The free preparation test below covers the current
PMP exam version (per 31 August 2011).
M ailed M ay 1 1 , 2 0 1 3 by V ijay K.R. (I ndia):
"D ear O liver,
Each question in this self assessment test has one [...]
best answer. I have pas s ed my P M P exam yes terday (1 0 - M ay). I would
like to thank you for your advic e and thos e valuable
Time to finish the test: 90 Minutes. c ontents on your webs ite - it has been a great help during
my preparation.
Y ou are great in this P M c ommunity and have been doing a
There is a timer in the title bar (top of most
wonderful job. Wis h you more s uc c es s in c oming days .
browsers). Bes t Regards ."
FREE Download for learning M ailed M ay 3 , 2 0 1 3 by Stuart B. (A us tralia, via L inkedI n):
and instruction. Click the dark blue button (below) to reset the timer
"O liver,
to 00:00:00. I pas s ed the P M P E xam in Sydney today and I us ed the
Insight tree supports prac tic e exams from your webs ite (the C A P M one inc luded)
project selection and helps you Click here for links to 3,000+ more PMP prep as part of my preparation.
become a decision tree expert. questions from various providers (4,000+ for PMI I jus t wanted to s ay that I thought the material was very
members). well written and realis tic of how the ac tual exam was
s truc tured and I c ertainly believe it helped me c ros s the
line.
Life training classes: M any thanks ."
www.oliverlehmann.com/seminar-dates.html
M ailed A pril 9 , 2 0 1 3 by A dhik K. (U SA , via L inkedI n):
PMI has not participated in the development of this s elf "H ello O liver,
as s es s ment tes t and has not reviewed the content. Y es terday I ac hieved my target of getting my P M P in firs t
attempt.
J us t wanted thank you for all your free ques tions that helped
me preparing better for my goal.
T hanks & Regards ."
184 Tw eet 96 Like 246 Send XING Follow Share
M ailed J anuary 2 3 , 2 0 1 3 by Rames h C h. (I ndia):
"Res pec ted O liver Sir,
I 'm glad to announc e that I ac hieved the mos t c oveted P M P
Ready? Click here to reset the timer and start the test
c redential on 2 1 s t J an 2 0 1 3 . I 'm even more glad and
thankful to your free res ourc es in www.oliverlehmann.c om
whic h had enric hed my P M knowledge and bridged the gaps
in infinite number of ways ."
See references Marked for review
M ailed J uly 2 4 , 2 0 1 2 by C hris tina W. (C anada):
"H ello O liver;
1. ________ is typically not referred to as a buffer type in critical chain project management.
T hanks for your links to the many prac tic e tes ts .
I took the P M P exam on J uly 1 9 th and did well.
Bes t Regards , C hris tina"
Resource buffer
M ailed J uly 0 9 , 2 0 1 2 by C handraShekhar B. (I ndia):
Free buffer "T his tes t is very helpful in evaluating weak areas ."
The measurements made at the end of the process yielded the following results:
4. Your project management team includes two external consultants each from a different
company. You found that repeated conflicts between the two consultants already slow down
project progress and jeopardize achievement of objectives.
5. During a project, earned value analysis is performed, resulting in the following numbers:
6. A project manager spent some days to create a multi-page document, which he called project
charter. The document should have been issued by the project sponsor. The sponsor found the
document outsized and asked for a condensed document.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 2/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
7. A document called ____________ is created by decomposing the project scope into smaller,
more manageable elements.
Scope Statement
Documentation reviews
Data precision rankings
Diagramming techniques
9. In order to speed up a project, you made a decision to fast-track a phase currently performed
with five team members, and another one which was planned to begin in four weeks time with
another five team members.
Make sure that all exit criteria of the consecutive phase have been met to ensure the flow
of communications in a team situation which is more complex by a factor of 2.
Make sure that all entry criteria of the previous phase have been met by planning and
performing a phase gate meeting to assess technical aptness.
Make sure that all exit criteria of the previous phase have been met by planning and
performing a phase gate meeting to assess technical performance.
