblasting
shall be included; For auxiliary steam pipe, sandblasting
and steam blowing shall be included;

including compressed air pipe of boiler house, closed cycle


cooling water pipeopen cycle coling water pipeservice
water pipeauxiliary steam pipeflush pipe of air
diameter of the pipe 57 preheater ,boiler hall washing water piping, and valves,
1.2 set 2 70 0
and133 hanger&support , accessory etc. For cooling water,
service water pipe,and compressed air pipe, sandblasting
shall be included; For auxiliary steam pipe, sandblasting
and steam blowing shall be included;

including compressed air pipe of boiler house, closed cycle


cooling water pipeopen cycle coling water pipeservice
water pipeauxiliary steam pipeflush pipe of air
diameter of the pipe preheater ,boiler hall washing water piping, and valves,
1.3 set 2 80 0
133 and219 hanger&support , accessory etc. For cooling water,
service water pipe,and compressed air pipe, sandblasting
shall be included; For auxiliary steam pipe, sandblasting
and steam blowing shall be included;

including compressed air pipe of boiler house, closed cycle


cooling water pipeopen cycle coling water pipeservice
water pipeauxiliary steam pipeflush pipe of air
diameter of the pipe preheater ,boiler hall washing water piping, and valves,
1.4 set 2 34 0
219 and273 hanger&support , accessory etc. For cooling water,
service water pipe,and compressed air pipe, sandblasting
shall be included; For auxiliary steam pipe, sandblasting
and steam blowing shall be included;

10/18
including compressed air pipe of boiler house, closed cycle
cooling water pipeopen cycle coling water pipeservice
water pipeauxiliary steam pipeflush pipe of air
diameter of the pipe preheater ,boiler hall washing water piping, and valves,
1.5 set 2 20 0
273 hanger&support , accessory etc. For cooling water,
service water pipe,and compressed air pipe, sandblasting
shall be included; For auxiliary steam pipe, sandblasting
and steam blowing shall be included;

one layer of
bitumen sandwich
one layers of fabric
Buried pipes,valves, accessory, etc Excavation, backfill glass; the total
diameter of the pipe and anticorrosive layer structure asphalt primer shall be thickness is
1.6 set 2 2 0
57 includedand the asphalt ,fabric glass and other paint for 2mm.All work and
the buried pipes are suppiled by subcontractor. test should be
completed to satify
the design
requirements
one layer of
bitumen sandwich
one layers of fabric
Buried pipes,valves, accessory, etc Excavation, backfill glass; the total
diameter of the pipe 57 and anticorrosive layer structure asphalt primer shall be thickness is
1.7 set 2 10 0
and133 includedand the asphalt ,fabric glass and other paint for 3mm.All work and
the buried pipes are suppiled by subcontractor. test should be
completed to satify
the design
requirements
one layer of
bitumen sandwich
one layers of fabric
Buried pipes,valves, accessory, etc Excavation, backfill glass; the total
diameter of the pipe and anticorrosive layer structure asphalt primer shall be thickness is
1.8 set 2 20 0
133 and219 includedand the asphalt ,fabric glass and other paint for 4mm.All work and
the buried pipes are suppiled by subcontractor. test should be
completed to satify
the design
requirements

