Professional Documents
Culture Documents
Reidbar used on
Network Arch Bridges
Designers Holmes Consulting Group attended a conference in 2007, given
by HERA's Bridge Design Group, on network arch bridges by Dr Per Tveit
of Norway. Network arch bridges have been used in Europe for some 40
years and have been shown to be economical in both construction and
maintenance.
Bridge 47, Mangamahu Road spans over the Mangawhero River north east
of Wanganui. Back in July 2006, devastating floods destroyed the original
3-span bridge and resulted in a temporary Bailey bridge erected to
maintain permanent access, till a replacement could be provided.
Suitable for shorter spans from 80m to 250m and made of composite steel
and concrete, these bridges have significant advantages through efficiency
of materials, in comparison to other forms of tied structures.
Using the arch concept enabled the opportunity to remove the central pier proposed in the middle of the
river, and eliminate the costs associated, with the river protection works that the central pier would have
required. The network arch superstructure is also shallower than the original bridge, meaning that the
approaches to the bridge did not have to be raised, in order to maintain clearances to the river below.
The relatively light superstructure allowed the use of common size mobile cranes.
Overall, the network arch bridge was the cheapest tender received for this project, producing a 30% cost saving from the
Council's conforming design and was completed, four months ahead of the envisaged program.
The resulting bridge is simple, elegant in design and an innovative solution for the site.
Project Specification
Bridge Specification
www.reids.co.nz 0800 88 22 12
Features
POST-TENSIONED Page 2
Slab-on-Grade Floor Systems Dereks Desk
Looking back on that first trip three things stood out Page 4
as opportunities in New Zealand: Compliance:
1. Tilt-up and Precast walling systems should be able to replace blockwork Clutch Discard Criteria
and metal-clad industrial and commercial buildings being built at the
time. Page 5
2. A more efficient and cost-effective precast connection system was Safety:
needed for the Precast Seismic Frame Building System that had
been introduced by Auckland Engineer, Carl OGrady. Safe Lifting Guide
3. The American system of using greased and sheathed strand seemed
far more efficient than the reinforced and saw-cut approach being used Page 6 / 7
for the construction of slabs on grade in New Zealand.
Bracing Feature:
Opportunity 1 was achieved with the introduction of properly designed lifting and Case Studies
propping systems with software programs that enabled us to tilt or rotate large
panels up to six storeys high into place without cracking the concrete.
Page 8
Opportunity 2 was realized when we entered into an agreement with Pacific Steel to New Technology:
produce our Reidbar System, which meant we could offer a Reidbar Grout Sleeve Magic Patch / Magic Coat
to provide a full-strength structural connection between precast structural elements.
Orbiplate
Opportunity 3 was attempted in the mid 1990s when we introduced the SwiftFloor
system. This involved using normal Reidbar placed inside PVC ducts to post-tension Page 9
concrete floor slabs. Product Launch:
Corrugated Tubing
Several very successful SwiftFloors were produced, including the Riccarton Shopping
Mall in Christchurch and the Harvey Norman warehouses on Aucklands North Shore. Stainless Steel Lifting Anchors
There were, however, several limitations to the Swiftfloor System due to having to use
low-strength Reidbar rather than proper post-tensioning strand. These included the Page 10
low level of pre-stress provided by 500 Grade Reidbar, the short lengths of Reidbar,
the cost and labour involved in threaded Reidbar into PVC tubes, etc. Because of this Sustainability:
Reid stopped promoting SwiftFloors ten years ago, even though several contractors Nirvana Code Compliance
have continued to use them. Building Green
Now finally after twenty-five years Reid New Zealand are launching a dedicated
post-tensioning flooring system complete with greased and sheathed strand, end Page 11
anchorages, slab edge rebate formers, edge reinforcing systems, etc. New Products
The first shipment is due to arrive at the end of April with most of the first container
load already allocated to projects where specifiers and builders have been keen to
Back Cover
adopt the system immediately. Sponsorship
Precast companies are keen to adopt the product and our Reid design service, which
will replace strongbacks and expensive timber shutters to enable slender precast
elements to be transported and erected on site.
New Zealand building owners can now enjoy the benefits of crack and joint-free
concrete floors that will not deteriorate quickly the way that saw-cut floors tend to do
under heavy wheel and fork hoist loads.
