You are on page 1of 28

Energy Practice

RISK Engineering Position Paper 01

Atmospheric
Storage Tanks
ii Atmospheric Storage Tanks
Contents
Section Title..............................................................................................................................Page

1. Background...................................................................................................................................... 1

2. Objective.......................................................................................................................................... 1

3. Scope................................................................................................................................................ 1

4. Selection of Atmospheric Storage Tanks............................................................................................ 2

5. Layout and Spacing........................................................................................................................... 3


5.1 Bunds (Dykes)................................................................................................................................... 4

6. Primary Containment........................................................................................................................ 5
6.1 Tank Design & Operation................................................................................................................... 5

7. Secondary Containment................................................................................................................... 8
7.1 Bund Integrity (leak tightness).......................................................................................................... 8
7.2 Tertiary Containment........................................................................................................................ 9

8. Overfill Protection........................................................................................................................... 10

9. Maintenance and Inspection........................................................................................................... 11

10. Leakage and Fire Detection............................................................................................................. 12


10.1 Leak Detection................................................................................................................................ 12
10.2 Fire Prevention and Protection........................................................................................................ 12

11. Fire Fighting Systems...................................................................................................................... 14


11.1 Water Systems................................................................................................................................ 14
11.2 Foam Fire Fighting Systems............................................................................................................ 14
11.3 Application Rates............................................................................................................................ 16

12. References to Industry Losses......................................................................................................... 17

13. References to Industry Standards.................................................................................................... 17

14. Appendices..................................................................................................................................... 19
Appendix A - Assessment Checklist................................................................................................. 19
Appendix B - Mechanical Component Checklist for Floating Roof Tank Inspections......................... 20
Appendix C - Loss Incidents............................................................................................................. 21

REV 1.0. Published: February 2011 Marsh iii


1. Background
There have been numerous incidents in the oil, gas and petrochemical industry involving atmospheric
storage tanks. Data has been compiled by a reputable operator in the USA that indicate that
overfilling of atmospheric storage tanks occurs once in every 3300 filling operations. In 2009 there
were two separate incidents just days apart, one in Jaipur, India (October 29) and one in San Juan,
Puerto Rico (October 23) that demonstrated the destructive capabilities of incidents at terminals and
tank farms.

The Buncefield incident in the UK in December 2005 resulted in an independent investigation


commissioned by the Health and Safety Commission in the UK. As a result of this, more guidance has
been provided to designers and operators of facilities. Such guidance has been included within this
position paper.

2. Objective
The objective of this position paper is to define the standards that would be expected of a very good
atmospheric storage facility in the oil, gas and petrochemical industry. These standards are also
reflected in the Marsh Energy Risk Ranking criteria. They can be used to determine risk improvement
opportunities and also to provide detailed advice to clients seeking to improve their atmospheric
storage facilities.

3. Scope
The scope of this position paper includes:

Guidance on the appropriate selection of atmospheric tank design for class of product to be stored

Guidance on layout and spacing

Guidance on appropriate means of ensuring primary containment

Suitable design of secondary containment

Detection arrangements for loss of primary containment and fires

Fire protection arrangements

Examples of loss incidents involving atmospheric storage tanks

1 Atmospheric Storage Tanks


4. Selection of Atmospheric
Storage Tanks
The layout and general design of a storage facility should be based upon
considerations of safety, operational efficiency and environmental protection. A
primary consideration is ensuring that the design of the storage tanks themselves is
suitable for the classification of the hydrocarbon being stored.

The table below summarises the design of tank suitable for each class of
hydrocarbon:

Crude oil Definition Recommended


derivative Storage Tank Design
class
Floating Fixed Roof
Roof
Class 0 Liquefied petroleum gases (LPG)
Class I Liquids which have flash points below
21C
Class II (1) Liquids which have flash points from 21C
up to and including 55C, handled below
flash point
Class II (2) Liquids which have flash points from 21C
up to and including 55C, handled at or
above flash point
Class III (1) Liquids which have flash points above
55C up to and including 100C, handled
below flash point
Class III (2) Liquid which have flash points above 55C
up to and including 100C, handled at or
above flash point
Unclassified Liquids which have flash points above
100C

Marsh 2
5. Layout and Spacing
Ideally, tank layout should be optimised to ensure that there is sufficient access to tanks for fire fighting
and to minimise the risk of escalation in the event of a tank fire.

Minimum spacing for tanks is specified in the table overleaf, although Marsh would advocate a minimum
separation distance of 1x the diameter of the largest tank with an absolute minimum of 15 metres, as such
a distance provides sufficient access for fire fighters.

Factor Minimum Seperation from any part of


the tank
Between adjacent fixed-roof tanks Equal to the smaller of the following:
(a) the diameter of the smaller tank;
(b) half the diameter of the larger tank;
(c) not less than 10m (Marsh advocate 15m).
Between adjacent floating-roof tanks 10m for tanks up to and including 45m
diameter.
15m for tanks over 45m diameter.
(The spacing is determined by the size of the
larger tank).
Between a floating-roof tank and a fixed- Equal to the smaller of the following:
roof tank (a) the diameter of the smaller tank;
(b) half the diameter of the larger tank;
(c) not less than 10m (Marsh advocate 15m).
Between a group of small tanks and any 15m
tank outside the group
Between a tank and the site boundary, 15m
any designated non-hazardous area,
process area or any fixed source of
ignition

Source: HSG 176. The storage of flammable liquids in tanks.

One notable exception is the separation between crude tanks, where the destructive effects of a boil over
can extend from 5 to 10 diameters. Therefore consideration should be given to locating crude tanks at the
edge of tank farm installations and with the largest practical separation from adjacent tanks.

These distances should only be used in conjunction with appropriate levels of fire protection (see below).
In the event that tanks are existing and do not conform to the above spacing, then additional fire
protection should be considered.

Floating roof tanks, with external metal domed roofs extending over the entire roof area (i.e. internal
floating roof tanks or tanks fitted with geodesic domes), may be considered as fixed roof tanks for the
purpose of tank location and spacing.