11/18
one layer of
bitumen sandwich
one layers of fabric
Buried pipes,valves, accessory, etc Excavation, backfill glass; the total
diameter of the pipe and anticorrosive layer structure asphalt primer shall be thickness is
1.9 set 2 4 0
219 and273 includedand the asphalt ,fabric glass and other paint for 5mm.All work and
the buried pipes are suppiled by subcontractor. test should be
completed to satify
the design
requirements
one layer of
bitumen sandwich
one layers of fabric
Buried pipes,valves, accessory, etc Excavation, backfill glass; the total
diameter of the pipe and anticorrosive layer structure asphalt primer shall be thickness is
1.10 set 2 40 0
273 includedand the asphalt ,fabric glass and other paint for 6mm.All work and
the buried pipes are suppiled by subcontractor. test should be
completed to satify
the design
requirements
diameter of the pipe including stainless steel piping,argon arc welding,valves,
1.11 set 2 6 0
57 support and hanger etc.
diameter of the pipe 57 including stainless steel piping,argon arc welding,valves,
1.12 set 2 20 0 compressed air
and133 support and hanger etc.
pipe & accessories
diameter of the pipe including stainless steel piping,argon arc welding,valves,
1.13 set 2 10 0 in #1 boiler house
133 and219 support and hanger etc.
diameter of the pipe including stainless steel piping,argon arc welding,valves,
1.14 set 2 4 0
219 and273 support and hanger etc.
Five BOP area system 0
1 Coal-fired system 0
Type: stacking: Q=4000t/h,reclaiming:Q=4000t/h boom
length:42m Scope of Works: assembly and installation of
Bucket-wheel stacker
1.1 running mechanism, door seat frame, rotary disk, set 3 3300 750 2250
reclaimer
cantilever frame, tail lathe, platform, walkway, handrails,
conveyor and hydraulic system etc..
1. Installation of central
B=2000mm,V=3.25m/s,Q=4000t/h,Qmax=4400t/h,L=122.2 nonstandard metal
1.2 no.2A,B conveyor set 2 94 227.239 227.239
54m,=6-12 framework, groove-type
B=2000mm,V=3.25m/s,Q=4000t/h,Qmax=4400t/h,L=1130 carrier roller, and
1.3 no.3A,B,C conveyor set 3 866 1695.405 1695.405 parallel roller. 2.
m,=0-16 Installation of tension
apparatus framework,
slide groove, roller,
trolley, fixed pulley,
heavy hammer, steel
wire, spring and guard
grating.3. Laying and
12/18 glued jointing of belt,
installation of coal guide
groove. 4. Installation of
clamping roller device
1. Installation of central
nonstandard metal
framework, groove-type
carrier roller, and
parallel roller. 2.
Installation of tension
B=2000mm,V=3.25m/s,Q=4000t/h,Qmax=4400t/h,L=146.7 apparatus framework,
1.4 no.4A,B conveyor set 2 113 247.474 247.474
16m,=6-10 slide groove, roller,
trolley, fixed pulley,
B=2000mm,V=3.25m/s,Q=4000t/h,Qmax=4400t/h,L=146.7
1.5 no.5A,B conveyor set 2 113 247.474 247.474 heavy hammer, steel
16m,=6-10 wire, spring and guard
B=2000mm,V=3.25m/s,Q=4000t/h,Qmax=4400t/h,L=103.8 grating.3. Laying and
1.6 no.6A,B conveyor set 2 81 280.66 280.66
0m,=5.5 glued jointing of belt,
installation of coal guide
B=2000mm,V=3.25m/s,Q=4000t/h,Qmax=4400t/h,L=227.1 groove. 4. Installation of
1.7 no.7A,B conveyor set 2 175 254.1 254.1
41m,=4.5 clamping roller device
B=1400mm,V=2.5m/s,Q=1275t/h,Qmax=1400t/h,L=187.15 and various protection
1.8 no.8A,B conveyor set 2 101 153.641 153.641 devices, signal device
13m,=4-10.8
(such as tape fracture
B=1400mm,V=2.5m/s,Q=1275t/h,Qmax=1400t/h,L=318.02 protection, tape slip
1.9 no.9A,B conveyor set 2 171 109.653 109.653
3m,=4-10.8 protection, tape off
B=1400mm,V=2.5m/s,Q=1275t/h,Qmax=1400t/h,L=205.4 tracking switch, coal
1.10 no.10A,B conveyor set 2 110 109.653 109.653 flow signal, coal
m,=0 blockage signal, bi-
3-location head moveable
1.11 B=2000mm,Q=4000t/h set 3 33 0
device
Q=1300t/h,Qmax=1400t/h
Installation and alignment of of baasement frame, screen
1.12 vibration screen set 2 26 16.4 32.8
frame, shaft, plate spring, spring seat, bearing seat, rubber
bumper and motor.
Q=1300t/h,
Ring-hummer-type coal crusher: 1. Sweeping and
checking of rotor bearing seat, hammer, lining board of
1.13 ring hammer crusher set 2 68 33.5 67
hammer, and screening bar. 2. Installation of shell,
materials loading hopper, bearing coupling, motor, and
electric pusher.
B=1400mm, V=2.5m/s, Q=1275t/h,=10.8
Checking of shifting frame and carrier roller; installation of
1.14 belt scale shifting frame, underbed, weight roller, cross spring set 2 1.2 9.06 9.06
lamination, sensor, standard weight scale, and
counterweight block.