Restructure your team and delegate tasks in order to ensure the flow of communications
in a team with the number of communication channels increased by a factor of 4.5.
10. A project manager has been asked to support an internal project request by developing a
business case.
The detailed information from a business standpoint to determine whether bidding for
the customer project will be successful.
The detailed information from a project management standpoint to determine whether
the project will be successful.
The detailed information from a technical standpoint to determine whether the project
will be successful.
The necessary information from a business standpoint to determine whether the project
is worth the investment.
11. You found the following earned value analysis information for a project that was recently
closed-out:
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 3/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
The project has been cancelled while it was executed. At that time the project was
behind schedule and on budget.
The project's deliverables have all been finished. The project came in behind schedule
but on budget.
The project's deliverables have all been finished. The project came in ahead of schedule
but on budget.
The project's deliverables have all been finished. The project came in on schedule but
over budget.
a decision to which no expected monetary value can be assigned so that a likely pay-off
can not be shown.
a chance to which an expected monetary value may be assigned to calculate the most
likely pay-off.
a decision to which an expected monetary value may be assigned to calculate the most
likely pay-off.
14. A project management team has subcontracted work to a service company. Which of the
following tools is the best choice to assure that this company will be able to meet the quality
requirements of the project?
Quality audit
Deliverable inspection
Fixed price contract
15. With your team you are using judgment from subject matter experts to identify and analyze
project risks. There is a small number of experts available, but some of them have long been in
a teacher-student or manager-assistant relationship.
Which of the following techniques can ensure best that there is no dominating opinion during
an expert review?
Peer review
SWOT analysis
Delphi technique
Monetary value calculation
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 4/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
16. You are running a project for a customer based on a cost-reimbursable contract with the
following terms:
Which is the PTA (= point of total assumption, break point) of the project?
$1,300,000
$1,500,000
$80,000
$1,125,000
17. During execution of a project which is performed for a customer on a T&M (time and material)
contract base, a new project manager is taking over the assignment.
He discovers that two members assigned to the project have charged time without performing
any work for the project customer. Upon further investigation, he determines that this occurred
because there have been no other project assignments open for these employees. The
customer is unaware of these facts.
Try to find some productive work for these staff members in the project and leave them
on the team.
The best thing is to do nothing. The customer will not realize the problem anyway.
Try to find a responsible person for the over-assignment who can be made accountable.
Take the two people off the team immediately and arrange for the refund of the excess
charges to the customer.
18. Start dates in the following network logic diagram are defined as early morning, finish dates
are evening.
19. Your project is executed with a globally spread virtual team. The project progress has been
found to be too slow. Which measure is most likely to immediately speed up the project?
20. A project management team wants to procure some customized products which are available
in identical grade and quality from many vendors. What should be included in the procurement
package to ensure that their offers will be comparable?
A statement of work describing the needs of the project in sufficient detail to enable
vendors to make suitable proposals
A statement of work specifying attributes and metrics of the requested deliverables in
detail to allow vendors submission of bids
The approved project scope statement, the WBS which should be broken down to work
package level and the WBS dictionary
The risk management plan and the reports from those risk management reviews which
have been made so far
21. Which of the following becomes increasingly important in a virtual team environment?
Requirements engineering
Communication planning
22. You are assigned as the project manager to a project which is executed for a customer under
FP contract. Your customer informed you this morning that they insist on certain "refinements"
of the project scope.
You agree that the requested actions make really sense to the project, but believe that they
constitute a major change increasing the project scope. What should you do next?
Accept the request of the customer. Diligently document the additional costs and working
hours spent by yourself and the team on the implementation of the change and invoice
these to the customer at appropriate rates.
Perform earned value analysis to assess the current status of the project and get all the
numbers you need to communicate the case to the change control board which then will
have to make the best decision regarding the customer request.
Check the contract, the project charter, the scope statement and other documents
related to the project and the contract. Implement ADR (alternative dispute resolution)
procedures if the conflict cannot be resolved otherwise.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 6/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
Talk to the project sales department and find a joint solution with them how to best
reject the request considering the commercial and strategic value of the customer to the
organization you are working for.