3 Atmospheric Storage Tanks


5.1 Bunds (Dykes) should be fitted with a water resistant
liner and whilst grass growth is
Above-ground tanks should be acceptable, it should be regularly
completely surrounded by bund walls maintained and kept short.
(see also Secondary Containment).
These should be designed to offer Tanks should ideally be located alone
protection to fire fighters. Therefore the within their own bunds, although
bund wall should be located so that a whenever tanks share a common bund,
reasonably close approach can be made intermediate walls up to half the height
to a tank fire. of the main bund walls and no more
than 0.5 metres high should be
Fire fighting screens and steps should provided to control small spillages from
be located at various points around the one tank affecting another.
bund wall to assist the positioning and
protection of fire fighting personnel and Bund floors should drain to a single
equipment. location complete with sump for the
regular removal of water from rainfall or
Bunds would normally be constructed firewater testing. Drains should
from earth or preferably concrete and normally be kept closed, with the drain
should be largely impervious to liquid isolation valve situated outside the
and capable of withstanding hydrostatic bund.
and hydrodynamic pressures to which
they could be subjected. Earthen bunds

Marsh 4
6. Primary Containment
It is essential that the risk of loss of tanks, refer to the UK HSEs review of High level alarm and independent
containment is properly managed. standards, Mechanical integrity back-up high level instrument (with
This can be achieved by the proper management of bulk storage tanks executive action only if
design, operation, maintenance and which can be found at the following appropriate)
inspection of tanks. Ideal practice is website address:
outlined below. Continuous automatic monitoring
of tank contents, including rate of
http://www.hse.gov.uk/research/rrpdf/
change during filling/emptying
The most effective way to prevent a rr760.pdf
major accident at any site is the Anti-rotation devices on floating
continued provision of suitable Outlined below is a summary of the roof tanks
primary containment of the features considered to be the most
flammable materials. This is achieved appropriate for a modern facility: Closed water drains
through the suitable design,
Single skin floors
construction and maintenance of the Double seals on floating roof tanks
storage systems in accordance with (NB foam dam heights should be Tank floor leak detection on double-
standards. above the height of the upper rim floor tanks. This is normally
seal to provide suitable protection comprised of an instrument to
For guidance on the most appropriate against a rim seal fire) detect loss of vacuum in the inter-
standards to use for the design and floor space
construction of atmospheric storage

6.1 Tank Design and accordance with a relevant standard Whenever valves are left normally
such as EEMUA 183 or BS EN 14015. open, then the following measures
Operation Leak detection should also be should be put in place:
Tanks should be designed to a provided on double-bottomed tanks.
relevant standard, such as API 650 or Hydrocarbon detection in drained
BS EN 14015. water with automatic isolation
Tank Roofs
Testing of operability of isolation
In some instances single skin bottom Double deck roofs on floating roof valves and detection systems (see
tanks are a better option than double- tanks are preferred to single deck overleaf)
bottomed tanks as these provide the roofs with external pontoons as they
optimum conditions for ensuring are more stable and less likely to lose
integrity of the tank floor by the buoyancy. Vents
inspection of tank floor plates.
Tanks should be provided with a weak
Disadvantages of double-bottom For floating roof tanks, the water seam/frangible roof construction, or
designs include settlement, product drains to remove rainwater from the with an emergency vent suitably sized
entrapment and modification to roof should be normally closed. To for the worst case relieving scenario,
nozzle compensating plates. ensure roofs are emptied of rainwater, to prevent overpressure under all
procedures should be in place and relief conditions. Emergency vents
Where double-bottomed tanks are followed for the opening and should comply with relevant
provided, additional inspection re-closure of valves. standards, such as API 2000.
measures should be provided in

5 Atmospheric Storage Tanks


Wherever a fixed roof tank is used for Rim Seals & Foam Dams
the storage of materials with a flash
point below 21C (generally on day Double rim seals (of fire-resistant
tanks, not recommended for large construction) are preferable to single
bulk storage tanks), then flame seals. Due to irregularities during the
arresters should be provided on the construction phase of large floating
vents to prevent ignition of the roof tanks, it is likely that a single seal
flammable vapours burning back into will not maintain a 100% seal
the tank. In warmer climates, where between the tank roof and tank wall
product surface temperatures could along the entire height of the tank
exceed 21C, flame arresters should wall. Therefore, a second seal will
be used wherever maximum surface improve the likelihood of achieving a
temperatures could be within 10C of tight seal, will reduce emissions and
the flash point. minimise the risk of rim seal fire.

Flame arresters should be included in When installing double rim seals, the
preventative maintenance routines to height of the second, upper rim seal
ensure they do not become blocked should be below the height of the
by scale, paint, ice or other materials. foam dam to ensure coverage
Flame arresters are not whenever rim seal pourers are
recommended for use when the activated.
material being stored is liable to
polymerise or foul the arrester. Due to Foam dams should be provided with
are specifically designed to maximise
the potential for blockage, intermittently-spaced gaps to allow
spread of fluids over a tanks surface.
conservation vents (vacuum and the drainage of rainwater. However, if
pressure relief) should not be fitted the gaps are too large or too
numerous, they may affect the ability For existing tanks, consideration
with flame arresters.
to form a single continuous foam should be given to modifications of
barrier in the event of a fire. tank top design and to the safe-re-
Fixed roof tanks can be fitted with a routing of overflowing liquids.
gas blanket (normally nitrogen) to
maintain an inert atmosphere in the Overflow
vapour space. Nitrogen supply Valves
pressure should be just above Consideration should be given to
providing suitable overflow systems All important valves on atmospheric
atmospheric, but sufficient to
to ensure that in the event of a tank tanks should be labelled and their
displace any liquid pumped out. As a
overfilling, the tank contents are function indicated.
back up, a vacuum breaker should be
provided in the event that nitrogen safely routed into suitable secondary
supply is lost. containment. Additionally, the Fire-safe shut off valves should be
overflow route should be designed to provided, preferably automatic and
minimise turbulent flow, reduce the remotely operated shut off/isolation
Vents or vapour recovery systems
surface area of flammable valves (ROSOV/ROIV). They must be
(often venting back to the source
hydrocarbon and reduce the fitted close to the tank on both the
vessel) are required. These should be
generation of flammable vapours, inlet and outlet connections. Valves
designed to relieve pressure slightly
such as through splashing. Particular must either conform to an
above that of the nitrogen and at a
care needs to be taken with appropriate standard, such as BS EN
suitable margin below the design
strengthening rings and firewater ISO 10497 or equivalent international
pressure of the storage tank.
dispersion rails around tanks which design, or should be of intrinsically

Marsh 6
fire-safe design. Such features Designed to minimise pressure Housekeeping
include: surges on system pipework and
couplings, particularly ship to shore Debris within bunds should be kept at
Metal-to-metal seats (secondary flexible pipes an absolute minimum. In addition to
metal seats on soft-seated valves the checks within formalised
are acceptable) Tank drainage valves should be inspection and maintenance routines,
blanked off when not in use. operators should also conduct
Must not be of cast-iron Whenever operations to remove frequent checks of tanks and their
construction accumulations of water from components as part of their routines
underneath the product are to be to ensure that the tanks are kept in a
Should not be wafer-bolted
conducted, isolation of the drain reasonable condition. A sample of
(sometimes referred to as long bolt
should be achieved by the use of two items to check is included in
flanges)
valves in series. The second valve can Appendix B.
In regions subject to a high risk of be a temporary installation.
earthquake and/or rapid ground-
acceleration, the isolation valves and
Piping
actuators should also be secured
directly to the tank wall and not to the In areas where earthquake is a
ground. Anchoring the valve to significant exposure, all associated
surrounding structures or the ground piping on storage tanks should have
could result in the valve separating step geometry to allow flexing in the
from the tank during excessive piping and prevent puncturing of the
vibrations. tank during an earthquake.