1.15 dynamic circle chain B=1400mm, V=2.5m/s, Q=1275t/h,=10.8 set 2 8.4 4.3 8.6

B=1400mm, V=2.5m/s, Q=1275t/h,=10.8


Machanical sampling device:1. Strip inspection of reducer,
1.16 sampling system roller, and chain wheel breaker. 2. Installation of set 2 11 14.6 14.6
framework, chain, chain wheel, chain hopper, shell, chain
wheel breaker device, tension device,reducer, and motor.

13/18
B=1400mm troughing angle:35
electric drive double- side
1.17 Installation of coal plough and coal drop hopper, and set 26 78 128 128
plough
installation of electric pusher.
1.18 wiper B=2000mm set 6 6 0
B=2000mm
belt-type magnetic Check and installation of electromagnetic iron, motor,
1.19 set 7 43 14.2 113.6
separater reducer, driving (driven) roller, and cooling fan; installation
of iron abandon belt, and supporting carrier roller.

B=1400mm
hang-type magnetic
1.20 Checking and installation of singal track crane; installation set 2 8 8.7 8.7
separater
of separator noumenon.
1.21 metal detector set 2 0.6 0.04 0.04
B=2000mm 1400mm*1400mm
1.22 electric driven diverter gate Dismantling inspection, clearing and installation, including set 8 20 0
motor installation
B=1400mm 1000mm*1000mm
electric driven billabong
1.23 Dismantling inspection, clearing and installation, including set 2 3.7 0
gate
motor installation
B=2000mm 1400mm*1400mm
electric driven billabong
1.24 Dismantling inspection, clearing and installation,including set 5 13 0
gate
motor installation
B=2000mm 1400mm*1400mm
1.25 absorber dismantling inspection, clearing, air-tight test and set 14 32 0
installation,including motor installation.
B=1400mm 1000mm*1000mm
1.26 absorber dismantling inspection, clearing, air-tight test and set 6 9.6 0
installation including,motor installation.
1.27 the other pumps including transporting, erection, alignment etc. set 1 5 0
including piping ,valves,hanging and support, accessory
diameter of the pipe etc,buried pipes (including antiseptic treatment, welding,
1.28 set 1 10 0
57 elbow, valves, excavation, backfill, accessories, hydraulic
test, etc.)
including piping ,valves,hanging and support, accessory
diameter of the pipe 57 etc,buried pipes (including antiseptic treatment, welding,
1.29 set 1 50 0
and133 elbow, valves, excavation, backfill, accessories, hydraulic
test, etc.)
2 Fuel oil system 0