23. A prime contractor in a customer project under CPFF contract has run into unexpected technical
problems. Fixing them will require a lot of additional work to be done.
The company made a decision to book more staff and equipment from their subcontractors in
order to adhere to the agreed timeline. The customer agreed to this decision.
The contractors indirect costs will increase and the customers payment for them will
increase, too.
The contractors indirect costs will increase, but the customers payment for them will not
increase.
The contractors indirect costs will not increase, but the customers payment for them will.
Both the contractor's indirect costs and the customers payment for them will not
increase.
24. A project management team is evaluating the causes that might contribute to unsatisfactory
performance and quality. Which of the following statements is not true?
Normal process variation is attributable to random causes and sometimes also called
"white noise".
Special causes are easier to predict and handle than random causes (also called common
causes).
Special causes are unusual events which are difficult to foresee and often produce
outliers.
A process can be optimized to limit the bandwidth of variations due to random causes.
25. You are performing a project management audit in your company and find that most of the
project plans are neither consistent nor up-to-date.
Projects should never be executed without a valid, updated and working project
management plan.
The consistency of the project management plan is secondary because it is only the
results that matter.
A great deal of effort is required to develop and update a project plan, but the benefits
include less pressure on all stakeholders and a resulting product that will satisfy the
requirements.
Poor planning and insufficient updating of project management plans are common
reasons for cost and time overruns.
26. You want to perform active risk acceptance. What should you do?
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 7/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
Develop a plan to minimize the probability of occurrence for identified risks.
Make additional resources available to speed up the project.
27. A project manager made 3-point estimates on a critical path and found the following results:
Assuming 3 sigma precision level for each estimate, what is the standard deviation of the
allover path?
A measuring instrument solely used to describe process capability. The process is found
capable if the 3 sigma range is exceeded by not more than 0.3% of a tested sample lot.
The limits of the six sigma area on either side of a control chart to plot measured values;
data found outside the area are out of specification and can lead to rejection of an entire
batch.
The area consisting of typically three standard deviations on either side of a mean value
of a control chart to plot measured values found in statistical quality control
The area consisting of typically three standard deviations on either side of a mean value
of a control chart to plot measured values found in quality assurance
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 8/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
31. Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6
days.
36 days
37 days
39 days
42 days
32. Which tool and technique is used in the processes Create WBS and Define activities?
a
b
b, c
c, d
Prevention means keeping errors out of the process by applying actions before the
process starts changing its input.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 9/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
Variables sampling means that the result is classified into one of the 3 categories:
"acceptable" - "acceptable after rework" - "rejected".
Inspection is often mainly done to keep errors out of the hands of the customer instead
of as a means of process control.
35. Which statement describes best why you should document assumptions?
Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows
baseline adjustments in case of project crisis.
Assumption analysis is a valuable tool and technique to explore the validity of
assumptions during risk identification.
Assumptions limit the project management team's options for decision making because
they can not be controlled by the team.
In case of schedule or budget overruns, the documentation of assumptions supports a
clear assignment of responsibility.
Prevention costs
Maintenance cost
Appraisal costs
Failure costs
37. You have recently been assigned as a project manager to a new B-O-T (build, operate,
transfer) capital project. Reviewing the initial documentation you found out that it has been
calculated with a very small margin during operations of its product for the shareholders. What
should you do?
As you are not responsible for lifecycle costing, you don't have to worry about operation
profits. Focus on project costs from initiation through handover.
Ensure maximum profits by buying the best and cheapest items, components and
modulespotentially from a big number of different suppliersand integrating them.
Create a realistic plan broken down to a sufficient level of detail. Perform all risk
management processes. Ensure real-time communications with all stakeholders.
Try to get a second project manager assigned to share decision making and
accountability to shareholders with the person.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 10/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
See references Marked for review
39. You are project manager in a global project with a team consisting of people from various
countries. What can you try to prevent misunderstandings due to cross-cultural differences?
Use all communication methods available that are suitable for the team and follow up in
writing when communicating verbally. Remember that cultural and individual diversity may
help project teams solving unforeseen problems during the course of the project.