2 www.reids.co.nz 0800 88 22 12
Page
ECC Development
BRIDGE MAINTENANCE
Recent figures indicate that in the U.S
Unlike conventional tension-softening concrete and fibre-reinforced concrete, ECC exhibits metal-
alone, an investment of $9.4 Billion per
year for 20 years is needed to eliminate like tensile strain hardening behaviour after matrix first cracking. The tensile ductility of the ECC we
are producing, is several hundred times that of normal concrete and the fracture toughness, is similar
all deficiencies, in the stock of 590,750
bridges.
We initially thought, that the largest potential for ECC was thin-walled precast elements, such as walls
and stairs. We soon realised, however, that the ability of this ductile concrete to be sprayed onto
HISTORICAL vertical or even overhead surfaces without debonding, opened up huge opportunities for remedial
RESTORATION
This heritage building will be seismically or retrofit projects.
upgraded in 2009 with `ReidCrete ECC
shotcrete and moved to its new site.
Reid engineers visiting Japan and the USA, were originally skeptical that the spraying of ECC onto
the under-side of concrete bridge beams could significantly contribute to the structural integrity
SEISMIC RETROFIT
There are 3500 unreinforced masonry
and longevity of these structures. Field and University testing, however, proved that ECC was highly
buildings in New Zealand requiring
seismic upgrade. Additionally, there are effective in this regard.
millions of buildings scattered across the
world in the same condition. Earthquake
damage to unreinforced masonry
buildings can be severe and fatal.
The reason ECC is so effective as a retrofit material, is the materials ability to micro-crack under
significant tensile or flexural deformations. Even if the cracking stress of the retrofit for ECC material
MODULAR STAIR
is exceeded, the crack width is restricted to approximately 0.1mm. This property enhances the
SYSTEM durability of the retrofitted structure, as even cracked ECC provides superior resistance to the
`ReidCrete ECC makes precast stairs
far lighter and more economic than passage of carbon dioxide or chloride ions, than the original concrete cover provided when the
conventional precast stair systems.
Stair systems can be assembled
on site without the need for large
structures were first constructed. Enviromental sustainability is also a significant advantage as a result
cranes.
of the use of Flyash in the mix.
PRECAST FLOOR Worldwide about 10% of GDP derives from infrastructure construction. In most industrialised
SYSTEM
`ReidCrete ECC precast flooring
countries, including New Zealand, roading, rail and marine infrastructure is aging. In the USA alone,
systems are prefabricated, light weight
and provide the benefits of a concrete 40% of their bridges are in a state of serious deterioration. In New Zealand, a similar assumption
would be reasonable.
floor while allowing easy fixing of
ceilings and installation of services.
reidCrete www.reids.co.nz
Reid ECC Modular Pre-cast Stair System
Recent research and development on 'bendable' ECC concrete (Engineered Cementitious
Composite), has highlighted an abundance of potential products for manufacture by the NZ Precast
Industry. One of those key products is a modular precast stair system. Another Reid innovation is
taking place.
Architectural Specification
Can be coloured using Peter Fell coloured concrete.
ECC is Environmentally Sustainable as a result of the use of Fly Ash during manufacture. Fly Ash is a by-product of coal
generation.
Modular Precast Stair System can be used in residential applications - no squeaking, lighter handling, minimal to no crane time
Suitable for tiling
For further information on this system, please contact Steve King, Development Manager ECC at stevek@reids.co.nz 3
Page
Compliance
The Approved New Zealand Code of Practice for Load Lifting Rigging (Section 5.13.1) requires that all
lifting eyes be recorded in a register and that a visual inspection should be made each time a lifting
eye is used.
3. The lifting eye must remain true to the dimensions and form in the drawing, with the exceptions
listed below (items 4-6).
4. The crown of the handle (dimension K) may lose up to 20% of its depth by metal displacement
by point loading of lifting shackles or hooks, at the mid point of (dimension A).
5. The loop through the sphere may lose up to but not more than 10% of diameter due to wear.
6. The slot in the sphere (dimensions H and M), must not exceed the maximum and minimum
dimensions given in the Reid Swiftlift Design Manual.
Gauges for 1, 2 and 5LE slots are available at no charge from Reid. 10 and 20LE slots must be
measured using callipers.
9. Where any doubt exists, individual Swiftlift Lifting Eyes may be sent by Reid Branches to Reid Head Office located in
Auckland, for QA inspection and proof testing.