Features of the ROIV should be: Suitably designed seismic hangers


should be provided in earthquake
Fail safe (or if not fail safe have a zones, and pipe supports should have
back-up power supply, especially if fire protection within fire hazard
the emergency plan requires the zones, e.g. within the bunded area.
tank to be drawn down in an
emergency)
Testing
It should not be possible to auto-
reset the ROIV Before filling tanks with flammable
liquids, leak testing of the installed
Adequate margin of safety for tank and associated pipework is
shutting off the valve, with at least required. Hydraulic testing should
150% torque available from fully only be used (i.e. not pneumatic) as
open to fully closed stored energy in hydrotesting is
substantially lower, and inherently
No manual operation or override
safer. However, air may be used as a
(e.g. hand wheels) which may
means of applying pressure to water-
inhibit the operation of the ROIV
filled tanks and piping.
Suitable integrity and performance
to satisfy the SIL (Safety Integrity Salt water should not be used to
Level) requirements hydraulically test systems containing
stainless steel.

7 Atmospheric Storage Tanks


7. Secondary Containment
Whilst priority should be given to preventing loss of primary containment, adequate secondary (and sometimes tertiary)
containment is necessary for the protection of the environment and to contain any spillages. In atmospheric tank
applications, secondary containment will be provided by bund walls.

Bund capacity should be sufficient to contain the largest predictable spillage. A bund capacity of 110% of the capacity of
the largest storage vessel within the bund will normally be sufficient. When estimating bund capacity, the space occupied
by other tanks should be taken into account.

7.1 Bund Integrity augment non-fire resistant materials. Bund floor penetration joints are
Similarly, joints to wall and floor inherently weak as failure of the
(leak tightness) penetrations need to be protected integrity is difficult to predict and
Bund wall and floor construction against the effects of fire. detect and may continue for some
should be leak tight. This includes the time unnoticed. Consequently, floor
provision of leak tight expansion Whenever designing protection plate, penetrations should not be
joints between different casts of consideration should be given to incorporated into new bund designs.
concrete in bund walls and wherever avoiding weakening the wall structure Existing bund floor penetrations
there are penetrations in the wall for in relation to resistance to fire, should be eliminated wherever
pipes. Surfaces should be maintained hydrostatic and hydrodynamic forces. practicable. Where flexible sealants
crack free, and without any are used in floor penetration joints,
discontinuities, and without any failed Bund penetrations should be avoided these should be replaced with fire-
joints that may allow liquid migration. unless alternative over-wall routings resistant sealants.
are not practical. On existing bunds,
As observed in major incidents, such fitting steel collars or bellows to There have also been a number of
as the Buncefield fire of 2005, the improve fire resistance at pipework significant accidents resulting from
joints in concrete bund walls are penetrations may introduce local leaks of hydrocarbons from tanks
particularly susceptible to the effects corrosion initiation sites in the through the base of storage tanks.
of fire and/or subsequent cooling. pipework and is not recommended Therefore the provision of a suitable
Therefore, to maintain integrity, joints unless corrosion prevention can be impervious base (ideally concrete
should be capable of resisting fire. assured. Where corrosion can not be with a membrane liner) or floor leak
Ideally, steel plates (waterstops) prevented, joints should be improved detection on double floor
should be fitted across the inner by replacing existing sealants with configurations should be provided.
surface of bund joints and fire fire-resistant sealants.
sealants should be used to replace or

Marsh 8
7.2 Tertiary Of cellular configuration to allow
segregation and limit the extent of
Containment spread of pollutants and/or fire
Tertiary containment need only be
Robust under emergency
concerned if there is a significant risk
conditions, e.g. loss of electrical
of secondary containment being
supply
insufficient to prevent an escalation
to a major accident affecting Capable of allowing the controlled
personnel, assets or the environment. movement of contained liquids
Firewater containment is one such under normal and emergency
example. Implementation of tertiary conditions
containment should therefore be a
risk-based decision. However, tertiary Capable of aiding the separation of
containment should be: water from pollutants (e.g. oil/
water separator)
Independent of secondary
containment Able to manage rainwater and
surface waters
Capable of fully containing
foreseeable firewater and liquid More guidance on tertiary
pollutant volumes on the failure of containment can be found in
secondary containment documentation including CIRIA 164
and PPG18.
Impermeable to water and
foreseeable entrained pollutants/
hydrocarbons

9 Atmospheric Storage Tanks


8. Overfill Protection
All tanks should be fitted with a suitably high integrity The trip function should include an audible/visual alarm
overfill protection system, which should be designed to SIL to prompt a check that the trip function has been
1 as a minimum, depending upon the risks associated with successful
failure.
In some cases it may be necessary to terminate the transfer
Overfill protection systems should be automatic and in a more gradual fashion, such as by limiting the closure
physically and electronically separate from the tank rate of the isolation valve to avoid damaging overpressures
gauging system, i.e. have an independent level gauging in upstream pipework. Due allowance must be given to the
system and back-up level switch or duplicated level maximum filling rate between LAHH being activated and
gauging system. the isolation valve finally closing.