When you are about to form a team for your project, keep in mind that some cultures are
developed, others are more primitive. Some have values, some not. You should
consequently avoid choosing members from countries with cultures that are not similar to
your own.
Cultural dilemmas can prevent any project from being successful. They should therefore
be smoothed or suppressed so as to make sure that they cannot disrupt project work.
Your effort should concentrate on communication that can help reach that goal.
As norms regarding communication habits differ significantly across various cultures,
communicating between people from different countries should only be done using
language. The nonverbal dimension simply bears too many risks.
41. A change request in a project has been rejected some weeks ago. Yesterday, the project
manager found out that it nevertheless has been implemented by the team members, who
knew of the change request, but not of the rejection.
Report performance
Verify scope
Perform integrated change control
Monitor and control risks
43. According to the project plan, a contractor is scheduled to deliver some software components
today afternoon. A regular payment is due to be made to this contractor tomorrow.
You and your project team received a note this morning informing you that the software
delivery will be delayed by 2 weeks.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 11/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
You should delay the payment also for 2 weeks.
You must immediately find a different contractor.
You should conduct a meeting with the contractor to resolve the delivery issues before
making the payment.
You should make the payment and reschedule the project plan.
44. In a software company a large number of simultaneously performed projects utilize the same
groups of human and other resources.
Concurrent engineering
Resource over-allocation
Resource pooling
Program management
45. What does the acronym RACI commonly stand for in project management?
46. You have used estimates made by your team members and applied the critical path method to
compute a network logic diagram for your project. Then you found out that it cannot be
sufficiently optimized for scarce resources and fast progress towards a given deadline. What
should you do next?
Remove physical constraints and replace hard logic with soft logic.
47. Liquidated damages (LDs) are contractually agreed payments in order to...
...give the contractor an incentive to meet an aggressive schedule or challenging quality
objectives.
...penalize the contractor for late completion of a project or failure to meet specifications.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 12/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
...cover the customer's costs caused by late completion or failure to meet specifications
by the contractor.
...make a bid or proposal binding for the offerer while the customer has time to select
among various bidders.
49. You are assigned as the project manager to a project which had a one-time cost variance in
the past caused by unexpected rework which has meanwhile been finished.
You perform earned value analysis and get the following results:
BAC is 500,000.
What is right?
EAC = 550,000
EAC = 525,000
EAC = 500,000
EAC = 425,000
50. An estimation has been made that the construction of a residential home will cost a certain
amount per square foot of living area. This is an example of what type of estimating?
Analogous estimating
Bottom-up estimating
Top-down estimating
Parametric estimating
They are tangible and allow for early feedback on requirements by stakeholders.
Prototypes are mostly developed toward the end of a design or build phase.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 13/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
A change request that helps improving the project and its product, service or result and
is discussed generally in a friendly style.
A direction by the buyer or an action taken by the seller that the other party considers an
undocumented change to the contract.
A field change or ad-hoc change mandated by the project customer in a public
construction project.
A change request which will lead to the re-construction of an older version of the project
performance baseline by the contractor.
53. Which of the following is generally not regarded to be a motivator according to Frederick
Herzberg?
54. What is true for modern project management? Project managers need...
55. You are the project manager in an engineering project and have recently signed a contract
with a software vendor for the development of a complicated control solution. The software will
be used to control machinery equipment which your project team is currently developing. The
contract is a lump-sum contract. The contractor has target cost estimated which seem rather
low to you. Which of the following statements is not true for this situation?
It is the contractor's risk in this type of contract that their profit may vanish if costs have
been underestimated.
This form of contract should only be chosen when all the requirements for the building of
the product are well-known by all parties involved.
In a fixed-price contract, change requests can cause issues regarding additional time and
extra costs for the changes to be applied.
It is likely that your organization may have to assume any unexpected additional costs
for the software development.
56. A review to determine whether of project activities comply with organizational and project
policies, processes, and procedures is commonly called
Quality auditing
Inspection
Quality testing
Reject screening
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 14/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
It allows one to easily identify the breakdown level of the item in the resource structure.