10. Where tensile testing is found necessary (para 2 above), Swiflift Lifting Eyes should be tested in both straight tension relative
to the axis of the anchor and at ninety degrees to that axis where the stress is across the slot in the sphere.
4
Page
Safe Lifting
We have updated our Safe Lifting training to include the new range of Edgelift Anchors with Feet and Plate / Face Anchors.
To ensure that your staff are up with the play, discuss with your local Reid or Ramset representative about our precast and tiltup
training program. All site personnel who complete the traing receive a Reid Hi-vis vest and Certificate of Completion.
Cheap tilt
-up or pre front
cast ancho
rs m ay sa ve you money up
but they can a
lso result in huge costs down the track.
Fortunately, Reid offers an alternative with total construction solutions that help
control costs in terms of safety, efficiency and productivity.
All things considered, can you afford to work with anyone else?
5
Page
Convenient Bracing
Saxton Fields Sports
Stadium Complex
Construction on the Saxton Fields Sports This is not a typical application for I asked Dave Anderson from John Jones
Stadium has been underway since late Reidbrace and came about during a Steel, What makes you continue to use
last year and is the largest investment value-added engineering session with Reidbrace? His reply was short and to
into sports facilities in the Nelson area to Arrow International, Project Managers and the point its so convenient to use
date. Over $12 million has been raised by Connell Wagners Carl Devereux, Design
the local community, Nelson City Council Engineer.
and Tasman District Council to build the
facility which has space to accommodate
five international sized netball courts,
12 volleyball courts, as well as room for
administrative offices.
In all, this project has been successful through ease of installation, time savings and the reduction of costs. For further information,
please contact the Reid Engineering Department, Terry Seagrave on 0800 88 22 12.
Mick and Phil used Reidbrace fittings in their scaffolding design, a truly unique
way of fitting a hanging structure. Holes were drilled through the road surface and
Reidbar was then inserted into the holes and fixed with Reidbar flange nuts.
From the underside of the bridge, Reidbrace ends hold up the working platform
6m x 100m long. 4m wide cantilevered split level wings were installed on each
side to gain access to the outside of the bridge balustrades. In all, over 100 tonne
of scaffold was fixed in place.
The project is due to finish early 2010 and will be able to survive a one-in-a-
thousand-year earthquake and handle up to 1200 buses each weekday. It is a
tribute to the original engineering design and it will continue to survive many years
to come.
www.camelspace.com
7
Page
New Technology
Light weight.
Strong - cures to a maximum strength of
20 Mpa.
Fire resistant.
Excellent high bond / adhesive qualities.
Steel trowel finish is smooth and will
match the base surface. Lightweight
Extremely cost efficient high build and Concrete Patching
finish coat all in one pass. Mortar
No primer required further reducing Reid Orbiplate Connector is a
application time patented assembly which assists in the
Once dry, Magic Patch can be sanded off connection of steel to steel or steel to
to provide a smoother surface if required
concrete allowing generous tolerances
0800 88 22 12
in all directions and providing a
full strength, non slip, structural
connection using only a spanner.
Suitable for use in:
Magic Coat Roll- Curtain walling and faade panels
Panel to panel concrete elements
on Texture and Water- Resistant Steel structural beams to concrete
In-situ pouring
Membrane This economical solution, involving
a cast in ferrule, overcomes the costly
Magic Coat is a DIY easy to use 'One Coat' grey texture and water resistant
architectural finish coat that can be used on a variety of concrete products and inefficiencies of hitting reinforcing
substrates to cover unsightly concrete surfaces with a 'render' look at a cost during drilling on site, re-welding
effective price. and excess crane time.
Magic Coat should not be used to replace a render coat. SOLUTIONS IN CONCRETE CONSTRUCTION
If you would like to know more about any of the Magic Reid Construction Systems
Coat or Patch products, please contact Trish Croot at A Division of ITW New Zealand Ltd
trishc@reids.co.nz.