However, justification for a single combined gauging and The site receiving any batch or delivery must have ultimate
overfill protection device could be made if the integrity of control and responsibility for stopping the transfer and
the instrument is sufficient for the risk of failure. should have local systems and valves to stop the operation.
This should not therefore be under the sole control of an
Tank gauging systems should have a LAH (High Level automatic system or operators at a remote location.
Alarm) to alert operators to the status of the tank which
gives sufficient time to interrupt the filling operation and Tank level instrumentation and information display
the subsequent activation of the back-up overfill protection systems should be of sufficient accuracy and clarity to
device LAHH (High-High Level Alarm). This should also ensure safe planning and control of product transfer into
take into account any thermal expansion of the fluid within tanks.
the tank. It is important that LAH should not be used to
control routine filling. It is preferable for tanks to be continuously and
automatically monitored for rate of level change during
Analogue sensors are preferred to digital (switched) transfer operations to match the actual rate of transfer with
sensors (i.e. there are two analogue sensing elements on expected rates. This would give an early indication that the
the tank), as these are able to alert whenever there is a fault main level gauging system was not functioning correctly or
in the primary level sensor before reaching high level. that the incorrect tank was being filled. During normal
storage operations, such a tool could also notify operators
Electro-mechanical servo gauges should be avoided for of a significant loss of containment.
use with flammable materials as these are intricate devices
considered to be vulnerable to a number of potential failure It is not within the scope of this document to detail the SIL
modes. Modern electronic gauge sensors, such as radar determination or its implications. However the following
gauges, should be used instead. points should be noted:

It is the Dutyholders responsibility to meet latest


Where practical the LAHH should have an executive action
international standards, IEC 61511 is a current good
to interrupt the filling operation by closing the isolation
standard
valve and/or stopping the pump. Features of a LAHH are:
The appropriate SIL required should be specified before
It should be set at or below the tanks rated capacity designing and installing overfill protection systems
Activation of the LAHH is to initiate a shutdown LOPA (Layer of Protection Analysis) is a suitable
LAHH may be limited to an audible/visual alarm to alert methodology to determine SIL
a human operator to rake the required action. Actions As overfill protection systems normally function
required must be specified and well documented. NB infrequently, they should be periodically tested in their
such options are not suitable for SIL 1 systems entirety to ensure they will operate when required

Marsh 10
9. Maintenance and
Inspection
All tanks must undergo regular Full floor scan
external and internal (out-of-service)
inspections to ensure their integrity Internal examination of shell to
and as such, a written scheme of annular floor weld
examination should be provided. NDE (Non Destructive
Overall guidance on the suitable Examination) of annular plate and
methods and frequency of such shell nozzles
inspections are detailed in EEMUA
159 and API 653. Visual inspection

Individuals responsible for the Deferral of internal inspections should


formulation of schemes of inspection be risk assessed and approved by a
and for the inspection of tanks should suitably competent person. Particular
be competent and have the attention should be given to tanks
appropriate qualification for tank that have had no previous internal
inspection and for the grade of inspection, as the probability of floor
materials used in construction. As a failure will increase with every year
minimum, personnel should be that the recommended interval is
competent to TWIs (The Welding exceeded. In such cases, it is unlikely
Institutes) Certification Scheme for that a deferral could be justified. be tested on a regular basis. All tests
Welding and Inspection, or should be formally documented.
equivalent. Failure of either a top or bottom floor
in double-bottomed tanks (as Pontoons should be included in
External inspections should be detected through the failure of formal maintenance and inspection
conducted on a higher frequency vacuum between plates) should be regimes as loss of pontoons (as a
than internal inspections based upon rectified within one year. Continued result of corrosion or long-term
RBI (Risk Based Inspection) operation in the interim period removal of pontoon cap) will affect
requirements, or as stated in the pending repair should be supported the stability and buoyancy of the
relevant codes. If active degradation by a technical justification supporting deck. The presence of flammable
mechanisms are found, then more its fitness for purpose. vapours within a pontoon also
frequent inspections should be increases the risk of vapour cloud
conducted. Tank repairs and modifications are explosion (VCE) within a pontoon.
specialist activities and should only
Particular attention should be given be conducted by suitably qualified The functional integrity of overfill
to insulated storage tanks, as personnel with appropriate protection systems is critical to
corrosion under insulation, and the qualification (as specified above). ensuring primary containment.
quality of external coatings applied Overfill protection systems may be in
prior to insulation, can have a Water drains on floating roof tanks a normally dormant state without
significant effect upon tank integrity. should also be formally included in being required to operate for many
routine maintenance if normally left years. For this reason, periodic testing
Thorough internal inspection can only open, including a check that isolation is an essential element in assuring
be achieved by removing a tank from valves can be closed. The detection their continuing integrity.
service, cleaning it and then systems for hydrocarbons should also
conducting, as a minimum:

11 Atmospheric Storage Tanks


10. Leakage and Fire Detection
It should be noted that leakage, overflow and top of the seal, and not on the foam dam, where
fire detection are mitigation layers and not they are less effective in detecting fires.
preventative layers, and are therefore of
secondary priority to overflow and leak Point heat detectors are generally of less use for
protection. large storage tanks, other than in the vicinity of
vents, given the large areas that need to be
covered. Therefore, optical flame detectors,
10.1 Leak Detection providing a large zone of detection, should be
Whilst flammable gas detection in storage areas used for bunded areas.
is considered to be a good measure (for highly
flammable materials), the dispersion of
flammable vapours is complicated to predict, so
10.2 Fire Prevention and
effective gas detection may not always be Protection
practical.
Bonding & Earthing
More effective detection of leaks is likely to be
By nature of the storage of flammable liquids,
provided by liquid hydrocarbon detectors.
flammable atmospheres are to be expected in
Typical locations would be in the bund drain,
the vicinity of vents, rim seals and within the
gutter or sump, where hydrocarbons would
tanks themselves. To minimise the risk of
accumulate. Such systems may be subject to
ignition the tank and ancillary equipment should
failures or spurious alarms (e.g. due to water
be fully bonded and earthed (grounded). A
collecting in the bund), therefore consideration
maximum resistance of 10 ohms to earth is
should be given to using multiple detectors at
recommended.
more than one location. Initiation of such alarms
should also initiate an interruption of any
Special attention should be made to the
transfer operation. This is of particular
earthing connection between the tank wall and
importance at terminals that are normally
the roof of a floating roof tank. Sliding shunts
unmanned.
(contactors) between the wall and roof often do
not maintain a good contact, thus overloading
Ideally CCTV (Closed Circuit Television) should those shunts which are maintaining a
be provided, with suitable resolution and connection. Therefore, an adequate number of
lighting in tank and bund areas to give operators shunts should be provided and checked to
assistance in detecting tank overflows.
ensure that contacts are maintained.
Operators should not be expected to monitor
these constantly, therefore CCTV should be
Due to the rising and falling of the floating roof,
provided with systems that detect and respond
excess lengths of earthing cable are required in
to changes in conditions and then alert
the vicinity of the walkway providing access to
operators to those changes.
the floating roof. The earthing cable can often be
severed when it is trapped between the wheels
Fire Detection of the access walkway and the rails upon which
it rolls, as in example shown overleaf.
For floating roof tanks, rim seals should be Retractable grounding systems on modern
constantly monitored by the use of linear heat tanks would address this.
detection. These should be located close to the