It describes the coding structure used by the performing organization to report financial
information in its general ledger.
It is the collection of unique identifiers generally assigned to WBS items.
It defines ethical behavior in the project and the responsibilities to the customer and the
profession.
58. You are the manager of your company's project management office. The company is running
many concurrent projects; most of them share a resource pool of technical staff. Understanding
how resources are utilized across projects has been found essential to overall project
performance, including cost effectiveness and profitability.
This morning you received a message that the resource pool members will be unable to
perform as planned for the next months because the overall work load has grown too high and
while delays are adding up, the morale of the staff is going down.
Ensure that quantitative information for all projects is being made available in a uniform
and reliable fashion and verify that the project management methodology is adhered to.
Then consolidate the information to get an understanding of the problems related with
the use of shared resources.
Implement an enterprise project management software solution which is able to level
the human resources across the various projects and which has the capability to model
resource assignment on a percentage level thus optimizing resource utilization for the
overall organization.
Do nothing related to the described problem unless you are explicitly requested by the
organizations upper management. Supporting decision making on the level on which
project portfolio management is done, is not the project management office's business.
Evaluate project management software which supports planning and scheduling across
enterprise-wide project portfolios. Avoid managing the availability of shared enterprise
resources for the projects run by an organization because this is not the business of a
project management office.
59. You have been criticized that certain specifications in your scope statement do not pass the
test for SMART objectives. What are SMART objectives?
Objectives specified in far more detail than necessary for a execution of a successful
project.
Easily achievable objectives which help you reducing the pressure on yourself and the
team.
Objectives that should be achieved in order to attain formal recognition by both the
customer and the project sponsor.
Objectives that are described using specific, measurable, assignable, realistic and time-
related specifications.
60. You have been assigned as a project manager to a software project. While you and your team
are working on a WBS (work breakdown structure), estimations for activity durations based on
the activity list vary significantly. Which additional documents may help you clarify this
situation?
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 15/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
Milestone list and scope baseline.
Project schedule network diagrams and human resource plan.
After budget approval, an additional and unexpected cost item has been identified, which
made the project more expensive some weeks ago. The item has meanwhile been paid by the
project team, and it is expected that for the remaining duration of the project, costs will be as
budgeted.
In this case, which is the best formula to calculate EaC (Estimate at Completion)?
EaC = BaC - CV
62. During a company event, you had the opportunity to talk to a colleague project manager. He
told you that in his current project actual costs are 15% under cumulated costs budgeted for
today.
The information given to you by the colleague is not sufficient to assess project
performance.
The project will probably be completed with total costs remaining under budget until the
end.
A significant cost increase during the further course of the project will probably bring the
costs back to baseline level.
Original cost forecasting and budgeting for the project must have been poor to allow this
variance.
Project managers should visit their customers far more often than what is usual in order
to avoid misunderstandings and bad emotions.
International projects may have an increased need for traveling which can lead to
additional costs and troubles with time zones.
Committee decisions can have the paradox outcome, that a jointly made or approved
decision is not desired by any individual group member.
A project is a temporary endeavor undertaken to create a unique product, service or
result. Repeating it would be similar to making the same journey twice.
64. Which of the following statements describes best the relationship between project phases and
the project life cycle?
The project life cycle includes the time when the project is performed and the expected
product lifespan after that.
In project management, the sequence of project phases and phase gates is often
referred to as project life cycle.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 16/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
The project life cycle is regarded as a sequence of project activities while phases are
defined to control overlapping activities.
The project life cycle describes how iterations of project management processes are used
when a project schedule is developed.
65. Which is an appropriate order in most project situations for the development of scope-related
documents?
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 17/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
A metaphoric description of the short term uncertainties that are present in every project.
The graph that describes the typical growth of earned value during the course of the
project.
67. An output of the process Estimate activity resources is a document called "activity resource
requirements". It identifies the types and quantities of resources...
68. What is not the purpose of configuration control when configuration management is applied in
a project?
69. Which statement describes best the meaning of the term cost baseline?
A cost baseline is always created by translating time-phased cost information into cost
data on activity or work-package level.