Phone: +64 9 920 4350
Fax: +64 9 920 4364
Email: sales@reids.co.nz
Web: www.reids.co.nz
8
Page
Product Launch
There are, however many instances where joints between precast The Red Cross was thrilled with the donation and were
elements are not highly stressed and unlikely to be subjected to putting the funds to good use in assisting more than 7500
cyclic seismic loads. To cater for this, Reid has introduced its people whose homes were either destroyed or rendered
own corrugated tubing to provide solutions for precast connects, uninhabitable.
service penetrations, formers for starter bars and post tensioning
ducts. ....I would like to thank you and the people in ITW
Construction Systems for your generous donations in support
The semi-rigid zinc plated metal duct is strong and durable for of the Red Cross Victorian Bush fire Relief Fund. You have all
casting into concrete and is easily tied into position adjacent to made a meaningful difference....
reinforcing steel.
9
Page
Sustainability
A Nirvana wall with 100mm inner structural layer has a mass of With Green Engineered products, design and construction
240kg/m, meets the Code requirement. professionals can meet the expectations for project design and
construction without compromise to product performance or the
Sample calculation for a normal Nirvana wall: 50/30/100 world we share.
R-value of moving air outside 0.040
R-value of 50mm of concrete 0.036 The cornerstone of the Green Engineered concept is our Research
R-value of 30mm of Nirvana Insulation Board 0.811 and Development of water based formulations. By using water
R-value of 100mm of concrete 0.071 based products, the impact on non-renewable resources such
R-value of still air layer inside 0.140 as petroleum and its distillates is reduced. The base for any
TOTAL R-value 1.098 biodegradable product, the best eco-friendly choice, is water.
Summary Ask for the Noxcrete water based products by name and accept
For all NZ Climate zones except Zone 3 - Option 3A standard nothing less.
30mm thick, Nirvana Poly Board used in a 50/30/100 Nirvana
wall will exceed the minimum wall R-Value of R1.0. For Zone
3 - Option A, replace 30mm board with 50mm to increase the Bio-Nox - 100% Biodegradable Form Release Agent
R-Value as required.
Formcoat E - Waterbased Form Release Agent
For further assistance on Nirvana R-values, please Silcoseal Select - Waterbased Bondbreaker
contact Ken Yallop at Reid on keny@reids.co.nz or
0800 88 22 12.
10
Page
New Products
Over the past two years, R&D have been developing an effective McDowel strip has a smooth upper face which allows the
anti-impalement cap for reobars and warratahs. precast floor slabs to move or rotate slightly with temperature
or shrinkage movements, while the patented serrated bottom
The Lifeguard reusable safety cap is manufactured from robust, face grips the bearing surface, preventing the strip from
UV-stabilised polypropylene and is designed for 12-20mm and 24- working its way out under cyclic movements.
36mm bars / warratahs.
The McDowel Bearing Strip is made from 100% recycled plastic.
The domed carapace is 115mm diameter and has an encapsulated
domed steel plate 2mm thick, with a central raised boss. Reg Design #27918
The product has undergone rigourous testing in Australia. Data Product Codes: Width Length
shows the Lifeguard cap is successful up to a weight of 114kg, MCDSTRIP75 75mm 2.4m
dropped from 3.05m high. MCDSTRIP100 100mm 2.4m
If you are concerned about site safety, why would you chose
anything else?
Shotcreting
Fibre Reinforced Polymers
Post Tensioning
Reid take 3rd place at2009
The research project focuses on Shotcreting using ECC
NZIOB PlaceMakers Golf Day
(Engineered Cementitius Composite) because it exhibits The Reid team of Eric Sangster (Stevensons Precast), Ashley
strength and strain hardening, as a cost-effective option for Ward (Reid), Bill Pretorius (Northern Gateway Alliance), and
retrofitting existing buildings. Keith Lesslie (Northern Gateway Newmarket), had a very
successful day at the recent NZIOB PlaceMakers Annual Golf
Reid applied for a TechNZ Research & Development and Tennis Tournament held at North Shore Golf Club.
scholarship grant and were awarded it on the basis that we
would employ a Post Graduate student for a year. The team was placed third overall. Well done guys! Special
thanks to Cameron Gilmour, the Reid caddy for the boys.
Yi-wei Lin is the Masters student who has come on board with
the Reid team to develop a suitable ECC shotcrete mix using Kay, Jim, Mason and Trish spent the day cooking flounder fillets
NZ materials. Throughout 2009 Yi-Wei will conduct tests on and serving them up to the players. A fun day was had by all.
unreinforced masonry walls sprayed with ECC, to determine
what level of seismic resistance can be achieved. Reid are proud to be Bronze sponsors of the Golf Day.