Marsh 12
Damaged Earthing Cable

One of the most common sources of ignition for Often, foam is applied to provide a blanket to
large tanks is lightning. Therefore, the provision suppress vapour emissions and prevent ignition.
of suitable lightning protection with bonding However, if this occurs on tanks storing
and earthing would help to minimise this. NFPA materials, such as naphtha, that are susceptible
780 Standard for the Installation of Lightning to ignition from splash-filling, careful
Protection Systems provides more details on the consideration should be given prior to the
specification of lightning protection systems. application of foam. If foam is to be applied, for
example in the event that electrical storms are
Some installations are provided with lightning expected, then this should be gently applied
masts intended to act as preferential routes for along the shell wall and not by splash-filling to
lightning to discharge itself, as opposed to via the surface of the material.
the storage tank. This concept is not proven and
some parties suggest that such masts act to
attract lightning to the vicinity of the storage
Zoning
tanks. Therefore, these are not currently A detailed assessment of the hazardous area
considered to be a robust mitigation against the classification (HAC) of the storage tank, ancillary
effects of lightning. equipment and bunded area must be
conducted. This should take into account the
Some materials are susceptible to the effects of class of material being stored.
static during splash-filling. Therefore, measures
should be taken in such instances to prevent the The specification of spark-inducing equipment
generation of electrostatic charges. should be suitable for the HAC zones location
and should be made in accordance with relevant
It is possible that floating roofs can become electrical standards, such as IP (Institute of
unstable and sink, maybe as a result of rainwater Petroleum) Model Code of Safe Practice Part 15,
accumulation, or failure of flotation devices. ATEX 95, ATEX 137 or BS 5345.

13 Atmospheric Storage Tanks


11. Fire Fighting Systems
Protection systems and fixed fire this position paper to detail may result in the destabilisation and
fighting installations should be emergency plans, but API 2021, sinking of the roof.
provided and comprise fixed/semi- Management of Atmospheric Storage
fixed foam systems and cooling water Tank Fires, provides some guidance in
sprays. Additionally, access to the this matter. 11.2 Foam Fire
tanks for mobile fire fighting Fighting Systems
appliances, equipment and materials Emergency response personnel
should be provided giving multiple Whilst being a good cooling medium
should receive training on the fire
points of attack with no dead-ends. for tanks, water is not a suitable fire
preplans, and regular exercises
extinguishing medium for
should be conducted to assess the
hydrocarbon fires. Therefore, foam is
In many cases it is safer and more suitability of the preplan.
used for such applications. The
practical to allow a tank fire to burn
design of foam fire-fighting systems,
itself out; for instance, when there is
no chance of escalation to other 11.1 Water Systems be they fixed or mobile, should be
suitable for the types of fires they
tanks, little environmental exposure
Provision should be made for the would be required to extinguish (or
or where the risks of fighting the tank
application of cooling water to fixed suitable for the cooling of adjacent
fire are greater than not fighting it.
roof tanks containing products equipment/tanks). Therefore each
Two notable exceptions are:
adjacent to those containing Class I or facility needs to have its own tailored
II (petroleum) or wherever there is fire fighting system. Important issues
Rim seal fires these will take a
less than 1 x diameter of the largest to consider when designing and
long time to burn out
tank between adjacent tanks. In installing a fire fighting system
Crude tank fires these are particular, there should be cooling include:
susceptible to boilovers due to the wherever there is less than 15 metres
presence of water access between tanks. Foam and the foam injection/
proportioning systems must be
Broad principles of water and foam Where water is to be applied to tanks, compatible (also important if the
application are given below. More water application rates should be: supplier of foam is changed)
details are given in the Energy
Institutes Model Code of Safe 2 lpm/m for exposed tanks Hydraulic design of foam systems
Practice Part 19: Fire precautions at must be specified
petroleum refineries and bulk storage 10 lpm/m for engulfed tanks (to
vertical and inclined surfaces) Foam selection must be
installations. Alternatively, NFPA 11 appropriate for the type of fire likely
Standard for Low-, Medium-, and e.g. AFFF, (Aqueous Film Forming
Source: IP 19. Model Code of Safe Practice
High-Expansion Foam can be used as Foam), should not be selected for
Part 19
a reference. polar solvents
Water application should be provided Correct proportioning of foam that
As for process plant, dedicated fire-
by either fixed or semi-fixed systems. may otherwise result in foam that
preplans should also be compiled for
It is unlikely that mobile tenders does not flow (too little water) or
storage installations. These should
would have sufficient capacity for that quickly goes back to solution
specify type of attack, firewater and
water storage to mount a prolonged (too much water)
foam application rates, location of
cooling water attack on a storage
hydrants, semi-fixed installations and
tank. Provision of facilities to aid the
mobile apparatus, firewater
maintenance or testing of
containment and worst case
Water should not be applied to the firefighting systems
scenarios. It is not within the remit of
roof area of floating roof tanks as this

Marsh 14
Location of equipment, e.g. Additionally, remote monitors are correctly, although if there are
monitors not too far from tanks for wasteful of foam and cannot direct changes to the foam type, foam
foam application to tank surface the jet so accurately as the objective proportion or even water supply,
is to apply foam to the rim seal as then the flow characteristics could
Attention to any faults in the quickly and gently as possible be affected so that a foam seal is
fabrication and installation of (irrespective of the roof level) and to not possible.
hardware, e.g. check valves retain a complete foam seal for as
installed the wrong way round, long as possible. Forced/irregular addition of foam.
transport packing still present The intention is to apply foam
around air inductors gently down the side of the tank
The most common and (arguably)
shell so that it forms an even
most effective method to control a
Once a system has been designed blanket within the rim seal area. If
rim seal fire is the application of foam
and installed, it is critical that it is the pourer has been incorrectly
via fixed rim seal pourers on the top of
tested. Whilst this may be expensive, positioned it may not apply the
the shell wall. Even with simple, fixed
it is critical to ensure that the system foam in such a way, e.g. catching
purpose-built systems, such as rim
actually completes the job it is on the top edge of the seal,
seal pourers, there is the danger that
intended to do. Ideally, systems resulting in splashing and loss of
basic errors can be made so that the
should be tested at the manufacturers foam to the roof.
system does not operate as intended.
as it is then cheaper, quicker and
Such examples that should be Foam pourers located too high on
easier to rectify any mistakes.
avoided are: the tank, exposing them to wind
and impairing their passage to the
Floating Roof Tank Fires Top of foam dam below the top of rim seal itself.
the rim seal this is especially an
Rim seal fires are the most common issue where secondary rim seals To overcome these issues, tests
type of fire on floating roof tanks. have been added to the tank to should be conducted on the system
There is little chance of these reduce tank emissions. The top of to ensure it operates correctly.
escalating to other tanks or turning to the foam dam should be at least 50 Depending upon the number of tanks
full surface tank fires if the design, mm above the top of the rim seal, being protected, annual testing
maintenance and layout of the tanks but ideally about 150 mm. frequency would be appropriate.
is suitable. This should not be
considered a rule, however, as a Too many or too large gaps at the
bottom of the foam dam. The Inspections should be conducted
poorly maintained tank could lose its
purpose of the dam is to hold the regularly to ensure air inlets to foam
integrity or be vulnerable to
foam in position around the generators are clear and that foam
subsequent explosions, perhaps as a
circumference of the tank to reduce pourers are not blocked by, for
result of vapour ingress into one of
the amount of foam needed. This example, birds nests. Other good
the pontoons.
ensures efficient application to the features to aid inspection or fire
rim seal and prevents unnecessary fighting in the event of a system
Rim seal protection should only be
loads being placed on the tank roof. failure are:
used on certain types of roofs (i.e.
double deck, steel pontoon, etc). Pan With large gaps at the bottom of
Walkway around the top of the
roofs for example, should have full the dam, a significant quantity of
floating roof tank this can be the
surface protection. foam could leak to the roof.
wind girder with a handrail around
However, small, intermittently
the circumference. This allows for
The application of foam from a remote spaced drains should be provided
the pourers to be accessed for
monitor (i.e. one outside the bund) to allow rainwater to drain away.
maintenance or for fire fighters to
would not represent best practice as Incorrect spacing of the foam access the roof with manual hoses.
it can create roof instability and pourers. Modern foams can flow in
potentially escalate the incident. excess of 30 metres if proportioned