14/18
HFO storage tank V=2000m3 (including fabrication &
2.1 HFO storage tank erction, sandblasting,and testing, platform & handrail, set 2 78.4 2 168
accessories, etc.)
LDO storage tank V=1000m3 (including fabrication &
2.2 LDO storage tank erction,sandblasting,and testing , platform & handrail, set 1 43.2 1 47.46
accessories, etc.)
centrifugal LDO supply
2.3 Q=28m3/h including proper equipment, local gauge, etc. set 3 9 3 9.3
pumps
strainers of LDO supply
2.4 filter screen checking, positioning, and installation set 3 0.6 3 0.3
pumps
centrifugal LDO unloading
2.5 Q=66m3/h including proper equipment, local gauge, etc. set 2 4 2 1.3
pumps
strainers of unloading
2.6 filter screen checking, positioning, and installation set 2 0.4 2 0.3
pumps
Q=59m3/h including proper equipment, local
2.7 screw HFO supply pumps set 3 3 3 4.98
gauge,alginment, grouting etc.
strainers of HFO supply
2.8 filter screen checking, positioning, and installation set 3 0.6 3 0.6
pumps
screw HFO unloading
2.9 Q=66m3/h including proper equipment, local gauge,etc. set 3 1.8 3 1.9
pumps
strainers of HFO unloading
2.10 filter screen checking, positioning, and installation set 3 0.6 3 0.6
pumps
2.11 HFO heaters set 2 1.6 2 72
centrifugal waste water
2.12 Q=10m3/h including proper equipment, local gauge, etc. set 1 1 1 0.428
pump
strainer of centrifugal waste
2.13 filter screen checking, positioning, and installation set 1 0.2 1 0.056
water pump
2.14 drain flash tank V=10m3 including installation alignment ,grouting etc, set 1 3 1 4.5
centrifugal steam drain
2.15 Q=10m3/h including proper equipment, local gauge, etc. set 2 1.2 2 0.944
pumps
2.16 gear drain oil pump Q=2m3/h including proper equipment, local gauge, etc. set 1 0.6 2 0.19
strainers of gear drain oil
2.17 filter screen checking, positioning, and installation set 1 0.2 2 0.072
pump
2.18 HFO coolers set 2 1.6 2 42.4
centrifugal direct-link
2.19 Q=90m3/h including proper equipment, local gauge, etc. set 2 1.6 2 0.6
pumps

15/18
including sandblasting, argon arc welding,valves, supports
diameter of the pipe
2.20 & hangers ,accessories, hydraulic test, steam blowing, set 1 5 1 13
57
buried pipes (including antiseptic treatment)etc.

diameter of the pipe 57 including sandblasting, argon arc welding,valves, supports


2.21 set 1 110 1 49
and133 & hangers ,accessories, hydraulic test, steam blowing, etc.

diameter of the pipe including sandblasting, argon arc welding,valves, supports


2.22 set 1 10 1 67.4
133 and219 & hangers ,accessories, hydraulic test, steam blowing, etc.

diameter of the pipe including sandblasting, argon arc welding,valves, supports


2.23 set 1 5 1 3.3
219 and273 & hangers ,accessories, hydraulic test, steam blowing, etc.
3 Diesel Generator system 0
including porper,steel plate, cooling system, start-up
diesel engines and the
3.1 system, lubricate system, fule oil system, in/out gas/duct set 3 100 0
other equipments
system, daily oil tank, accessory , etc
including piping,valves, supports and hangers, accessory,
3.2 relevant piping set 3 1.5 0
etc
4 fly ash system 0
including porper,structure,plateform, drive device,
4.1 hight efficiency setting tank set 1 95 0
accessory,etc
Ash vessel of economizer v=0.5m3 including support ,manual knife gate,expansion
4.2 set 12 6 0
hopper joint, feed dome valve,vent valve,opening up valve etc.

v=2m3 including support ,manual knife gate,expansion


4.3 ash vessel of ESP set 32 32 0
joint, feed dome valve,vent valve,opening up valve etc.

ash vessel of ESP third& v=0.5m3 including support ,manual knife gate,expansion
4.4 set 64 32 0
fourth &fifth&sixth field joint, feed dome valve,vent valve,opening up valve etc.

v=0.5m3 including support ,manual knife gate,expansion


4.5 ash vessel of air preheater set 8 4 0
joint, feed dome valve,vent valve,opening up valve etc.

4.6 bottom ash sluicing pump including motor and accessory etc. set 2 4 0
4.7 sealing water pump including motor and accessory etc. set 2 0.8 0
4.8 sewage pump include motor and accessory etc. set 5 3 0
4.9 fly ash slurry pump include motor and accessory etc. set 4 17 0
4.10 slurrying water pump include motor and accessory etc. set 2 2 0
4.11 fly ash slurry mixer including motor and accessory etc. set 2 5 0
4.12 water pump including motor and accessory etc. set 2 2 0

16/18
4.13 exhaust fan including accessory etc. set 1 1 0
4.14 double paddle mixer including motor and accessory etc. set 1 8 0