A cost baseline is an approved time-phased budget that will be used to measure and
monitor cost performance on the project.
Data to draw a cost baseline can be easily generated and updated as necessary from
information related to actual project cost.
A cost baseline is usually displayed in the form of an inverse S-curve drawn from the
beginning of the project until data date.
70. Which is not true in regard of RoI (return on investment) for a project?
It defines the cumulated net income from an investment at a given point in time or during
a defined period.
It includes investment, direct and indirect costs and may include allowances for capital
cost, depreciation, risk of loss, and/or inflation.
It is most commonly stated as a percentage of the investment or as a dimensionless
index figure.
It is the time when cumulated net income is equal to the investment.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 18/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
71. A project sponsor requested earned value data on two concurrent projects from the project
managers. Both projects are regarded as equally important and strategically beneficial and
have been finished by over 80%. He received the following information:
Project A:
PV: $1,800,000
EV: $2,300,000
AC: $2,100,000
Project B:
PV: $2,000,000
EV: $1,500,000
AC: $1,600,000
The sponsor considers to shift some resources from project A to project B to speed up the
second project which is currently behind schedule.
Changing team assignments during late course of a project typically increases cost
efficiency.
Changing team assignments during late course of a project typically increases time
efficiency.
According to the law of diminishing returns, the consolidated cost variance of the two
projects will decrease.
According to the law of diminishing returns, the consolidated cost variance of the two
projects will increase.
72. Which of the following statements describes best the relationship of quality and grade?
Low grade is always a problem; low quality may be overcome by a good rework and
repair process.
Grade is a category or rank given to entities having different functional requirements but
the same need for quality.
Both quality and grade can often be improved through intelligent measuring, testing and
examining.
Low quality is always a problem as it bears on the ability of an item to meet
requirements; low grade may sometimes be acceptable.
73. Network templates which contain only portions of a network are often referred to as
Programs
WBS items
74. You have been asked to calculate the internal rate of return (IRR) of a project? What will you
assess?
The time period needed to pay back the investment from a project when future income is
discounted.
The inherent discount rate or investment yield rate produced by the project's deliverables
over a pre-defined period of time.
The rate of negative risk that can be accepted for a project without turning the expected
net present value negative.
The expected benefit from a projects deliverable calculated as a percentage of the
original investment over a specified time period.
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm 19/22
14/07/2013 Test time: 02:04:32 - Total test time: 90 Min.
75. You just created the following network logic diagram to describe the planned flow of activities
for your project which will start tomorrow:
Which potential inconsistency in the diagram should you solve right now?
Result: of 75, %
N otes :
- A fter c lic king the Solve Sample T es t button, the correct answers will be highlighted in blue c olor above in the
ques tions & ans wers s ec tion.
- P M I made a dec is ion in 2 0 0 6 to not publis h pas s ing s c ores for the exams any more. T he ac tual s c ore is es timated to be
between 7 0 % and 7 5 % . I rec ommend to target 75% results or better in this and all other diffic ult prep tes ts you are taking,
8 2 % in s imple tes ts .
I am...
...generally interested in the PMP
certification.
M o r e P r o v id e r s o f F r e e P M P ( +C AP M )
P r e p a r a t io n Q u e st io n s
Christelle P. from Canada mailed Oct 11 2003:
"I passed the test! Thanks for the 75 prep questions. The only way to succeed is to write tons of
practice exams!"
So true! In 2002, I was the only provider of free PMP exam prep questions on the web. Today, you
can find thousands of them on the web.
Below are links to many providers with more than 3,000 free prep items (questions and answering
options); more than 4,000 for PMI members:
# of
Level of
free
Provider URL Comment difficulty
test
(explain)
items
Ajith Namboothiri www.ajithn.com 208 Requires registration. Number of
questions may grow, as visitors
are invited to add further
questions. Many questions of
C APM exam style.
La Tha 206-free-pmp-exam- 206
questions.blogspot.com
C ertC hamp www.certchamp.com 200
C ertGear www.certgear.com 6 Free trial of C ertGear's exam
simulator.