15 Atmospheric Storage Tanks


Provide a foam hydrant at the top from low level through the tank itself
of the tank (preferably at the top of via a coflexip flexible pipe.
the stairs) for fire fighters in the
event of rim seal pourers becoming One shot systems an extinguishing
blocked. This also requires less agent (such as obsolete Halon) is
equipment to be carried up the applied at the rim seal in a single
tank in the event of a rim seal fire. burst extinguishing the flames. Whilst
Careful consideration needs to be potentially effective as an initial
given as to the safety of personnel extinguisher, these do not prevent
when attempting such a tactic. re-ignition and require all the parts,
including cylinders, being placed on
It is important that foam can be
the roof. For that reason, Marsh does
applied equally well when the
not recommend such an approach.
floating roof is at high level and
when it is at low level.
Fixed roof tanks
Other foam delivery systems that are
more complex to varying degrees are: Similar systems can be applied to
fixed roof tanks, with foam
Catenary systems foam applied to application to the surface of the
the rim seal by local generators product through a fixed or semi-fixed
located directly within the foam dam system, or even sub-surface allowing
through a supply line attached to the for the foam to float to the surface of
the product. NFPA 11 Standard for Example of sub-surface foam application
roof via the rolling ladder apparatus
Low-, Medium-, and High-Expansion
Foam provides a guide as to which
Coflexip system foam solution is
products and materials can be
applied in the same way as a catenary,
protected by such systems.
although the supply pipe runs up

11.3 Application Type Rate Source: Energy Institutes Model Code


(l/min/m2) of Safe Practice Part 19: Fire
Rates Applied with mobile precautions at petroleum refineries and
equipment bulk storage installations
A minimum of 40 minutes attack
should be envisaged in order to have Pool fires 5-10*
*The higher rate may be applied to Class I
a reasonable chance of success in Fixed roof tanks, Class I 5-10* products, including gasoline containing up to
product 10% of oxygenates.
extinguishing a fire, and foam stocks
Fixed roof tanks, Class II/III 5
should be sufficient for this duration; product
a duration of 60 minutes is preferred Applied with fixed or
for crude oil tank fires. semi-fixed equipment NFPA 11, Standard for Low-,
Fixed roof tank with pourer 4 Medium-, and High-Expansion Foam
Typical application rates for foam outlet also provides similar application
solution are shown below, although Base injection (oils only) 4 rates, although there are some minor
foam manufacturers advice on the Floating roof rim seal fires 12 differences.
type of foam and application should Floating roof tanks (roof area), 6.5
projected foam
always be sought:
Floating roof tanks (roof area), 4
fixed pourers

Marsh 16
12. References to Industry Losses
Examples of Industry losses have been included in Appendix C.

13. References to Industry standards


Model Code of Safe Practice Part 19: PPG 18. Planning Policy Guidance 18: Safety and environmental standards
Fire precautions at petroleum Enforcing Planning Control. for fuel storage sites. December 2009.
refineries and bulk storage December 1991. ISBN Process Safety Leadership Group.
installations. Energy Institute, 9780117525542.
February 2007. ISBN 978-0-85293- http://www.hse.gov.uk/comah/
437-1. HSG 244. Remotely Operated Shutoff buncefield/fuel-storage-sites.pdf
Valves (ROSOVs) for Emergency
BS EN 14015. Specification for the Isolation of Hazardous Substances - EEMUA PUB N 159 - Users guide to
design and manufacture of site built, Guidance on Good Practice. October the inspection, maintenance and
vertical, cylindrical, flat-bottomed, 2004. ISBN 0717628035. repair of above ground vertical
above ground, welded, steel tanks for cylindrical steel storage tanks.
the storage of liquids at ambient API 650. Addendum 3 - Welded Steel January 2003. Engineering
temperature and above. February Tanks for Oil Storage. October 2003. Equipment and Materials Users
2005. American Petroleum Institute. Association.

BS EN 61511-1:2004/IEC 61511- API 653. Tank Inspection, Repair, EEMUA PUB N 183 - Guide for the
1:2003 Functional safety. Safety Alteration, and Reconstruction, Third Prevention of Bottom Leakage from
instrumented systems for the process Edition. December 2001. American Vertical, Cylindrical, Steel Storage
industry sector. Petroleum Institute. Tanks. January 2004. Engineering
Equipment and Materials Users
BS EN ISO 10497:2004. Testing of API 2000. Venting Atmospheric and Association.
valves. Fire type-testing Low-pressure Storage Tanks, Sixth
requirements. British Standard/ Edition. November 2009. American RR760 - Mechanical integrity
European Standard/International Petroleum Institute. management of bulk storage tanks.
Organisation for Standardisation. HSE.
API RP 2350. Overfill Protection for
HSG 176. The storage of flammable Storage Tanks in Petroleum Facilities, http://www.hse.gov.uk/research/
liquids in tanks. HSE. ISBN 0 7176 Third Edition. January 2005. rrpdf/rr760.pdf
1470 0.
NFPA 11 Standard for Low-, Medium-, Note: RR760 provides a summary of
CIRIA Report 164: Design of and High-Expansion Foam, 2010 relevant codes and standards for the
Containment Systems for the Edition. assurance of mechanical integrity in
Prevention of Water Pollution from storage tanks. These provide an
Industrial Accidents. January 1997. Buncefield. The Final Report of the assessment of the most appropriate
Construction Industry Research and Final Investigation Board. December standards for different elements of
Information Association. ISBN 2008. Buncefield Major Incident maintenance and design of facilities.
086017476X. Investigation Board. http://www.
buncefieldinvestigation.gov.uk/
reports/index.htm#final

17 Atmospheric Storage Tanks


Marsh 18
14. Appendices
Appendix A - Assessment Checklist
The following checklist is based on a very good rated atmospheric storage tank facility and can be
used to assess the quality of that facility and identify any gaps or areas for improvement.