4.15 fluidizing blower of ash silo including motor and accessory etc. set 2 2 0
electric air heater of ash
4.16 including motor and accessory etc. set 1 0.8 0
silo
4.17 motor-driven air-lock feeder include motor and accessory set 4 1 0
4.18 dry ash unloader include motor and accessory set 1 0.3 0
4.19 exhaust air filter set 1 1.5 0
4.20 hopper fluidizing blower include motor and accessory set 4 5.2 0
4.21 hopper fluidizing air heater include motor and accessory set 4 1.2 0
4.22 aeration trough Inspection, clearing and installation set 92 1.84 0
4.23 discharge boxes set 6 3 0
cast stone -lined steel pipe
4.24 set 1 130 0
and vales
4.25 GRP & valve set 1 23 0
4.26 the other pipe including valve, and accessory etc.. set 1 6 0
Pressure relief valve
4.27 set 1 0.51 0
DN500
4.28 manhole door set 2 0.35 0
5 compressed air system 0
air compressor (including
5.1 proper equipment, motor, Q=42Nm /minP=0.80MPa250KW6.6KV set 6 42 0
etc.)
air compressor (including
5.2 proper equipment, motor, Q=50Nm /minP=0.75MPa300KW6.6KV set 3 21 0
etc.)
5.3 conveying air direr Q=50Nm /minP=0.80MPa415V, 9.5KW set 3 9 0
5.4 filter Q=50Nm /minP=0.80MPa set 18 9 0
5.5 combined dryer Q=40Nm /minP=0.8MPa415V, 7.5KW set 3 9 0
5.6 conveying air direr Q=60Nm /minP=0.80MPa415V, 9.5KW set 3 9 0
V=30m3 including proper equipment, safety valves, local
5.7 air storage tank set 7 56 0
gauge etc..
V=15m3 including proper equipment, safety valves, local
5.8 air storage tank set 3 15 0
gauge etc..
diameter of the pipe including carbon steel piping,valves, support and hanger
5.9 set 1 1 0
57 etc.

in air compressor
house

17/18
diameter of the pipe 57 including carbon steel piping,valves, support and hanger
5.10 set 1 2 0
and133 etc.
diameter of the pipe including carbon steel piping,valves, support and hanger in air compressor
5.11 set 1 10 0
133 and219 etc. house
diameter of the pipe including carbon steel piping,valves, support and hanger
5.12 set 1 8 0
219 and273 etc.
diameter of the pipe including carbon steel piping,valves, support and hanger
5.13 set 1 8 0
273 etc.
diameter of the pipe 57 including stainless steel piping,valves, support and hanger
5.14 set 1 0.5 0
and133 etc. in air compressor
diameter of the pipe including stainless steel piping,valves, support and hanger house
5.15 set 1 2 0
133 and219 etc.
SIX Civil Work 0
1 Grouting 0
Cu.
1.1 60 non shrinking cement Provide and construction, etc.. 20 0
m
Cu.
1.2 40 non shrinking cement Provide and construction, etc.. 20 0
m
M25-M35 FINA
Cu.
1.3 AGGREGATE ,CHIPS Provide and construction, etc.. 20 0
m
DN20MM
HIGH-STRENGTH
Cu.
1.4 GROUTING WITHOUT Provide and construction, etc.. 20 0
m
SHRINKAGE
0 #REF!
0
1.The QTY in BOQ is temperorary, payment will be calculated according to the work actually completed. The formulate of payment is: payment=quantity actually
Note:
completed rate in BOQ, inclusive all the costs of Contractor.
2. The Rate in BOQ is firm and final and not liable to any change under QTY change or whatever reasons.
3.Mobilization and demobilization of all necessary manpower and equipments as per specification including shifting & erecting the same from one location to the
other.
4.The above rates are all inclusive unless otherwise specified, firm and final and not liable to any change under any condition whatsoever from the date of
Commencement Date.
5.The rate includes all the taxes and duties.
6.Contractor shall perform the Works according to the related drawings and technical specifications and construction standards. The above working description
of the item are subject to approval of the Owner's/Employer's Engineer based on the agreed technical specification,if Owner's/Employer's Engineer doesn't agree
about it .the related modifications and related cost incurred will be undertaken by the Contractor,always based on the agreed technical specifications.