Element/feature Criteria

Containment All tanks separately bunded and sized for 110% of capacity. Bund walls sized and
designed to contain and prevent bund overtopping (may include tertiary containment).

Layout/Spacing Meets risk-based tank spacing evaluation and risk evaluation available.
Non-crude inter tank spacing equal to or greater than one diameter of largest tank and at
least 15 metres. Crude oil tanks separated by five tank diameters to prevent risk from
boilover.

Instrumentation HLA, HHLA (totally independent includes tappings, transmitters, etc.) linked to automatic
shutdown of feed. Temperature indicator. LLA, LLLA (independent) linked to automatic
shutdown of pump out and complete with on-line diagnostic capability (i.e. not simple
switch). Shutdown system and components SIL rated in accordance with application and
location. All indicators to control room. Continuous mass balance system for tank farm.
Online blending.

Construction Double welded seals on floating roof. Weather shield. Concrete base with impervious
membrane and sides sloped away from base weld. Anti rotation device on floaters.
Earthing, lightning conductors. Good access to pontoons, and handrails on access walk
way around periphery. Auto bottom water drain. Tank floor leak detection with double
floor.
Roof drainage: rainwater receptors and spill over connections to product (limits water
level to 10).

Selection As appropriate to class of product.

Drainage of Bunds Grading to pump pit sump. Impermeable bund material.

Equipment and Pipework Buried common inlet/outlet pipework and no equipment within bund area.

Bund Construction and Condition No penetrations or gaps in the walls. Any gaps in bund walls should be sealed
appropriately with a fireproof material. Concrete faced earth wall. Consideration given to
preventing bund overtopping.

Gas Detection Bunds fitted with flammable gas detectors for low flash point materials capable of
sustaining a VCE. Detectors interlocked with tank filling system to interrupt transfer.

Fire Detection Linear Heat Detection or fusible-link/ tube (for rim seals only). Systems are self
monitoring with status indication to HMI (Human/Machine Interface).

Fixed Fire Protection Multi-head foam pourers with foam dam for all tanks. Shell cooling water spray, or use of
- Floating Roof multiple monitors with proof of response capability. Supply from two separate locations.
Foam for bunded area. Fixed system supplies foam.
Fixed radiant protection on exposed walls.

Fixed Fire Protection Subsurface foam injection (for non-polar compounds, otherwise foam chambers). Roof
- Cone Roof and shell cooling. Foam for bunded area - dual supply. Fixed systems.

Fixed Fire Protection Foam pourers. Roof and shell cooling; bund protection with foam - dual supply. Fixed
- Cone roof with internal floater system.

19 Atmospheric Storage Tanks


Appendix B - Mechanical
Component Checklist for
Floating Roof Tank
Inspections

Cleanliness
Debris on roof?
Ponding or rainwater on roof?

Leakage
Signs of oil or holes on roof?

Roof Drains
Clogging of roof drain screen mesh?

PV Vent Mesh
Clogging of PV vent mesh?

Emergency Roof Drain


Clogging of emergency drain mesh?

Weather Shields/Seals
Damage or corrosion?
Excessive gaps between seal and shell?

Pontoon Compartments
Presence of water or oil?
Covers tight?

Earthing Cable
Damage on cable or connections?

Guide Poles
Damage on guide pole rollers?

Rolling Ladder
Damage on wheel?

Roof Drain Valves


Ease of movement?

Bottom of Shell
Water pooling?
Corrosion?
Vegetation?

Marsh 20
Appendix C - Loss Incidents
The application of the measures specified in this document should minimise the risk
of a major accident occurring at a storage facility or individual storage tank.

The table below gives some examples of incidents that have resulted in loss of
containment to illustrate that they should not be considered as rare events. Data has
been compiled by a reputable operator in the USA that indicates that overfilling
occurs once every 3,300 filling operations.

Location Date Fuel released Consequence


Jacksonville, 1993 Unleaded petrol/ 190 m3 released. The spill ignited, leading to a
Florida, USA gasoline major explosion and fire.
Coryton, UK 1997 Unleaded petrol/ 81 m3 released. Spill contained within bund
gasoline no ignition.
Belgium 2001 Hexene Approximately 90m3 released. Spill contained
within bund no ignition.
Sour Lake, Texas, 2003 Crude oil 80 m3 released. Spill contained within bund
USA no ignition.
Torrance, 2004 Jet fuel Approximately 10m3 released. Spill contained
California, USA within bund no fire or explosion.
Bayonne, New 2004 Fuel oil 825 m3 released. Oil contained on tank farm.
Jersey, USA no fire or explosion.
Casper, 2004 Unleaded petrol/ Up to 1270 m3 released. Spill contained within
Wyoming, USA gasoline bund no ignition.
Rensselaer, NY, 2005 Unleaded petrol/ 0.4-4 m3 released. Spill contained within bund
USA gasoline no ignition.

Location Date Fuel released Cause Consequence


Fawley, UK 1999 Crude oil (400 Corrosion of tank base No injuries or off-site effects. All
tonnes) of the oil was recovered from
primary containment.
Milford 2005 Kerosene (653 Leak from damaged No injuries, but nearby gardens,
Haven, UK tonnes) sump escaped through farmland, and stream
permeable floor of contaminated. All wildlife killed in
bund stream.
Antwerp, 2005 Crude oil Catastrophic failure of Overtopping of the bund wall
Belgium (26,000 tonnes) storage tank as a result occurred due to sudden release.
of corrosion
Plymouth 2005 Kerosene Corrosion of the tank No injuries. Kerosene entered
Harbour, (tonnage base and a permeable into the ground.
UK uncertain) bund base
Coryton, 2006 Gas oil (121 Tank overfilled, oil No injuries or harm to the
UK tonnes) escaped from bund by environment.
defective drain valve
Poole 2006 Diesel oil (19 Diesel escaped through No injuries. Pollution of ground
Harbour, tonnes) damaged base plate but not of the harbour.
UK and through cracks in
concrete bund floor

21 Atmospheric Storage Tanks


Incidents with similarities with the Buncefield incident of 2005 are summarised below.

Location Date and time Comments background Comments explosion


Houston, Texas, April 1962 Severe leak from gasoline tank. Almost windless Described as a blast, but no details are available.
USA conditions. Ignition near adjacent highway.
Baytown, Texas, 27 January 1977 Overfilling of a ship with gasoline. Few details are available, but it is likely that there
USA would have been congestion.
Texaco, Newark, 7 January 1983 Overfilling of a tank containing unleaded gasoline. Relatively uncongested area. High overpressure
New Jersey, USA After 00.00 hrs 114-379 m3 (80-265 tonnes) of gasoline released. reported but not quantified. Three minor explosions
Slight wind, ignition source 300m away. preceded the main blast.
Naples Harbour, 21 December Overfilling of a tank containing unleaded gasoline. Relatively congested area. The tank overtopped 1.5
Italy 1985 700 tonnes escaped. Low wind speed (2 m/s). hours before ignition. Various overpressures
estimated from damage analysis but they are
minimum values (e.g. 48 kPa).
St Herblain, 7 October 1991 Leak of gasoline from a transfer line into a bund. Presence of parked petrol tankers may have been
France 04:00 hours Wind <1 m/s. 20 minutes delay, ignition in car park sufficient to generate turbulence. High overpressures
c. 50 m away. Volume of flammable cloud est produced but not quantified.
23,000m3.
Jacksonville, 2 January 1993 Overfilling of a tank containing unleaded gasoline. High overpressure produced but not quantified.
Florida, USA 03:15 hours 50,000 gallons (190m3, 132 tonnes) released.
Laem Chabang, 2 December 1999 Overfilling of a gasoline tank. Few details. High overpressure produced but not quantified.
Thailand 23:25 hours Relatively low congestions in the area.

Below are statistics on the frequency of incidents taken from the LASTFIRE project, a group of operating companies
sharing information on the prevention and protection of fires in large atmospheric storage tanks. This data is valid up to
2006 and should not be seen as comprehensive.

Spills and Initial Fire Events


Loss of Containment Initial Fire Event
Onto Roof Sunken Into Bund Rim Seal Small Large Spill on Full
Roof Bund Bund Roof Surface
N of Incidents 55 37 96 55 3 2 1 1
Frequency (x10-3/ 1.6 1.1 2.8 1.6 0.09 0.06 0.03 0.03
tank year)

Rim seal Fire Frequency by Region


Country/Region Nigeria Southern Northern North Venezuela Thailand Singapore Saudi
Europe Europe America Arabia
N of Fires 7 13 15 9 2 3 2 1
Tank Years 333 6,247 15,264 4,611 159 224 1,035 3,392
Frequency (x10-3/tank year) 21 2 1 2 13 13 2 0.3
Thunderstorm days/year 160 30 20 40 60 70 120 10

Full Surface Fire Analysis


One escalation in 55 rim seal fires (roof pontoons contained flammable vapour and/or liquid)

One escalation in two bund fires impinging on tank shell

One escalation from a spill fire on a roof

One full surface fire in 37 sunken roof incidents

Escalation to two downwind tanks in one full surface fire (volatile fuel)

One boilover in six full surface fires NB of the six fires, one was a crude tank which resulted in a boilover. It should
always be assumed that a crude tank full surface fire will boilover

Marsh 22
The Engineering Services team
Marshs Risk Engineering Services risk, assessed against peer plants
team has been established for over world-wide.
25 years and is uniquely qualified
to provide risk managers and From the earliest planning stage to
underwriters with the essential the last operational phase, the
information they need to engineering services team is able
determine the right limit and to contribute practical and
scope of cover and the right price. cost-effective advice and
assistance.
Each member of the team is a
qualified engineer, with practical In addition to tailored
experience in design, programmes, the team has a series
construction, operation and of core packages, covering
maintenance across a broad range everything from managing a major
of oil, gas and petrochemical risks. emergency to risk reduction
design features and safe working
They have all been trained in practices.
advanced insurance skills, in the
ability to assess and analyse risk The Engineering Services team is
and to communicate effectively unmatched among insurance
and frequently in more than one brokers and risk advisers because
language. of the scale of investment, the
breadth of expertise and the
The goal is to build bridges experience it incorporates.
between risk engineering,
insurance and risk management More importantly, the team uses
and between the client and the its practical knowledge and
underwriter. At the same time, the practical skills to communicate a
comparative skills of the team real understanding of physical
permit a benchmarking system risks, their insurance implications
which gives a global opinion of the and the commercial operating
environment.

23 Atmospheric Storage Tanks


Marsh 24
For further information, please
contact your local Marsh office or visit
our web site at: marsh.com

Beijing London Oslo


Tel: +86 10 6533 4070 Tel: +44 (0)20 7357 1000 Tel: +47 22 01 10 00
Fax: +86 10 8529 8761 Fax: +44 (0)20 7929 2705 Fax: +47 22 01 10 90

Calgary Madrid Perth


Tel: +1 403 290 7900 Tel: +34 914 569 400 Tel: +61 8 9289 3888
Fax: +1 403 261 9882 Fax: +34 913 025 500 Fax: +61 8 9289 3880

Cape Town Moscow RIO DE JANEIRO


Tel: +27 21 403 1940 Tel: +7 495 787 7070 Tel: +55 21 2141 1650
Fax: +27 21 419 3867 Fax: +7 495 787 7071 Fax: +55 21 2141 1604
Dubai Mumbai San Francisco
Tel: +971 4 223 7700 Tel: +91 226 651 2900 Tel: +1 415 743 8000
Fax: +971 4 227 2020 Fax: +91 225 651 2901 Fax: +1 415 743 8080
Houston New York Singapore
Tel: +1 713 276 8000 Tel: +1 212 345 6000 Tel: +65 6327 3150
Fax: +1 713 276 8888 Fax: +1 212 345 4853 Fax: +65 6327 8845

Marsh is one of the Marsh & McLennan Companies, together with Guy
Carpenter, Mercer, and Oliver Wyman.
The information contained herein is based on sources we believe
reliable and should be understood to be general risk management
and insurance information only. The information is not
intended to be taken as advice with respect to any
individual situation and cannot be relied upon as such.
In the United Kingdom, Marsh Ltd. is authorised
and regulated by the Financial Services
Authority for insurance mediation
activities only.
Copyright 2011 Marsh Ltd.
All rights reserved.

You might also like